Sei sulla pagina 1di 46

Eni S.p.A.

Divisione Exploration & Production

GENERAL SPECIFICATION

PROGRAM OF CHECKS AND TESTS FOR


ELECTRICAL INSTALLATIONS

05221.VAR.ELE.SPC
Rev. 6
March 2010

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 2 di 46

FOREWORD
Rev. 1

Total number of pages 28


June 1988

Rev. 2

Total number of pages 20


August 1997
Computerized issue

Rev. 3

Total number of pages 21


July 2003
Issue for normative references revision and contents conformity

Rev. 4

Total number of pages 59


December 2004
General revision

Rev. 5

Total number of pages 59


October 2006
Revised pt. 6.14.2. for compliance to IEC 60364-6

Rev. 6

Total number of pages 46


March 2010
General Revision

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 3 di 46

Eni S.p.A.
Exploration & Production Division

INDEX
1.
1.1

SCOPE OF PROGRAM........................................................................................................................ 5
Normative References................................................................................................................... 5

2.

DEFINITION OF TERMS ...................................................................................................................... 6

3.

PROGRAM DEFINITION CRITERIA.................................................................................................... 7

3.1
3.2
3.3
4.
4.1
4.2
4.3
5.
5.1
6.
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
6.10
6.11
6.12
6.13
6.14
6.15
6.16
6.17
6.18
6.19
6.20
6.21
7.
7.1
7.2
7.3

Checking of materials before installation ................................................................................... 7


Mechanical Completion ................................................................................................................ 7
Pre-commissioning ....................................................................................................................... 8
DUTIES AND RESPONSIBILITIES ..................................................................................................... 9
Inspector......................................................................................................................................... 9
Scheduling and procedures ......................................................................................................... 9
Contractor's duties........................................................................................................................ 9
CHECK AND TEST RESULTS .......................................................................................................... 10
Documentation ............................................................................................................................ 10
MECHANICAL COMPLETION REQUIREMENTS ............................................................................ 10
General ......................................................................................................................................... 10
Conduct of Tests ......................................................................................................................... 10
Safety ............................................................................................................................................ 11
Generators ................................................................................................................................... 12
Power Transformers ................................................................................................................... 13
Neutral earthing resistors........................................................................................................... 14
MV & LV Motors .......................................................................................................................... 15
MV & LV Switchgear and Bus-bar.............................................................................................. 16
MV Power Cables......................................................................................................................... 19
L.V. Power & Control Cables...................................................................................................... 20
DC Supply System: UPS, Battery Charger and Batteries........................................................ 21
Lighting & Small Power Distribution System ........................................................................... 22
Navigation AIDS........................................................................................................................... 23
Earthing ........................................................................................................................................ 24
Electrical Heaters ........................................................................................................................ 26
Electrical Equipment & Device (Local Panel - Push Button - Power Socket) ....................... 26
Junction Box ................................................................................................................................ 27
Electrical substations, HV switchyards, telephone exchanges, battery
rooms, etc .................................................................................................................................... 28
Chatodic protection system. ...................................................................................................... 29
Cable tray & rack. ........................................................................................................................ 30
Apparatus for Use in Hazardous Areas .................................................................................... 30
PRE-COMMISSIONING REQUIREMENTS ....................................................................................... 33
General ......................................................................................................................................... 33
Conduct of Tests ......................................................................................................................... 33
Safety ............................................................................................................................................ 33
Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

7.4
7.5
7.6
7.7
7.8
7.9
7.10
7.11
7.12

8.
8.1
8.2
8.3
9

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 4 di 46

Generators ................................................................................................................................... 34
Power Transformers ................................................................................................................... 35
Neutral earthing resistors........................................................................................................... 36
MV & LV Motors ........................................................................................................................... 37
MV & LV Switchgear and Bus-bars ........................................................................................... 38
DC Supply System UPS & Battery Charger and Batteries ................................................... 41
Lighting & Small Power Distribution System ........................................................................... 41
Navigation AIDS........................................................................................................................... 42
Electrical Equipment & Device (Heater, Panel, Junction Box, Push-Button
Station, Socket) ........................................................................................................................... 43
REFERENCE DOCUMENTS ............................................................................................................. 44
Specification, Standards and Codes ......................................................................................... 44
Electrical Mechanical Completion Check Lists........................................................................ 44
Electrical Pre-Commissioning Record Sheet ........................................................................... 45
METHOD OF COMPANY STANDARS REQUEST / INFORMATIONS ............................................ 46

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

1.

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 5 di 46

SCOPE OF PROGRAM
The program defines checks and tests to be carried out on individual materials and
electrical system during installation or on completion.
Checks and tests aim at determining any abnormalities that may have occurred
during transport, installation and assembly and at establishing the efficiency of
systems and circuits and feasibility of components.
These checks and tests do not aim at repeating inspections carried out at the
supplier's premises and, therefore, at verifying the performance and correct
construction of materials.

1.1

Normative References
All systems, equipment and materials shall be in accordance with regulations in force
in the country where they must be installed.
The rules applicable standards ENI are listed in the specification of Company:
-

List applicable regulatory standards at the time of electrical 20138.DOC.ELE.ELN

Of that specific company, the Contract / Supplier will have to verify the validity of
each rule (latest edition available) and also will check for the issuance of new
regulations which follow

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

2.

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 6 di 46

DEFINITION OF TERMS
The following words and expressions shall have the meanings hereby assigned to
them:
- "COMPANY" (or Employer) shall mean the name of Company who has called for
Tenders to provide and execute the works and who will employ the CONTRACTOR
and the legal successors in title to the Employer but not (except with the consent of
the CONTRACTOR) any assignee of the Employer;
- CONTRACTOR" means the person or persons, firm or company whose tender has
been accepted by the Employer and includes the Contractors personnel
representatives, successor and permitted assignees subject to Employer consent;
- INSPECTION AUTHORITY, i.e. the organization nominated by COMPANY to
supervise checks and tests.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

3.

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 7 di 46

PROGRAM DEFINITION CRITERIA


The program described on the following pages takes into account the Client's
requirements and has been defined considering that every check and test has a
specific intrinsic value with regard to data or characteristics to be established.
However, this value varies depending on the role played by the system, circuit or
component to which it applies and this role is linked to implications concerning
malfunction and safety of personnel and equipment.
Therefore, depending on the importance of the circuit, checks and tests may be
carried out only on a sample of identical or similar circuit components (e.g. motor
starters).
The program has been prepared by subdividing checks and tests as follows:
3.1

Checking of materials before installation


Before being installed, materials must undergo a "visual examination" to determine
any damage or breakage to prevent the installation of materials that will require
replacement at a later stage.
This check will, generally, be carried out at the warehouse.
However, for some materials which must be transported to the place of installation in
their packing (e.g. panels) it can be carried out on site.
Note: In doubtful cases instrument checks and/or tests can be carried out.

3.2

Mechanical Completion
Mechanical Completion is defined as that point in the project when work to install,
erect and fit out the facilities has been completed, and that fitting out work has been
tested.
Eg. Electric cables will have been installed, terminated, continuity and insulation
resistance tested but not energised. Motors will similarly have been checked out but
not run.
Checks and tests must be carried out during construction or when systems or a
constituent part of them are mechanically completed to ensure that the equipment
and individual components are installed in accordance with design requirements,
suppliers' instructions, technical codes and accident prevention codes and that there
is no obvious damage or breakage.
Mechanical equipment will be installed, aligned and fitted with any temporary devices
(strainers, etc.) required for commissioning. Initial fill of lubricants, etc., will be made.
Mechanical completion will be done on a methodical system by system basis, and
checks will be documented and compiled in a similar manner.
In the case of areas with potentially explosive atmospheres, checks must be carried
out to ensure that the whole system and individual components are installed in
compliance with appropriate codes.
More particularly, checks and tests listed below must be carried out.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 8 di 46

In the case of parts of systems or materials which are not indicated below, checks
and tests must be carried out by analogy with those of materials indicated and in
accordance with the supplier's instructions.
3.3

Pre-commissioning
Pre-commissioning is defined as the activities following Mechanical Completion
carried out to facilitate safe and efficient commissioning of a system.
Eg. Electrical switchgear relays will be tested and settings verified. Motors will be run
for 30 minutes without load (uncoupled). Cables will be energised as required.
Mechanical equipment will be prepared for operation by testing and running
auxiliaries, by checking trips and other functions. Seal oil and lube oil systems will be
flushed.
These checks and tests must be carried out during construction or on completion
and, in any case, before commissioning in order to:
a) determine any abnormalities that may have arisen during installation;
b) ensure the efficiency of systems and circuits;
c) ensure that components operate under safe conditions.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

4.

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 9 di 46

DUTIES AND RESPONSIBILITIES


Duties and responsibilities relevant to checks and tests are as indicated in "Data
Sheet for duties ant responsibilities of checks and tests of electrical installations"
(MOD.ELE.FTC.001).
The following prescriptions shall also apply:
4.1

Inspector
Tests and/or checks outlined with code (P) on Data Sheet for duties and
responsibilities entrusted to qualified engineer who will be responsible for the
organization of checks and tests and whose instructions must be complied with by all
persons for whatever reasons they may be present.
The above engineer is the "Inspector" and must therefore sign all documents
associated with checks and tests.

4.2

Scheduling and procedures


The Company shall agree with the Contractor on the schedule and procedures for
the execution of checks ant tests.

4.3

Contractor's duties
All duties connected with the Contractor's responsibilities shall be at his own
expenses (e.g. labour equipment, instruments, documentation, etc.).

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

5.

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 10 di 46

CHECK AND TEST RESULTS

5.1

Documentation
Results of tests mentioned in paragraph 3.1 need not be recorded.
Results of checks and tests mentioned in paragraphs 3.2 and 3.3 must be recorded
on appropriate documents which must be attached to this PROGRAM so as to have
complete and exhaustive file on the subject.
For further information see the following chapter 8.

6.

MECHANICAL COMPLETION REQUIREMENTS


6.1

General
The main scope of Mechanical Completion inspections and tests is to ensure
conformity with the project specifications and drawings and to prove that all
equipment and materials are suited to the duties they are intended to perform.
This procedure covers the general responsibilities of the electrical contractor during
checkout of electrical equipment. Specific requirements are given for the following
types of testing:
- General checks
- Grounding system tests
- Insulation resistance tests
- Protective relay system tests
- Load tests
- Noise tests
- Temperature tests
- Vibration tests (where appropriate)
- Illumination level tests
- DC system tests
- Navigation Aids Tests
All work shall be executed in strict accordance with project specifications and the
approved drawings. The written approval of the COMPANY is required for any
deviations.

6.2

Conduct of Tests
a) The Mechanical Completion program shall demonstrate the proper installation of
the complete electrical system.
b) Checkout tests shall be witnessed by the COMPANY as required.
c) Checkout tests may be conducted concurrently with Pre-commissioning tests.
d) Complete dossier shall be submitted to the COMPANY at completion of
Mechanical Completion.
e) After the Mechanical Completion program has been completed and accepted by
the Company, the Contractor shall be responsible for maintaining the equipment
in safe and protected conditions. All covers, doors and access plates shall be
properly fastened. All wiring shall be completed..

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 11 di 46

f) It should be noted that Mechanical Completion work may be carried out on


adjacent equipment to live installations. The safety precautions listed must be
observed.
6.3

Safety
a) General Safety Precautions
The consequences of shock or burn from electrical systems are serious. Work on
electrical equipment shall, therefore, be carried out only when the equipment is
de-energised, and by qualified personnel, and who fully understand the electrical
system of the project.
One-line diagrams shall be available at all times. All feeding equipment and
circuits shall be tagged-out and locked-out. The test/check operatives own key or
lock shall form part of the lock-out procedure.
All equipment such as bus bars, circuit breakers, and motor shall be properly
grounded as appropriate before any testing or other work is initiated.
b) Equipment Isolation
All equipment shall be physically disconnected from its power source to prevent
accidental injury to personnel resulting from inadvertent re-energisation.
Equipment isolation is necessary to ensure that voltages applied to the equipment
under test are not allowed to feed-back into power transformers, generators and
associated upstream synchronising and control circuits. The consequences of
back-feeding voltages include danger to personnel and damage to equipment.
c) Medium-Voltage Testing
While any medium-voltage testing is being conducted shall be ensured that the
test area is properly guarded to prevent unauthorised entry and that DANGER
notices are posted adjacent to, and at all access ways to the test area during the
period of the test.
All cables must be discharged both before and after applying any test voltage.
Any associated cables not being tested shall be grounded during the test, e.g.,
other phase conductors of a three-phase circuit.
Temporary conductors used for test purposes shall not be sized less than the
rating of the circuit under test.
Caution notices shall be posted adjacent to, and at all access ways to the test
area.
d) Portable Electrical Equipment
Unless portable electrical equipment is double insulated or connected to ground
fault interrupters, the equipment shall be grounded using flexible supply cable that
incorporates a ground continuity conductor.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

6.4
6.4.1

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 12 di 46

Generators
Installation and Mechanical Completion
a) Ensure that the equipment meets the area classification and specification
requirements.
b) Note the nameplate ratings of the generators and compare with those given on
the approved drawings.
c) Ensure that the enclosure IP rating meets specification requirements.
d) Ensure the mechanical integrity of all components.
e) Ensure that any shaft blocking or transit packing has been removed.
f) With the coupling removed ensure that the generator rotates freely and that the
end play of the rotor is within tolerances.
g) Without dismantling, inspect as far as possible oil rings, oil levels, grease packing
and bearings. Inspect for leakage.
h) Inspect the paint finish for damage. Any damaged areas shall be repainted.
i) Inspect the earthing stud and the connection to the general earthing system,
including those in the terminal box.
j) Ensure that all terminal boxes are clean, dry and in good condition. Check that all
spare entries are plugged.
k) Check that cables are properly terminated, connected and supported, that the
terminated box layout is satisfactory and that any current transformers are
securely installed.
l)

Check that terminal boxes are properly phase segregated, where applicable.

m) Ensure that anti-condensation heaters are correctly installed and terminated.


n) Ensure that all vibration and temperature monitoring equipment is properly
installed (if fitted).
o) Ensure that internal are free from dust, debris, etc.
p) Ensure that the installation and fixing of equipment is correct (level, alignment,
etc).
q) Ensure that gaskets and seals are correctly installed and are in good condition.
r) Ensure that the conductors are correctly connected to terminals (also in order to
the direction of rotation) and that the insulation distance to earth is appropriate.
s) Ensure that drains are correctly installed and effective;
t) Ensure that there are not obvious damages to mounted instruments.
u) Ensure that the air filters are correctly installed and clean.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 13 di 46

v) Ensure that the brushes, when existing, are transversally staggered on the
surface of the rings without, however, being in contact with ring corners so that
they do not splinter. The distance between brushes and ring surface is that
anticipated by the manufacturer and the inclination, if any, is correct, i.e. opposite
to the direction of rotation.
Brushes move freely, there is even contact with rings and the brush spring
pressure is that specified by the manufacturer. Braided brush leads do not touch
the brush gear
w) Check that all mounting and holding down bolts are secure.
6.4.2

Test Certificates
a) Installation and Mechanical Completion shall be recorded on Check List CL-E001
(MOD.ELE.FTC.002).

6.5
6.5.1

Power Transformers
Installation and Mechanical Completion Checks
a) Ensure that the equipment meets the area classification and specification
requirements.
b) Note the nameplate ratings of the generators and compare with those given on
the approved drawings.
c) Ensure that the enclosure IP rating meets specification requirements.
d) Ensure the mechanical integrity of all components.
e) Inspect the paint finish for damage. Any damaged areas shall be repainted.
f) Ensure that the transformer is complete with all accessories and instruments.
g) Ensure that there are not obvious damages to transformers, accessories and
instruments.
h) Ensure that the oil level (or other dielectric liquid) in the conservator corresponds
to the level prescribed with regard to the oil temperature read on the dial
thermometer. If the level is too low add new oil; if the conservator is fitted with a
water collecting trap, drain it using the drain valve Only for oil transformer.
i) Ensure that air bubbles have been evacuated by opening and closing appropriate
breather plugs in the tank, radiators and insulators Only for oil transformer.
j)

Ensure that the thermometer bulb tube is full of oil Only for oil transformer.

k) Ensure that the oil level in the air dryer sump corresponds to that marked Only
for oil transformer.
l)

Ensure that silica gel (silicon oxide) of the air dryer is dry (if blue: dry; if purple:
20-30% humidity; if pink: damp-saturated). It can be regenerated by removing the
dryer with the air intake pipe blocked: the silica gel must then be spread on to a
metal sheet and heated to 180-200C until it turns blue. Before turning down the
dryer to remove the silica gel, the oil sump at the bottom of the container must be
unscrewed Only for oil transformer.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 14 di 46

m) Inspect tap change mechanism.


n) Ensure that the pressure valve or bursting disk are not blocked in the "closed"
position and can operate freely Only for oil transformer.
o) Ensure that the level of the compound or oil in the cable terminal box corresponds
to that prescribed Only for oil transformer.
p) Ensure that insulators are clean.
q) Inspect the earthing stud and the connection to the general earthing system,
including those in the terminal box.
r) Check that cables or bus-bars are properly terminated, connected and supported;
s) Ensure that all terminal boxes are clean, dry and in good condition. Check that all
spare entries are plugged.
t) Ensure that internal are free from dust, debris, etc.
u) Ensure that bus-bar or cable terminal protection boxes are well closed.
v) Ensure that there are not loose or missing screws or nuts. Accessories are well
fixed.
w) Ensure that rollers on rails are chocked.
y) Ensure that gaskets and seals are correctly installed and are in good condition.
x) Ensure that neutral connections are secure.
z) Ensure that the padlocking facilities are satisfactory.
a1) Ensure that enclosures suitable for protection against adverse weather conditions
and sun are securely installed.
a2)Ensure that warning labels (high voltage, high temperature, etc) are properly
installed.
a3)Inspect the transformer and auxiliary equipment for alignment and tightness of
foundation bolts and fixings in general.
6.5.2

Test Certificates
a) Installation and Mechanical Completion shall be recorded on Check List CL-E002
(MOD.ELE.FTC.003).

6.6
6.6.1

Neutral earthing resistors


Installation and Mechanical Completion
a) Ensure that the equipment meets the area classification and specification
requirements.
b) Note the nameplate ratings of the neutral earth resistors (NER's) and compare
with the approved drawings.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 15 di 46

c) Ensure removal of any temporary weatherproofing and any drying agents (e.g.
silica-gel).
d) Inspect the neutral earthing resistors for alignment, tightness of foundation, bolts
and fixings.
e) Inspect the connections to the neutral earthing resistor.
f) Inspect the frame earthing arrangement.
g) Ensure all cable supports and glanding are satisfactory.
h) Ensure all terminations are satisfactory.
i) Ensure that all gaskets are installed correctly.
j) Ensure that the internals of the NER are free from dust and debris.
k) Ensure warning labels for sudden high temperature in the event of operation
are in place.
6.6.2

Test Certificates
a) Installation and Mechanical Completion shall be recorded on Check List
E017 (MOD.ELE.FTC.030).

6.7
6.7.1

CL-

MV & LV Motors
Installation and Mechanical Completion
a) Ensure that the equipment meets the area classification and specification
requirements.
b) Note the nameplate ratings of the motors and compare with those given on the
approved drawings.
c) Ensure that the enclosure IP rating meets specification requirements.
d) Ensure the mechanical integrity of all components.
e) Ensure that any shaft blocking or transit packing has been removed.
f) With the coupling removed ensure that the motor rotates freely and that the end
play of the rotor is within tolerances.
g) Without dismantling, inspect as far as possible oil rings, oil levels, grease packing
and bearings. Inspect for leakage.
h) Inspect the paint finish for damage. Any damaged areas shall be repainted.
i) Inspect the earthing stud and the connection to the general earthing system,
including those in the terminal box.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 16 di 46

j) Ensure that all terminal boxes are clean, dry and in good condition. Check that all
spare entries are plugged. In addition, for MV motors check that terminations are
satisfactory.
k) Check that cables are properly terminated, connected and supported.
l)

Ensure that anti-condensation heaters are correctly installed and terminated.

m) Ensure that all vibration and temperature monitoring equipment is properly


installed (if fitted).
n) Ensure that internal are free from dust, debris, etc.
o) Ensure that the installation and fixing of equipment is correct (level, alignment,
etc).
p) Ensure that gaskets and seals are correctly installed and are in good condition.
q) Ensure that the conductors are correctly connected to terminals (also in order to
the direction of rotation).
r) Check that all mounting and holding down bolts are secure.
6.7.2

Test Certificates
a) Installation and Mechanical Completion shall be recorded on Check List CL-E003
(MOD.ELE.FTC.004).

6.8
6.8.1

MV & LV Switchgear and Bus-bar


Installation Completion
a) Ensure that the equipment meets the area classification and specification
requirements.
b) Note the nameplate ratings of the equipment and compare with those given on
the approved drawings.
c) Ensure that the enclosure IP rating meets specification requirements.
d) Inspect the switchboard assembly for alignment, level, tightness of foundation
bolts and fixing in general. Ensure that circuit breaker trucks can be easily
manoeuvred in and out of their cubicles - applicable to all withdrawable
equipment.
e) Compare the switchgear equipment with the Equipment Schedule, paying
particular attention to the rating and any circuit changes.
f) Inspect the switchboard earth bar and earth cable for electrical and mechanical
continuity.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 17 di 46

g) Ensure that all panel doors and gland plates are bonded to the switchboard
structure and that non-magnetic gland plates are fitted to single core cables.
h) Ensure that all equipment installed in the switchboard is in good condition,
particularly bus-bar insulation and bracing and joint insulation.
i)

Inspect bus duct connections.

j) Inspect the inside of the switchgear for cleanliness, paying particular attention to
the insulators.
k) Ensure that all equipment (i.e. circuit breakers, contactors, fuse, switches,
voltmeter, ammeter, protection relay, overload relay, current transformer, etc.)
are in good condition and in particularly meet the drawings, data sheet and
specification requirements.
l) Ensure that there are not obvious damages to equipment and instruments.
m) Ensure that the mechanical operation of equipment, in particular circuit-breakers
and operating devices, is correct. In order to verify this, the circuit-breaker
mechanisms and springs, if any, must be operated, mechanical locks must be
checked and, if the breaker is withdraw able, and this operation should also be
checked.
n) Ensure that switchboards and equipment are securely fixed to supports.
o) Ensure that doors and panels close properly and there are keys for all locks.
p) Ensure that holes that are not used but are planned for future equipment or
instruments are correctly plugged.
q) Ensure that switchboards installed outdoors are protected against adverse
weather conditions and sun with suitable canopy.
r) Ensure that warning labels, fitted by the manufacturer for special indications, are
intact.
6.8.2

Mechanical Completion Certification Testing


a) Prior to securely fitting the bus-bar covers, check the tightness of bus-bar joint
bolts, measure the insulation resistance of the bus-bar. Ensure that cable and/or
bus ducts are certified.
b) Test the switchboard earth system for electrical and mechanical continuity.
measure the earth path resistance at the earth bar to the general earth system.
c) Measure the insulation resistance of the bus-bar and control wiring after ensuring
any sensitive equipment has been disconnected and also ensuring control wiring
is not subjected to bus-bar test voltages. This test should be carried out prior to
and immediately after the pressure test and before energizing the switchboard.
The minimum acceptable resistance, together with the relevant test voltage, is
given in the table below.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 18 di 46

Eni S.p.A.
Exploration & Production Division

SWITCHGEAR
VOLTAGE
(V)

TEST
VOLTAGE
(V)

MIN INSULATION
RESISTANCE
(M)

- Up to 1 kV

1000 Vdc

10

- Up to 4.6 kV

2500 Vdc

150

- Above 4.6 kV

5000 Vdc

200

d) A DC high voltage test (pressure test) on both the main and auxiliary circuits shall
be carried out between phases and phase-to-earth. The following conditions
must be adhered to for the tests:
(i)

All current transformers secondaries will be short-circuited for the test.

(ii)

All voltage transformers shall be disconnected by removal of primary and


secondary fuses for the duration of the test.

(iii) One pole of the testing supply shall be connected to earth and to frame of the
assembly for the phase to earth test.
DC TEST VOLTAGE
(FOR 1 MINUTE)
(kV)

MAX SYSTEM VOLTAGE


(kV)
- Up to 1

1,5

- 3.6

10 (*)

- 7.2

20 (*)

- 12

28 (*)

- 17.5

38 (*)

- 24

50 (*)

- 36

70 (*)
(*): or as recommended
by Manufacturer

e) Upon completion of testing, reconnect all cables and function test the circuit to
ensure all links and fuses are replaced.
6.8.3

Test Certificates
a) Installation Completion and Mechanical Completion shall be recorded on form
CL-E004 (MOD.ELE.FTC.005).
b) All originals of test certificates generated by supplier must be attached to form
CL-E004 (MOD.ELE.FTC.005) for inclusion in the system test dossier.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 19 di 46

Eni S.p.A.
Exploration & Production Division

6.9
6.9.1

MV Power Cables
Installation Completion
a) Check that the cable installation is as per project specification and drawings.
b) Ensure that the gland certificates meet the Area Classification and Specification
requirements.
c) Inspect the cable glands for tightness and good workmanship. Ensure that the
correct type of gland has been used for the size and type of cable installed.
d) Where conductors have been terminated using crimped connections, ensure that
the correct size and type of crimping lug bas been used.
e) Inspection the earth connections.

6.9.2

Additional Installation Completion Checks (MV Cables)


a) Ensure that cables have been glanded in accordance with Supplier's instructions.
b) Check that any incorporated stress relief measures and termination kits are
satisfactory.
c) Ensure that the minimum cable bending radius has not been exceeded.

6.9.3

Mechanical Completion Certification Testing


Before any cables are tested, all cleaning, supports, etc. shall be completed.
Intermediate insulation resistance tests will be carried out before cleaning. Before
making any measurements, the Inspector shall ensure that both ends of the cable
have been disconnected and are clean of any metal and that core continuity of
jointed cables is correct.
a) Measure the insulation resistance of the cable and record on the relevant test
certificate. The table below gives the test voltages and minimum acceptance
values of insulation resistance. Where necessary, measure the conductivity of
the earth conductor.
For all multicore cables, insulation resistance should be measured core-to-core,
core-to-earth and screen-to-armour. Record only the lowest figure obtained.

CABLE OPERATING
VOLTAGE
(V)

TEST VOLTAGE

U0 /U

(*)

For cable length above 1 km =

(V)
5000

INSULATION
RESISTANCE
(M)
(MINIMUM)
200 (*)

200
Cable lenght (Km)

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 20 di 46

Eni S.p.A.
Exploration & Production Division

6.9.4

Additional Mechanical Completion Certification Testing (M.V. Cables)


a) Apply a DC test voltage (pressure test) as per IEC code & regulations between
the conductors of each high voltage cable and the copper tape screen of each
conductor, also between each conductor and earth.
Record test voltage and duration of test measure and record any leakage
current.
Each cable shall be discharged after the above tests and the conductors earthed
until the cable is out into service. The test voltage and duration are as tabulated
below:

CABLE OPERATING
VOLTAGE
(V)
U0 /U

BETWEEN
CONDUCTORS
(V)
4 U0

BETWEEN
CONDUCTORS
AND EARTH
(V)
4 U0

TIME
(min)
15

b) As an alternative, and by agreement between the contractor and purchaser, an


a.c. voltage test at power frequency, in accordance with the following points b1
and b2, can be used:
b1) Test for 5 min with the phase-to-phase voltage of the system applied
between the conductor and the metallic screen;
b2) Test for 24 hours with the normal operating voltage of the system;
Note: that the tests above mentioned are for new installations only; electrical tests
on repaired installations are subject to installation requirements.
6.9.5

Test Certificates
-

6.10
6.10.1

MV cable check sheets and test certificates are for individual cables.
Mechanical completion certification testing of the M.V. cables shall be recorded
on forms CL-E005 and CL-E006 (MOD.ELE.FTC.006 and 007).

L.V. Power & Control Cables


Installation Completion
a) Check that cable installation is as per project specifications and drawings.
b) Ensure that the gland certificates meet the Area Classification and Specification
requirements.
c) Inspect the cable glands for tightness and good workmanship. Ensure that the
correct type of gland has been used for the size and type of cable installed and
that, where specified, insulating gland adapters have been installed. Particular
attentions should be paid to barrier glands.
d) Where conductors have been terminated using crimped connections, ensure that
the correct size and type of crimping lug has been used.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 21 di 46

Eni S.p.A.
Exploration & Production Division

6.10.2

Mechanical Completion Certification Testing


Before any cables are tested, all cleaning, supports, etc. shall be completed.
Intermediate insulation resistance tests will be carried out before cleaning. Before
making any measurements, the Inspectors should ensure that both ends of the cable
have been disconnected and are clear of any metal and that core continuity of
jointed cables is correct.
a) Measure the insulation resistance of the cable and record on the relevant test
certificate. The table below gives the test voltages and minimum acceptance
values of insulation resistance. Where necessary, measure the conductivity of
the earth conductor.
For all multicore cables, insulation resistance shall be measured core-to-core, coreto-earth and screen-to-armour. Record only the lowest figure obtained.

CABLE OPERATING
VOLTAGE
(V)
500
600 / 1000

6.10.3

TEST VOLTAGE
(V)

500
1000

INSULATION
RESISTANCE
(M)
(MINIMUM)
1
10

Test Certificates
Installation Completion and Mechanical Completion certification testing of cables
shall be recorded on Forms CL-E006 (MOD.ELE.FTC.007).

6.11
6.11.1

DC Supply System: UPS, Battery Charger and Batteries


Installation Completion
a) Note the nameplate rating of the equipment and number, type and rating of
batteries supplied. Compare with the ratings stated on the approved drawings for
the equipment.
b) Ensure that the equipment certificates meet the Area Classification and
Specification Requirements.
c) Inspect the chargers and battery stands for alignment, level and tightness of
foundation bolts and fixing.
d) Inspect the earthing bolts and connections to the earth system, where applicable.
e) Check cleanliness. Where necessary clean the interiors of all control panels,
chargers, etc. Remove any temporary silica-gel drying agents from the panels.
f) Note the type, size and rating of all fuses and protective devices and compare
with the values stated on the approved drawings.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 22 di 46

g) Inspect all batteries for cracks, damage, tightness and cleanliness of terminals
and connections.
h) Remove any transit bungs and store for possible future use.
i) Inspect all bolted connections between individual cells in a bank of batteries.
Ensure that all battery terminals have been coated with vaseline or equivalent.
j)

Inspect battery circuit breakers.

k) Where batteries and battery chargers are housed in the same cubicle or suite of
cubicles, check the integrity of the gas tight seal between the compartments.
l) Ensure that there is not leakage of the electrolyte.
m) Ensure that connections between cells and blocks are such as to prevent any
short circuit.
n) Ensure that connections from batteries to switchboards are well installed and
suitably marked.
o) Ensure that warning labels, fitted by the manufacturer for special indications, are
intact.
6.11.2

Mechanical Completion Certification Testing


a) Ensure that all cables have been certified.
b) Measure the earth path resistance at the main earthing terminal. Note that
special care must be taken when making tests on electronic equipment due to its
susceptibility to damage by over voltage.

6.11.3

Test Certificates
a) Installation Completion and Mechanical Completion shall be recorded on forms
CL-E007 and CL-E008 (MOD.ELE.FTC.008 and 009).

6.12
6.12.1

Lighting & Small Power Distribution System


Installation Completion
a) Ensure that the equipment meets the Area Classification and Specification
requirements as laid down in the Design Specification and drawings.
b) Note the distribution board circuit numbering and the fuse rating of the circuits
and compare with the approved drawings. Verify the operation of any safety
features, such as interlocks, padlocks and door switches.
c) Note the location of the lighting fittings, sockets, etc. and compare with the
approved drawings. Lighting equipment is correctly located and is no obstructed
by pipes or other plant component thereby preventing the illumination of the
areas
d) Inspect the earthing bus-bar and cable earthing connections inside the
distribution boards and the earthing connections from individual items of
equipment to the earthing grid where detailed on drawing refer to the
earthing/bonding procedure.
e) Inspect lighting fittings, sockets and switches for neatness, weatherproofing,
glanding, internal connections, general good workmanship and labelling.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 23 di 46

f) All equipment in hazardous areas should be inspected in accordance with the


requirements of the procedure for the apparatus for use in hazardous areas.
g) Carry out inspection of junction boxes in accordance with the junction box
inspection procedure.
h) Ensure that the circuits are correctly marked.
i) Ensure that the safety lighting system is installed as per the design project.
j) Ensure that glass and guards of lighting equipment are no broken.
k) Ensure that local lighting panels are suitably welded to the support structure. The
mechanical operation of circuit-breakers is satisfactory.
l) Ensure that protection against corrosion has been provided and is complete or
made good where necessary.
m) Ensure that poles and floodlights are complete with accessories and are earthed.
n) Ensure that road lighting equipment and floodlights are correctly orientated.
6.12.2

Mechanical Completion Certification Testing


a) Confirm that all cable certification is complete, including supply cable to
distribution boards.
b) Measure insulation resistance of distribution board phases to ground.
c) Measure each distribution board and sub-circuit insulation resistance to earth.
d) Check the earth continuity of each outgoing circuit.
e) Check the operation of MCCB, ESD and RCD isolation, where applicable, on
each circuit.
f) Check that each circuit is correct to latest drawing revision.
g) As each sub-circuit from a distribution board is inspected, complete an inspection
tag and attach it to the sub-circuit control switch in a prominent position.

6.12.3

Test Certificates
a) Installation Completion and Mechanical Completion shall be recorded on form
CL-E009 (MOD.ELE.FTC.010).

6.13
6.13.1

Navigation AIDS
Installation and Mechanical Completion
a) Check that the equipment certification meets the Area Classification and
Specification requirements.
b) Note the nameplate rating of the supplied equipment and compare this rating with
that on the approved drawings.
c) Inspect the installation of equipment for alignment, level and tightness of
foundation bolts and fixings.
d) Ensure that the insides of any control panels, etc, have been cleaned out.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 24 di 46

e) Inspect the earthing arrangements, including earthing connections, inside the


connection boxes.
f) Inspect the paint finish, paying particular attention to externally located
equipment. Any damaged areas shall be made good.
g) Inspect the weatherproofing and bolting of the connection boxes.
Weatherproofing should not be dependent upon the application of paint, tape or
plastic compounds.
h) Ensure that the appropriate requirements of the procedure for the apparatus for
use in Hazardous areas are carried out, if applicable.
i) Note the size, type and rating of all fuses and protective devices. Compare with
the values stated on the approved drawings.
6.13.2

Test Certificates
a) Installation Completion and Mechanical Completion shall be recorded on form
CL-E010 (MOD.ELE.FTC.011).

6.14
6.14.1

Earthing
Installation Completion
a) Compare the earth connection type and size with the Schedule.
b) Where conductors have been terminated using crimped connections, ensure that
the correct size and type of crimping lug has been used.
c) Ensure all connections are tight and greased.
d) In the case of instrument earths, refer to installation specification.
e) Ensure that buried conductors and earth rods are located in accordance with the
design.
f) Ensure that conductors installed without protection are sheathed (yellow/green).
g) Ensure that the continuity of the protective conductors (PE), equipotential
conductors and other conductors which form part of the earthing system has
been verified.
h) Ensure that conductors rising from the floor or ground are protected by means of
a conduit section.
i) Ensure that buried joints of conductors are protected against damp with a
bitumen or similar mixture.
j) Ensure that earthing and equipotential connections are provided for machines,
panels, equipment, components and structures, including those outside the
electrical installation, as anticipated in the design and in accordance with
reference codes.
k) Ensure that down conductors and other apparatus relevant to lightning protection
system comply with the design.
l)

Ensure that transformer neutrals are correctly earthed.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 25 di 46

m) Ensure that earthing of concrete reinforcing bars has been carried out, if required
by the design.
n) Ensure that terminals and earth bus-bars are correctly installed.
o) Ensure that protective conductors (PE) and earthing conductors are sized in
relation to the design and are correctly fixed and protected.
p) Ensure that metal sheaths and cable armouring are earthed.
q) Ensure that protection against corrosion has been provided and is complete or
made good where necessary.
6.14.2

Mechanical Completion Certification Testing


a) Measurement of grounding grid resistance (RE):
-

The measurements shall be carried out before the start-up of the plant and
subsequently with a periodicity dictated by regulations.

b) Measurement of step and touch voltages (US and UT):


The measurement of step and touch voltages is not necessary if the ground
potential rise (UE: maximum electrical potential that a grounding grid may attain
relative to a distant grounding point assumed to be at the potential or remote
earth. This voltage (GPR) is equal to the maximum grid current (IE) times the
grounding grid resistance (RE)), measured and/or calculated, does not exceed
the maximum allowable values of step and touch voltages;
c) Measurement of earth fault loop impedance (ZS):
The measurement of earth fault loop impedance shall be taken into account in
TN systems. The measurements aim to establish if the protection device against
indirect contacts (carried out by means of automatic breaking of the circuit),
operates correctly.
The relationship to be met is the following:
ZS(m) 2/3*U0/Ia
Where:
-

ZS(m): measured impedance of fault loop ();


U0: rated voltage between the system phase and earth (V);
Ia: verified and recorded current causing the tripping of the protection device
within the times indicated in the applicable standards (A);

The situations that can occur are the following:


-

The protection device is a residual current relay: the relationship is always


respected;
The protection device are fuses, circuit-breaker or other overcurrent
protection devices: the relationship should be verified;

When the above mentioned relationship is not verified, it is necessary to proceed


by:
- increasing the cross section of phase conductor and protective conductor (PE);
- replacing, if possible, the protection device (circuit-breaker, overcurrent release
of circuit-breaker, fuses, etc);
- inserting a residual current protection device;

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

6.14.3

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 26 di 46

Mechanical Completion Certification Testing and Test Certificate


a) Installation Completion and Mechanical Completion shall be recorded on form
CL-E011 (MOD.ELE.FTC.012).
Tests shall be recorded on form MOD-ELE-FTC-015 and 016.

6.15
6.15.1

Electrical Heaters
Installation Completion
a) Ensure that the equipment meets the Area Classification and Specification
requirements.
b) Ensure that the equipment identification is correctly shown.
c) Ensure that the heater is free from damage and the paintwork is correct.
d) Ensure that the cables are supported correctly, glands are made off correctly and
spare entries are plugged.
e) Ensure that flanges are undamaged and that seals and gaskets are correctly
fitted.
f) Inspect the earthing for mechanical and electrical continuity. Refer to
earthing/bonding procedure.
g) Inspect the terminal box of the heater for neatness of connections and general
good workmanship.
h) All equipment in hazardous areas should be inspected in accordance with the
requirements of the procedure for the apparatus for use in hazardous areas.

6.15.2

Mechanical Completion certification testing


a) Confirm all cable certification is complete.
b) Measure insulation resistance of heater.
c) Check the earth continuity of the heater.

6.15.3

Test Certificates
a) Installation Completion and Mechanical Completion shall be recorded on
form CL-E012 (MOD.ELE.FTC.013).

6.16
6.16.1

Electrical Equipment & Device (Local Panel - Push Button - Power Socket)
Installation and Mechanical Completion
a) Ensure that the equipment meets the area classification and specification
requirements.
b) Note the nameplate of the devices and compare with those given on the
approved drawings.
c) Ensure that the enclosure IP rating meets specification requirements.
d) Inspect for correct alignment, level, tightness of foundation bolts and fixing in
general.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 27 di 46

e) Ensure that the equipment is free from damage and that the paintwork is correct.
f) Ensure that cables are supported correctly, glands are installed correctly, spare
entries are plugged, flanges are undamaged and seals and gaskets are correctly
fitted.
g) Ensure that all panel doors and gland plates are bonded to the panel structure.
h) Inspect the earthing for mechanical and electrical continuity. Refer to earth
procedure.
i)

Ensure that all terminal shrouds are correctly fitted.

j) Ensure that all ferrules and crimps are correct and that all internal wiring is neatly
fitted.
l)

Inspect the inside of the panel for cleanliness.

m) Ensure that door locking arrangements are correct.


n) Ensure that access is satisfactory.
o) All equipment in hazardous areas should be inspected in accordance with the
requirements of the relevant procedure.
p) Ensure that all equipment is securely fixed to the ground (if applicable).
q) Ensure that the base-plate is correctly executed (if applicable).
r) Ensure that the position is as specified in the design.
s) Ensure that covers have been installed as indicated in the drawings.
t) Ensure that there are not obvious damages to switches and they operate
correctly.
u) Ensure that instrument glasses and warning lamp covers are not broken.
v) Ensure that warning lamp covers are of the correct colour.
w) Ensure that boxes are complete with all bolts and are securely closed.
x) Ensure that plugs fit properly and mechanical interlocks operate correctly
6.16.2

Test Certificates
a) Installation Completion and Mechanical Completion shall be recorded on forms
CL-E013 (MOD.ELE.FTC.014).

6.17
6.17.1

Junction Box
Installation and Mechanical Completion
a) Ensure that the equipment meets the area classification and specification
requirements.
b) Note the nameplate of the devices and compare with those given on the
approved drawings.
c) Ensure that the enclosure IP rating meets specification requirements.
d) Ensure that the junction box location is correct.
e) Ensure that the junction box is adequately supported and identified.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 28 di 46

f) Ensure that the terminal type, size, fixing and identification are correct.
g) Ensure that the earthing, internal and external, is correct.
h) Ensure that the glands and accessories are correctly fitted and that unused cable
entries are plugged.
i)

Ensure that grease and gaskets are correctly installed, as required.

j)

Ensure that the box is correctly sealed.

k) For hazardous area installation, procedure for apparatus for use in hazardous
areas must be followed.
6.17.2

Test Certificates
a) There are no specific standard forms for recording that the requirements of this
procedure
have
been
implemented,
however,
form
CL-E013
(MOD.ELE.FTC.014) may require endorsement to show that the requirements of
these procedures have been complied with.

6.18
6.18.1

Electrical substations, HV switchyards, telephone exchanges, battery rooms, etc


Installation Completion
a) Ensure that doors and hatches close properly, are provided with keys and, from
the inside, can be opened using the handle or crash-bar only as anticipated in the
design.
b) Ensure that fencing and boundary limits for keeping persons away from
equipment installed outdoors (e.g. transformers) are correctly installed.
c) Ensure that glass panels are not broken.
d) Ensure that ventilation openings are not blocked off and are fitted with gratings
and insect nets.
e) Ensure that the artificial ventilation system in the panel room and/or battery room
operates correctly.
f) Ensure that the layout of panels and equipment meets requirements as regards
working and safety space, as anticipated in the design.
g) Ensure that all parts of civil works are complete and comply with the design. The
floor slope is correct and the drain pit is clean.
h) Ensure that the floor and walls of the battery room are coated and/or painted with
acid-resistant paint (where necessary). The floor slope is correct and the drain pit
is clean. The floor is fitted with insulating footboards.
i) Ensure that the lighting system and socket outlets are correctly executed.
j) Ensure that the earthing system is complete.
k) Ensure that the floor is fitted with insulating footboards, where necessary.
l) Ensure that canopies are installed on transformers if anticipated in the design.
m) Ensure that fencing and boundary limits for keeping unauthorized persons away
are correctly installed and connected to the earthing system (where necessary).

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 29 di 46

n) Ensure that protection against corrosion is provided and is complete or made


good where necessary.
o) Ensure that rooms are clean.
p) Ensure that warning labels are fixed to access doors, fencing of transformer
bays, battery room door, etc.
q) Ensure that a set of electrical diagrams is available for whoever must operate the
electrical plant. The one line diagram is correctly displayed and updated.
r)

Ensure that first-aid equipment and fire-extinguishers are suitably positioned and
available for whoever must operate and maintain the plant. Selectors with
automatic extinction prearrangement and relevant signalling are correctly
installed and operative.

s) Ensure that energy tripping pushbutton, if any, is operative and clearly identified.
6.18.2

Mechanical Completion Certification Testing


a) Installation Completion and Mechanical Completion shall be recorded on
form CL-E014 (MOD.ELE.FTC.017).

6.19
6.19.1

Chatodic protection system.


Installation Completion
a) Ensure that control panels are clean and there are no foreign bodies or dust in
them.
b) Ensure that there is no obvious damage to mounted instruments and equipment.
c) Ensure that protection devices are set in accordance with the design value.
d) Ensure that doors close properly and are supplied with keys.
e) Ensure that cables and conductors are correctly installed. Conductors of the
protection circuit are correctly connected.
f) Ensure that holes which are not used but which are anticipated for future
equipment and cable inlets are plugged.
g) Ensure that measuring points are correctly positioned in accordance with design
and properly installed.
h) Ensure that measuring points are correctly numbered.
i) Ensure that characteristics of the anodes and reference electrodes for the
measurements are as anticipated in the design.
j)

Ensure that the number and location, both plan and depth-wise, of the anodes
and reference electrode are as indicated in the design.

k) Ensure that characteristics of the anodic bed (material surrounding the anodes)
are as laid down in the design.
l)

Ensure that the ground of the anode has been compacted and is not subject to
future settlement.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 30 di 46

m) Ensure that passive protections against corrosion are provided; these are in
complete execution and do not present faults when restored, if required (painting,
thermoplastic sheaths).
n) Ensure that dielectric joints are correctly positioned and are adequate for the
utilization (operating temperature, isolating and conducting fluids etc.)
o) Ensure that the field connections are properly executed, the connections through
bolts and brazing are protected against corrosion (stainless steel bolts,
bituminous or thermoplastic insulations for buried joints).
p) Ensure that the current absorbed by the protection system is compatible with that
of project design in relation to the adopted protection system: CV constant
potential supply constant current CC CV constant potential with base current
Ib.
q) Ensure that protective overloads dischargers of insulation joints and those
towards earth are correctly positioned and adequate to the installation site.
r) Ensure that cathodic protection system does not present interferences with other
protected structures and earthing system.
6.19.2

Mechanical Completion Certification Testing


a) Installation Completion and Mechanical Completion shall be recorded on
form CL-E015 (MOD.ELE.FTC.018).

6.20
6.20.1

Cable tray & rack.


Installation Completion
a) Ensure that the equipment meets the area classification and specification
requirements, where applicable.
b) Ensure the mechanical integrity of all components.
c) Inspect the paint finish for damage. Any damaged areas shall be repainted.
d) Inspect the equipment assembly for alignment, level, etc.
e) Inspect the earthing for mechanical and electrical continuity.

6.20.2

Mechanical Completion Certification Testing


a) Installation Completion and Mechanical Completion shall be recorded on form
CL-E016 (MOD.ELE.FTC.019).

6.21
6.21.1

Apparatus for Use in Hazardous Areas


Installation Completion
The following is a general inspection guide for all types of equipment used in
hazardous areas or specified accordingly and installed in non-hazardous areas.
The particular requirements for special equipment used in these locations will be
listed individually and should be read in conjunction with hazardous area
classification data sheet.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 31 di 46

a) Ensure that the apparatus is appropriate to the area classification, the surface
temperature class is correct, the apparatus group is correct and that any special
conditions on the certificate have been followed.
b) Ensure that there are no unauthorised modifications and that it carries correct
circuit identification.
c) Ensure that all bolts, glands and stoppers are tight and that the condition of the
enclosure gaskets is satisfactory.
d) Inspect the interior of the equipment for dust or dirt accumulation and ensure that
all electrical connections are tight. A check should also be made that the
electrical protection is adequate for the drive rating where applicable.
e) Inspect the equipment earthing for security and tightness.
f) Ensure that there is not damage to any cables and that the equipment is
adequately protected against corrosion, weather, vibration and other adverse
factors.
g) Ensure that the lamp rating and type are correct.
h) Where guards are used, ensure that they are correctly located and that motor
fans and couplings are not rubbing.
i) The following additional checks are required on special equipment as listed
(where applicable):
(i) Ex'd', Flameproof Enclosure
Ensure that:
- Obstructions in the vicinity of the equipment do not impair the efficient
operation of the flame-path.
- All gaps are correct and free from damage, corrosion, dirt and paint.
- The machined surface may be protected with one of the approved greases.
- All conduit runs are tight and free from corrosion.
(ii) Ex'e', Increased Safety
- A seal must be provided between the gland and the enclosure by means of a
sealing washer.
- Unused cable entries should be closed with plugs to maintain as a minimum,
the same IP rating as the enclosure, using a tool for insertion and removal.
(iii) Ex'n'
- Any unused cable entries shall be closed with plugs that maintain the degree
of protection of the enclosure.
(iv) Ex'i', Intrinsically Safe
- All installation should be inspected to ensure that any cable screens are
earthed in accordance with the relevant standard drawing.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 32 di 46

- All diode safety barrier installations should be inspected to ensure that the
correct type of barriers has been fitted and that they remain firmly fixed to
the barrier earth bar.
- Boxes containing diode safety barriers and junction boxes should be
inspected to ensure that they do not contain wiring other than that specified
in the documentation for the intrinsically safe system.
-

All installations should be inspected to ensure that relays and similar devices
which act as safety barriers between circuits have not become damaged be
repeated operation or vibration in a way which reduces the segregation
afforded.
- The earth path resistance must be measured.
- Ensure Ex'i' earth system is segregated from other earthing systems.

(v) Ex'p', Pressurised or Purged


- The purge medium is from an uncontaminated source.
- Any filters are clean and accessible.
- The purge system shall be thoroughly checked to ensure that the purge
pressure, cycle times, interlocks, lock out sequence, etc. are correct.
(vi) General
The particular earthing requirements of any of the above equipment must be
clarified with reference to the specific Code of Practice for the equipment. It
is also recommended that where there is any ambiguity in the interpretation
of the requirements, reference should be made to the relevant Code of
Practice.
6.21.2

Mechanical Completion Certification Testing


The diversity of equipment and special components which are contained in a
particular type of apparatus does not permit a generalisation of the testing required
to demonstrate suitability for service in a hazardous area. Special requirements
for testing may be contained in the standard or specific Code for the equipment and
this should be compiled with prior to final energisation of the circuit.
Supplier manuals shall be examined to ensure that electrical components and
equipment have been certified in compliance with appropriate code, National
Standards and that relevant certificates are available.
Such certificates must also be examined to determine whether the validity of the
certificate is subject to specific installation instructions and further testing after
installation, e.g. testing of cables for intrinsically safe apparatus.

6.21.3

Test Certificates
There is no specific standard for recording that the requirements of the Procedure
have been implemented; forms should be used to record the results of any checking
and testing required by the Standard and Code certificate to demonstrate suitability
for use in a hazardous area.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 33 di 46

The forms, however, make reference to this Procedure and require endorsement to
signify that the equipment and the standard of installation is suitable for use in
hazardous areas.
7.
7.1

Pre-Commissioning requirements
General
This section covers the general responsibilities of the electrical contractor during
Pre-commissioning of electrical equipment.
a) All work shall be executed in strict accordance with project specifications and the
approved drawings. The written approval of the COMPANY is required for any
deviations by the CONTRACTOR from specifications.
b) The CONTRACTOR shall bring to the attention of the COMPANY any areas of
this specification which conflicts with or does not meet safe and acceptable
electrical practices.
c) The CONTRACTOR shall be responsible for the protection and security of all
equipment during all stages of checkout and commissioning.
d) The CONTRACTOR shall not perform any electrical equipment or system tests
that would either void warranties or damage equipment.

7.2

Conduct of Tests
a) Written programmers for commissioning electrical equipment shall be developed
by the CONTRACTOR.
b) The Pre-commissioning program shall detail the final tests to be conducted on all
electrical equipment after the checkout program is complete. The Precommissioning program shall demonstrate the proper operation of the complete
electrical system.
c) All checkout and Pre-commissioning may be witnessed by the COMPANY.
d) Pre-commissioning tests may be conducted concurrently with Mechanical
Completion.
e) The CONTRACTOR shall submit a full test dossier to the COMPANY at
completion of Pre- commissioning.
f) After the checkout and Pre-commissioning program has been completed and
accepted by the COMPANY, the CONTRACTOR shall be responsible for leaving
the equipment in a safe and operable condition. All covers, doors, and access
plates shall be properly fastened. All wiring shall be complete and all jumpers
used in testing shall be removed. Some items may be left energised, on
agreement with COMPANY.

7.3

Safety
a) General Safety Precautions
The consequences of shock or burn from electrical systems are serious. Work on
electrical equipment shall, therefore, be performed only when the equipment is
de-energised, and by qualified personnel, and who fully understand the electrical
system of the project.One-line diagrams shall be available at all times. All feeding
equipment and circuits shall be tagged-out and locked-out. The test/check
operatives own key or lock shall form part of the lock-out procedure.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 34 di 46

The CONTRACTOR shall be completely responsible for the safety of his own
operatives, and other personnel, at all times.
All equipment such as bus bars, circuit breakers, and motor shall be properly
grounded before any testing or other work is initiated.
b) Equipment Isolation
All equipment shall be physically disconnected from its power source to prevent
accidental injury to personnel resulting from inadvertent re-energisation.
Equipment isolation is necessary to ensure that voltages applied to the
equipment under test are not allowed to back-feed into power transformers,
generators, and associated upstream synchronizing and control circuits. The
consequences of back-feeding voltages include danger to personnel and damage
to equipment. A lock-out procedure will be developed.
c) Medium Voltage Testing
While any high or medium voltage testing is being conducted, the
CONTRACTOR shall ensure that the test area is properly guarded to prevent
unauthorized entry and that DANGER notices are posted adjacent to, and at all
access ways to the test area during the period of the test.
All cables must be discharged both before and after applying any test voltage.
Any associated cables not being tested shall be grounded during the test, e.g.,
other phase conductors of a three-phase circuit.
Temporary conductors used for test purposes shall not be sized less than the
rating of the circuit under test.
d) Portable Electrical Equipment
Unless portable electrical equipment is double insulated or connected to ground
fault interrupters, the equipment shall be grounded using flexible supply cable
that incorporates a ground continuity conductor.
7.4
7.4.1

Generators
Pre-Commissioning Certification Testing
a) Check that all factory checks and tests have been completed as par specification
requirement.
b) Check that all original of suppliers checks list and test records are available.
c) Ensure that all cables and/or bus ducts have been certified in accordance with
the Cable and/or bus ducts Test Procedures.
d) Verify that incoming circuit breaker has been tested in accordance with the
requirements of Electrical Procedure.
e) Short and earth all semi-conductors and carry out insulation resistance checks on
the exciter field. Remove shorts and earths after test.
f) Measure the status phase-to-frame insulation resistance. After separating the
windings at the star point, measure the insulation resistance between windings.
Reconnect the windings on completion of test.
g) Measure the polarization index of the generator carried out by supplier (only if
original certification records are not available from the manufacturer).
h) Measure the insulation resistance of the anti-condensation heater.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 35 di 46

Eni S.p.A.
Exploration & Production Division

i) Remove earth strap on driven end of generator and measure non-driven end
bearing pedestal insulation. Replace driven end earth strap on completion of test.
j) Test the circuit continuity of temperature protection devices. Insulation resistance
tests shall not be carried out on thermistors.
k) Confirm that torque of generator lubrication and cooling systems are operational.
l)

Confirm that generator lubrication and cooling systems are operational

m) Ensure that all protection and metering has been tested in accordance with the
requirements of the specification and relevant procedures.
7.4.2

Test Certificates
a) Pre-commissioning certification testing shall be recorded on Form RS-E001
(MOD.ELE.FTC.020).
b) Any certificates generated by the requirements of electrical procedures (i.e.
protection relay etc.) shall be attached to Form RS-E001 (MOD.ELE.FTC.020) for
inclusion in the system test dossier.
c) Supplier test sheets shall be attached to Form RS-E001 (MOD.ELE.FTC.020) for
inclusion in the system test dossier.

7.5
7.5.1

Power Transformers
Pre-Commissioning Certification Testing
a) Check that all factory checks and tests have been completed as par specification
requirement.
b) Check that all original of suppliers checks list and test records are available.
c) Test the alarm and trip circuits.
d) Ensure that all cables have been certified in accordance the relevant procedures.
e) Ensure adequate separation distances on high voltage cable connection
chamber and terminations are as per Supplier's drawing.
f) Inspect tightness of bus-bar connections plus bracing from secondary winding to
bus-bars of switchgear.
g) Measure the phase-to-phase and phase-to-earth insulation resistance for
auxiliary circuits and both the MV and LV windings. The table below gives the test
voltages and minimum acceptable values of insulation resistance.
TRANSFORMER
WINDING
VOLTAGE
(V)

TEST
VOLTAGE
(V)

MIN INSULATION
RESISTANCE
(M)

- Up to 1 kV

1000 Vdc

10

- Up to 4.6 kV

2500 Vdc

150

- Above 4.6 kV

5000 Vdc

200

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 36 di 46

Eni S.p.A.
Exploration & Production Division

h) Carry out a power frequency voltage (pressure test) between the MV and LV
windings. The test should be carried out for one minute between each winding
with the core and tank earthed.
Alternatively, a dc pressure test may be applied. Duration of this test shall be
fifteen
(15) minutes.
The test voltages to be applied are given in the table below.
TRANSFORMER
WINDING
VOLTAGE
(V)

TEST
VOLTAGE
AC
(V)

MIN INSULATION
RESISTANCE
(M)

5000

10000

Note: Hi-pot test shall be carried out by supplier (only if original


certification records are not available from the manufacturer).
i) Carry out the required testing of any protection and/or meter circuitry with cables
and bus ducts disconnected and in accordance with Supplier's commissioning
instructions.
j)

Check phase rotation of transformer secondary windings.

k) Check the operation of cooling fans (if fitted).


7.5.2

Pre-Commissioning Certification Testing


a) Pre-commissioning certification testing shall be recorded on Forms RS-E002
(MOD.ELE.FTC.021).
b) All supplementary certificates should be attached to Forms RS-E002
(MOD.ELE.FTC.021) for filing in the System Test Dossier.
c) Supplier test sheets shall be attached to Form RS-E002 (MOD.ELE.FTC.021) for
inclusion in the system test dossier.

7.6
7.6.1

Neutral earthing resistors


Pre-Commissioning Certification Testing
a) Check that all factory checks and tests have been completed as par specification
requirement.
b) Check that all original of suppliers checks list and test records are available.
c) Ensure all cable certification is complete as per relevant procedures.
d) Measure the insulation resistance of
outgoing connections disconnected.
resistor with resistor in cold state.
resistance for temperature stated on
design resistance.

the resistor to earth with incoming and


Measure the value of neutral earthing
Using temperature coefficient calculate
the nameplate. Compare calculated and

e) Measure resistance of frame earth path.


Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 37 di 46

Eni S.p.A.
Exploration & Production Division

f) Test the anti-condensation heater and circuits, where fitted.


g) If current transformers have been fitted, check that Supplier test certificates and
magnetising curves are available.
h) Measure the equipment earth path resistance at the main earthing terminal to the
general earth system.
i)
7.6.2

Upon completion of tests, reconnect the incoming and outgoing cables.

Test Certificates
a) Pre-commissioning certification testing shall be recorded on Forms RS-E011
(MOD.ELE.FTC.031).
b) Any supporting current transformer certificates should be attached to the relevant
protection certificate.
c) Supplier test sheets shall be attached to Form RS-E011 (MOD.ELE.FTC.031) for
inclusion in the system test dossier.

7.7
7.7.1

MV & LV Motors
Pre-Commissioning Certification Testing
a) Check that all factory checks and tests have been completed as par specification
requirement.
b) Check that all original of suppliers checks list and test records are available.
c) Ensure that all cables have been certified in accordance with the Cable Test
Procedures. Check the phase sequence and polarity of all connections.
d) Measure the insulation resistance phase-to-phase if the windings can be
separated and phase-to-earth. If the windings require drying out, reference shall
be made to the guidance notes and typical drying out curves as detailed in
Vendor's Instructions.
MOTOR
VOLTAGE
(V)

TEST
VOLTAGE
(V)

MIN INSULATION
RESISTANCE
(M)

- Up to 1 kV

1000 Vdc

10

- Up to 4.6 kV

2500 Vdc

150

- Above 4.6 kV

5000 Vdc

200

e) Measure insulation resistance of anti-condensation heater (if fitted).


f) Check motor cooling and lubrication.
g) If special motor protection devices (e.g. thermocouples) have been fitted, test
their circuit continuity. (Insulation resistance tests should not be carried out
across thermistor terminals or thermistor control units).
h) Verify that the starter cubicle has been tested in accordance with relevant
Procedures (SWITCHGEAR).
Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 38 di 46

i) Verify that the water cooling, pressurization and purge systems have been tested
and are available (if applicable).
j) Where applicable, remove earth strap on drive end of motor and measure nondrive end pedestal bearing insulation. If satisfactory, refit drive end earth strap.
k) Confirm that torque of motor terminations conforms to Supplier's Specifications.
l) Have the coupling broken to separate the motor from the driven unit or the belts
removed from the belt-driven equipment. Ensure that the motor rotates freely and
the rotor end play is within tolerance.
m) Start the motor to determine the direction of rotation and compare this with the
required rotation of the driven unit.
n) Run the motor for about 30 minutes and check the bearings for undue
temperature rise. Check for vibration. Tabulate results after 30 minutes to confirm
temperature stabilizes. On DC motors check for armature sparking (if fitted).
o) Measure and record the line current of the free running motor (at no load).
7.7.2

Test Certificates
a) Pre-commissioning certification testing shall be recorded on Forms RS-E003
(MOD.ELE.FTC.022).
b) Supplier test sheets shall be attached to Form RS-E003 (MOD.ELE.FTC.022) for
inclusion in the system test dossier.

7.8
7.8.1

MV & LV Switchgear and Bus-bars


Pre-Commissioning Certification Testing
a) Check that all factory checks and tests have been completed as par specification
requirement.
b) Check that all original of suppliers checks list and test records are available.
c) Check for correct voltage of trip/close supplies.
d) Prove correct operation of all mechanical and electrical interlocks (incoming
feeder, outgoing feeder, all MCC cubicle, etc.).
e) Energise switchboard and check for correct bus-bar phase rotation.

7.8.2

Circuit Breakers Pre-Commissioning


a) Check that all factory checks and tests have been completed as par specification
requirement.
b) Check that all original of suppliers checks list and test records are available.
c) Ensure manual trip and close is functional.
d) Ensure electrical trip and close is functional.
e) Ensure earthing switch is functional (if fitted).
f) Ensure that the appropriate requirements of Procedure for apparatus for use in
hazardous areas have been complied with, if applicable.
g) Carry out insulation resistance tests before and after pressure test with circuit
breaker both open and closed.
h) Carry out pressure tests as detailed on relevant Procedure and Supplier's
instruction.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division
i)

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 39 di 46

Control Circuits - The following checks shall be undertaken.


Check electrical closing and tripping from the following locations:
- local to breaker;
- local station;
- remote station (discrepancy switches);
- closing from dead bar and auto synchronizer contacts;
- tripping from protection trip relay.
Check control circuit operation for closing and tripping. Where coils are short-time
rated, check the isolating contacts for operation.
Check anti-pumping circuitry on circuit-breakers to ensure non-reclosure whilst
keeping close push-button depressed.
Check breaker trip/close test facility in the isolated position.
Check alarm indications and status lamps at the following:
- local to breaker;
- local station;
- remote station.
Check circuit supervisions, i.e. closing circuit supervision for safety/energy
schemes and trip circuit supervisions for circuit-breakers and latched contactors.
Supervisory circuits are sensitive to control circuit resistances and
tripping/closing coil resistances.
When commissioning a supervisory system it is essential to ensure that
supervisory voltage drop across the supervised coil does not activate the coil.
Some iron cored coils have a very low pick up voltage i.e. 12-20V for a 110Vdc
control voltage.

j) Carry out required testing of any protection and/or meter circuitry in accordance
with Supplier's Commissioning Instructions using primary and secondary injection
methods as appropriate and if applicable.
7.8.3

Contactor Starter (MCC Cubicle) Pre-Commissioning


a) Check that all factory checks and tests have been completed as par specification
requirement.
b) Check that all original of suppliers checks list and test records are available.
c) Ensure that the requirements of Procedure for apparatus for use in hazardous
areas have been complied with, if applicable.
d) Function Check starter including remote control, annunciation and indicating
instrument.
e) Tests and records the starter insulation resistance.
f) Carry out required testing of any protection and/or meter circuitry in accordance
with the requirements of specifications and relevant procedures.
g) Setting of the thermal overboard protection relay.
h) Function check of the earth fault protection relay.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

7.8.4

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 40 di 46

Fuse Switches Pre-Commissioning


a) Check that all factory checks and tests have been completed as par specification
requirement.
b) Check that all original of suppliers checks list and test records are available.
c) Measure the insulation resistance through the closed isolator (phase to phase
and all phases to earth).
d) Carry out required testing of any protection and/or meter circuitry in accordance
with the requirements of specifications and relevant procedures.

7.8.5

Testing of Protection Circuits


The following equipments may require testing of protection and/or meter circuitry by
means of primary and/or secondary injection:
-

Switchgear & Bus-bars

Circuit Breakers

Contactor Starter

Fuse Switches

Power Transformers

Panels/Consoles

Generator

Owing to both the variety of schemes and the diverse types of relays in use, no
attempt has been made to produce a standard Testing Procedure.
The following commissioning tests must be carried out in accordance with the
relevant manufacturers commissioning documentation and with reference to the
project "Power System Design - Protection Co-ordination Study documents",
specification data sheet, etc.
1) Check that all factory checks and tests have been completed as par specification
requirement.
2) Check that all original of suppliers checks list and test records are available.
3) Individual items of protection have not been damaged by transport and
handling. This is proved by Secondary injection Tests.
4) The correct items have been connected together, e.g. the correct set of Current
Transformers have been connected to a given set of relay. This is provided by
Primary Injection Tests.
5) All connections, panel wiring and intertrips are correct. This is provided by
Function Tests.
6) The correct settings and/or adjustments have been applied according to the
requirements of the specification, data sheet and Protection Co-ordination
Study.
7.8.6

Voltmeter & Ammeter Testing


a) Check that each individual items have not been damaged by transport and
handling.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

7.8.7

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 41 di 46

Test Certificates
a) Pre-commissioning certification testing shall be recorded on Form RS-E004
(MOD.ELE.FTC.023).
b) Any certificates generated by the requirements of electrical procedures (i.e.
protection relay etc.) shall be attached to Form RS-E004 (MOD.ELE.FTC.023) for
inclusion in the system test dossier.
c) Supplier test sheets shall be attached to Form RS-E004 (MOD.ELE.FTC.023) for
inclusion in the system test dossier.

7.9
7.9.1

DC Supply System UPS & Battery Charger and Batteries


Pre-Commissioning Certification Testing
a) Check that all factory checks and tests have been completed as par specification
requirement.
b) Check that all original of suppliers checks list and test records are available.
c) Measure the voltage at the terminal of each cell and compare with the
recommended values. Record the results and ensure that a copy of the Check
List remains with the batteries.
d) When all inspection and tests have been carried out, the batteries may be given
their initial charge. This shall be carried out under the supervision of the
Supplier's representative on site. The boost and float charge rates should be
noted.
Under NO CIRCUMSTANCES WHATSOEVER are sealed cells to be boost
charged.
e) Check the operation of all alarms.
f) Measure the level of output voltage ripple on load and check in the Supplier's
data that this is within tolerance.
g) Check the operation of ESD trip and battery circuit breaker.
h) Carry out battery discharge test using a Procedure acceptable to the Supplier
and record the results, including decay graphs, on test sheets (care must be
taken not to damage batteries by excessive discharging).
i)

Switch on the inverter and record the frequency, input and output voltage and
current.

j) Transfer the load from the inverters via the static switch to mains by pass and
from mains by pass back to the inverters via the static switch.
7.9.2

Test Certificates
a) Pre-commissioning certification testing shall be recorded on Forms RSE005, RS-E006 and RS-E012 (MOD.ELE.FTC.024, 25 and 32).
b) Any certificates generated by the requirements of electrical procedures (i.e.
protection relay etc.) shall be attached to Forms RS-E005, RS-E006 and RSE012 (MOD.ELE.FTC.024, 25 and 32) for inclusion in the system test dossier.
c) Supplier test sheets shall be attached to Forms RS-E005, RS-E006 and RSE012 (MOD.ELE.FTC.024, 25 and 32) for inclusion in the system test dossier.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

7.10
7.10.1

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 42 di 46

Lighting & Small Power Distribution System


Pre-Commissioning Certification Testing
a) Test the voltage and polarity of each socket.
b) Check the operation of interlock on all sockets in hazardous areas.
c) Check the voltage drop at the further point of each circuit.
d) Carry out illumination tests. Illumination levels should comply with the
specification requirements.
e) Test the operation of emergency lighting systems, paying particular attention to
discharge times of battery-backed fittings.
f) Function check of each push-button including operation of interlock (where
applicable) and indicating lamp.

7.10.2

Test Certificates
a) Pre-commissioning certification testing shall be recorded on Form RS-E007
(MOD.ELE.FTC.026).
b) Results of illumination level checks shall be recorded on Form RS-E007
(MOD.ELE.FTC.026).
c) Form RS-E007 (MOD.ELE.FTC.026) shall be endorsed to signify that the
requirements of electrical procedure for apparatus for use in hazardous areas
and procedure for junction box, if appropriate have been carried out satisfactorily.

7.11
7.11.1

Navigation AIDS
Pre-Commissioning Certification Testing
a) Ensure that all Site-installed cables have been certified in accordance with the
relevant Electrical Procedure and test certificates completed.
b) If applicable, carry out testing of batteries and battery chargers in accordance
with the Procedure for batteries and battery chargers.
c) Check correct operation of all control/synchronising circuits.
d) Check correct operations of all alarm circuits.

7.11.2

Test Certificates
a) Pre-commissioning certification testing shall be recorded on Form RS-E008
(MOD.ELE.FTC.027).
Form RS-E008 (MOD.ELE.FTC.027) requires endorsement to confirm that the
requirements of electrical procedure for apparatus for use in hazardous areas,
battery and battery charger have been carried out.
b) Supplier test sheets shall be attached to Form RS-E008 (MOD.ELE.FTC.027) for
inclusion in the system test dossier.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

7.12
7.12.1

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 43 di 46

Electrical Equipment & Device (Heater, Panel, Junction Box, Push-Button


Station, Socket)
Pre-Commissioning Certification Testing
a) Confirm that all cable certification is complete.
b) Confirm that all electrical equipments are correct to latest revision of drawings.
c) Carry out function test of electrical equipments (for each equipment installed, i.e.
metering and protection devices, ammeter, voltmeter indicating lamp, etc. refer to
the electrical relevant procedures).

7.12.2

Test Certificates
a) Pre-commissioning certification testing shall be
RS-E009 and RS-E010 (MOD.ELE.FTC.028 and 029).

recorded

on

form

b) Supplier test sheets shall be attached to Form RS-E009 and RS-E010


(MOD.ELE.FTC.028 and 029) for inclusion in the system test dossier.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

8.
8.1

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 44 di 46

REFERENCE DOCUMENTS
Specification, Standards and Codes
Electrical installation check and test shall be carried out in accordance with the
requirements of this procedure, the vendors documentation, the project electrical
drawings and with the latest edition of the project specifications and codes:

8.2

Electrical Mechanical Completion Check Lists

MOD-ELE-FTC-001

Data sheet for duties and responsabilities of checks


and tests of electrical installations

MOD-ELE-FTC-002 (CL-E001)

Generator check list

MOD-ELE-FTC-003 (CL-E002)

Transformer check list

MOD-ELE-FTC-004 (CL-E003)

MV & LV Motors check list

MOD-ELE-FTC-005 (CL-E004)

MV & LV Switchgear and bus-bar check list

MOD-ELE-FTC-006 (CL-E005)

MV Cables test certificate

MOD-ELE-FTC-007 (CL-E006)

MV & LV Power and control cables check list

MOD-ELE-FTC-008 (CL-E007)

UPS & D.C. System check list

MOD-ELE-FTC-009 (CL-E008)

Batteries check list

MOD-ELE-FTC-010 (CL-E009)

Lighting & Small power check list

MOD-ELE-FTC-011 (CL-E010)

Navigation aids check list

MOD-ELE-FTC-012 (CL-E011)

Earthing bonding check list

MOD-ELE-FTC-013 (CL-E012)

Heater check list

MOD-ELE-FTC-014 (CL-E013)

Electrical Equipment & Device check list

MOD-ELE-FTC-015

Earthing system measurements

MOD-ELE-FTC-016

Measurement of earth fault loop impedance

MOD-ELE-FTC-017 (CL-E014)

Electrical substation, etc check list

MOD-ELE-FTC-018 (CL-E015)

Cathodic protection system check list

MOD-ELE-FTC-019 (CL-E016)

Cable Tray & Rack check list

MOD-ELE-FTC-030 (CL-E017)

Neutral earthing resistor check list

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

8.3

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 45 di 46

Electrical Pre-Commissioning Record Sheet

MOD-ELE-FTC-020 (RS-E001)

Generator pre-commissioning record sheet

MOD-ELE-FTC-021 (RS-E002)

Transformer pre-commissioning record sheet

MOD-ELE-FTC-022 (RS-E003)

MV & LV Motors pre-commissioning record sheet

MOD-ELE-FTC-023 (RS-E004)

MV & LV Switchgear pre-commissioning record sheet

MOD-ELE-FTC-024 (RS-E005)

D.C. System pre-commissioning record sheet

MOD-ELE-FTC-025 (RS-E006)

Batteries pre-commissioning record sheet

MOD-ELE-FTC-026 (RS-E007)

Lighting & Small Power pre-commissioning record sheet

MOD-ELE-FTC-027 (RS-E008)

Navigation Aids pre-commissioning record sheet

MOD-ELE-FTC-028 (RS-E009)

Heater pre-commissioning record sheet

MOD-ELE-FTC-029 (RS-E010)

Electrical Equipment pre-commissioning record sheet

MOD-ELE-FTC-031 (RS-E011)

Neutral earthing resistor pre-commissioning record sheet

MOD-ELE-FTC-032 (RS-E012)

Inverter ups pre-commissioning record sheet

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Eni S.p.A.
Exploration & Production Division

05221 VAR.ELE.SPC
Rev.6 March 2010
Sheet 46 di 46

METHOD OF COMPANY STANDARS REQUEST / INFORMATIONS


For employees of Eni Exploration & Production Division:
All documentation Company Standards, for ENI employees, is available
on follow ENI intranet:
http://wwweandp.eni.it/TSServices/ITEM/Standards-/index.asp
To request technical informations on this document write to
Community of Pratics Electrical / Automation / Instrumentation:
CopEleStau@eni.it
For the outside companies:
The outside Companies that in a contract with the contractor must use the
Company standards, they may request a copy of the Company standard at the
Development manager of the contract.

Il presente documento RISERVATO ed di propriet di ENI E&P. Esso non sar mostrato a Terzi n sar utilizzato per scopi diversi da quelli per i quali stato inviato.
This document is CONFIDENTIAL and the sole property of ENI E&P. It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.

Potrebbero piacerti anche