SYSTEM
NESMA
Inspection and Test Plan for Fire Protection PMC OXGAON
NOVEC System VILLAGE
COMPANY
LIMITED
Main
Contractor
Tamimi Global Co.
Contract Rev
Project 20,000 PERSON NRC OXAGON PLOT D ITP No: TPE-MEC-ITP-000000 No:
01 DATE
# No.
Controllin
g Acceptance Level of Participation Points
S.N Activity Phase Inspection / Test Method Document/ Remark
Criteria NEOM
O CONTRACTO PMC(SAJ)
Reference Project
R
Standard Monitor
1 Document Review
Review of shop drawings NEOM Specs Section 212200
with reference to IFC S
1.1 drawings Approved R/H R
drawings
2 Receiving Inspection
Visual inspection for Approved material
submittal Project Approved material MIR / DELIVERY NOTE / MAT
damage, deformity and
Specific 212200 submittal Project S
2.1 Correct label. Specific 212000 H W APPROVAL / MATERIAL
PROCUREMENT CHECKLIST
PHASE
2.2 Material receiving NEOM Specs Section 212200 Approved material
Inspection of Clean submittal Project H W S
agent Fire Extinguishing Specific 212000
system
4.2 Room integrity test As per Approved WIR / MIR APPROVAL / DRAWINGS /
Project SPEC 212200 method of statement
Integration of Novec to the Fire H H S MECH-TIC1.1
Station BMS.
MOS for Fire Fighting As per Approved WIR / MIR APPROVAL / DRAWINGS /
Testing commissioning Installation, method of statement H H S MECH-TIC1.1
Testing, and
Commissioning
NEOM Specs 212200 part
3.9 & NFPA 2001
NEOM QUALITY MANAGEMENT
SYSTEM
NESMA
Inspection and Test Plan for Fire Protection PMC OXGAON
NOVEC System VILLAGE
COMPANY
LIMITED
Main
Contractor
Tamimi Global Co.
Contract Rev
Project 20,000 PERSON NRC OXAGON PLOT D ITP No: TPE-MEC-ITP-000000 No:
01 DATE
# No.
Controllin
g Acceptance Level of Participation Points
S.NO Activity Phase Inspection / Test Method Document/ Remar
Criteria NEOM
CONTRACTO PMC(SAJ) k
Reference Project
R
Standard Monitor
GENERAL NOTES:
1) The first (3) of each inspection or testing activity listed requires 100% participation of client site inspection personnel. After
this period,client inspection may adjust the level of client participation based on the contractor's performance.
2) Hold: The QA/QC team shall be notified of the schedule of inspection or test in advance. Inspection or test shall not be
carried outwithout the QA/QC Team/Client representative in attendance.
3) Review: Required qualification/certification/reports shall be submitted for the QA/QC team review and approval.
4) Witness: The QA/QC team shall be notified of the schedule of inspection or test in advance. If the QA/QC Team/Client
representative
doesn’t come on time for inspection, the activity can proceed.
5) Surveillance: QA/QC team to monitor work in progress without notice from the construction organization/Random check
selection.
6) Once Neom has issued an acceptance of ITP, CONTRACTOR shall not deviate from the requirements in it, unless prior
written from NEOM. The acceptance of this ITP shall not release CONTRACTOR from any other obligations in Schedule”
Q”, or any other contractualobligation.
Hold point for NEOM/ EPM / QC
H inspection/test R Review of Documents S Surveillance
W Witness Inspection / Test RH Review And Approval Of Documents I 100% Contractor Inspection
DOCUMENT CODE: NEOM-NEN-
REVISION CODE: 01.00
SOP-
008_FRM11
©NEOM [2021]. All rights
reserved
INSPECTION CHECKLIST TIC NUMBER Date: WIR NUMBER
Inspection and Test Plan for Fire Protection MECH-TIC-1.3
NOVEC System Rev:
3.7 The test found satisfactory and Acceptable (No leak Found)
Verify That the System Is in Normal Mode and Check the Control Panel Display
4.3
and Indicators in The Front of The
Panel SECTION
1st Stage Activate One Detector in A Protected Hazard Area and Please Check 212200 & NFPA 2001
4.4 the Following
QC Client Representative
Inspector
Performed Inspection
Name, Initials Work/Rework May Proceed T&I Witnessed
andDate: QC Record Reviewed
Name, Work Verified
QC Supervisor / Manager
Initialsand
Name, Sign Date:
andDate: