Projects New GES Logistic Building
1 The striking formal concision of the new drawings, is transposed into the synthetic boundary with the town of Maranello.
View of entrance
2
Logistis building for Gestione Sportiva Fer- plasticity of a volume conceived as an im- The streamlined, agile profile of the atypi-
General plan rari at Fiorano evokes on the one hand the mense extrusion, providing a compact, en- cal industrial hangar extends for a length
3 visionary dreams of certain Futurist procla- ergetic image which finds the reasons for of nearly 112 m and is divided into three
View of racetrack mations, like a metaphor for those “broad- its construction all within a self-referential sections, corresponding to three functional
4
Side of building
chested locomotives that gallop over the and consistent grammar of composition. In areas and fire-fighting compartments: the
rails, like enormous steel horses harnessed this sense, the scintillating, tapered form of section to the north is reserved to the main-
in tubes” (F.T. Marinetti), while on the other the hangar designed by the Studio Sturchio tenance, loading and unloading of trucks, as
hand it shows reference to a linguistic ex- Architects and Designers pursues the inten- well as to the storing of materials at a height
pressionism of vague Mendelsonian flavor, tion of strong figurative recognition and of of + 6.2 m, on a gangway 8 m wide coinciding
appropriate to an architecture based on the contextual alienation, affirming its reality as with the longitudinal axis of the structure.
principle of organic unity. “The eloquence of an uprooted organism, as if accidentally and The middle section, with stairway and ample
the brief dream, of a single setting” (Bruno temporarily stranded on the border of the elevators (3.2 x 4.3 m), is used for handling,
Zevi), already apparent in the design pencil- Fiorano car testing track, marking its eastern treating and storing materials for the racing
Progetti Nuova Logistica Gestione Sportiva 5 ed ampio montacarichi (3.2 x 4.3 m), è adibito verticali di 2, risulta alto 11.5 m e largo 25.
Pianta delle coperture
6 alla movimentazione, trattamento e deposito Il passaggio al lembo intermedio, lungo 33
Sezione trsversale dei materiali per i box di gara, a locali tecnici, m, è definito da una marcata soluzione di
7 e a magazzino vestiario al livello superiore; continuità, ottenuta grazie alla repentina
Fianco il segmento verso sud, autentica testata del- contrazione di un metro e mezzo dell’omo-
8
Pianta piano primo l’intera struttura, anch’esso munito di scala loga sezione trasversale e risolta attraverso
9 - 10 ed ascensore, ospita gli uffici direzionali al una raffinata sovrapposizione degli involucri
Prospetto frontale piano terra ed i servizi per il personale al metallici, determinando, così, la percezione
e posteriore primo piano. di un innesto telescopico tra le due parti
Tale frazionamento interno, ancorché assor- contigue. I successivi 14 m del lembo me-
bito dall’unitario inviluppo volumetrico, tro- ridionale, infine, registrano un continuo e
va un sottile riscontro esteriore nella varia- progressivo incremento della curvatura, per
5
zione della sezione trasversale complessiva concludersi in una morbida calotta di chiu-
e nel differente valore materico attribuito al sura su cui è centrato il varco d’ingresso agli
rivestimento superficiale in alluminio. spazi amministrativi.
Dal punto di vista geometrico, il lembo Nel ribadire la medesima cadenza funzionale
settentrionale dell’edificio è originato dalla interna, poi, il tratto nord, il cui fianco ovest
traslazione di una generatrice composita se- prospiciente la pista è solcato da una sequen-
condo una direttrice rettilinea di circa 65 m: za regolare di dieci “boccaporti” di accesso
il profilo trasversale, costituito da due quarti alti 4.5 m e larghi 5, esibisce una vibrante
di circonferenza di raggio pari a 9.5 m, rac- finitura in lamiera ondulata, tipo well-te-
cordati in chiave da un segmento orizzontale ch, dal serrato passo di 6 cm; per contro, il
di 6 m e completati all’imposta da segmenti tratto centrale, anch’esso scavato da quattro
9
6
78
Pietro Savorelli
7 10 11
0 10 30m 5 boxes, to technical facilities, and to a clothing though the abrupt contraction of a meter and
Plan of roofs warehouse on the upper level. The section a half in the homologous cross-section and
6
Transversal section to the south, the authentic head of the whole resolved through a refined superimposition
7 structure, which also has a stairway and el- of the metal shells, thus determining the
Side evator, houses the managerial offices on the perception of a telescopic grafting of the two
8 ground floor and facilities for personnel on contiguous parts. Lastly, the subsequent 14
Plan of ground floor
the first floor. m of the southern section register a continu-
Projects New GES Logistic Building
9 - 10
Front and rear perspective This interior division, although absorbed by ous and progressive increase in curvature,
C B
the unitary volumetric envelope, finds a sub- to conclude in a gentle calotte on which is
tle exterior echo in the variation of the over- centered the entrance to the administrative
all cross-section and in the different material offices.
value assigned to the facing in aluminum. Reiterating the same interior functional ca-
From the geometric viewpoint, the northern dence is the northern section, whose western
section of the building has originated from side overlooking the race-track is broken by
A A the translation of a generatrix composed a regular sequence of ten “portholes” of ac-
according to a rectilinear directrix of about cess, 4.5 high and 5 wide, exhibiting a vibrant
65 m: the transverse profile, constituted by finish in corrugated sheet iron, of the well-
two-fourths of a circumference with radius of tech type, with a narrow step of 6 cm. By
9.5 m, connected by a horizontal segment of contrast, the central section, it too opened by
6 m and completed at the impost by vertical four more portholes, presents a smooth skin
segments of 2 m, is 11.5 m high and 25 wide. made of horizontal courses of plates half a
The transition to the intermediate section, 33 meter high with flat lap joints, while the
8
C B m long, is defined by a marked gap, obtained southern end, wedged onto a base in exposed
Progetti Nuova Logistica Gestione Sportiva 12
0 200 500cm Sezioni trasversali B-B
e C-C
13
Dettagli della calotta:
A. particolare plinto
C colonna; B. particolare
attacco collegamento
B con HEA 300 calandrato
e pacchetto
di rivestimento;
C. particolare nodo pilastro
copertura; D. particolare
nodo pilastro soppalco;
D E. particolare plinto
colonna HEA 300
14
Vista del fianco dell’edificio
all’altezza dello stacco
tra la parte rivestita
in lamiera ondulata
e quella rivestita in lamiera
liscia
A E
12
80
B C D 12
Transversal sections B-B
and C-C
13
Details of dome:
A. detail of column plinth;
B. detail of joint with
grilled HEA 300 and facing
aggregate; C. detail
of junction of roof pillar;
D. detail of junction
of mezzanine pillar;
E. detail of column plinth
in HEA 300
14
View of the side
of the building
at the height where
the facing in corrugated
metal is interrupted
by the one in smooth metal
Projects New GES Logistic Building
A E
Pietro Savorelli
13 0 50 100cm 14
Progetti Nuova Logistica Gestione Sportiva 15 13 8 6 5 2 4 1 9 7 Legenda: 1. sormonto ulteriori portelloni, presenta una pelle levi-
Vista del fianco dell’edificio della guaina impermeabile
in corrispondenza in corrispondenza della vite; gata in ricorsi orizzontali di lastre alte mezzo
della finestra a nastro 2. vite autofilettante sotto metro con giunti piani a sormonto, mentre
16 guaina per fissaggio lana di l’estremità sud, incuneata su uno zoccolo in
Particolare del pacchetto roccia; 3. lamiera liscia di cls a faccia vista ed appena incisa da un’asola
di rivestimento con rivestimento calandrata e
lamiera ondulata rivettata in alluminio tipo orizzontale vetrata, mostra analoghi ricorsi
calandrata e rivettata “well-tech” w 10/60; di lastre, ma con aggraffature a risalto, tali da
17 4. guaina impermeabile; produrre un effetto plastico di rigatura.
Particolare del serramento 5. materassino in lana Lo spazio interno dell’hangar è scandito dal
a nastro di roccia sp. 10 cm; 6.
sottostruttura portante in ritmo della centinatura portante, realizzata
lamiera grecata microforata con profilati HEA 300 ogni 6 m (HEA 200
sp. 16 cm; 7. sormonto delle ogni 2 m nella testata sud), e dalla struttura
lamiere ondulate; 8. vite a telaio del ballatoio di spina, con due file di
di fissaggio degli omega alla
struttura portante; pilastri (ø 43 / passo 12 m) distanziate di 6
9. profilo in alluminio omega m, cui corrisponde la fascia piana della co-
calandrato sp. 8 cm; 10. pertura su cui sono inseriti i lucernari e gli
HEA 300; 11. bussola; 12. evacuatori di fumo raggiungibili dalla scala
vite; 13. lamiera ondulata
13 2 1 7 12 14 11 6 5 4 9 di rivestimento calandrata esterna che segna il fronte nord.
e rivettata in alluminio tipo
“well-tech” w 10/60; 14.
rivetto in alluminio;
15. scossalina metallica sp. 8
mm; 16. canale di gronda in
c.a. incassata nella muratura; Informazioni Information
17. muratura rivestita in
Ascensori Elevators KONE Ascensori
mattoni; 18. scarico acque
superficiali nella griglia di
raccolta; 19. angolare per Elementi d’acciaio Stahlbau Pichler
fissaggio del controtelaio alla Steel elements
lamiera grecata portante;
20. lamiera superiore a Esecuzione strutture Mario Neri
chiusura del pacchetto di in calcestruzzo, fondazioni,
rivestimento; 21. serramento; infissi, intonaci, opere
22. davanzale in scossalina
in muratura, pitture murali
di acciaio; 23. muratura
10
di mattoni intonacata e Concrete elements,
tinteggiata; 24. pavimento foundations, standing finish,
industriale; 25. soletta in c.a.; plastering, masonry works,
0 20 50cm 26. vespaio; 27. terreno wall painting
sill in steel flashing; 23. wall tance of 6 m, to which corresponds the flat
with plastered and colored band of the roofing in which are inserted the
bricks; 24. industrial floor; skylights and the smoke evacuators, reach-
25. floor slab in reinforced
concrete; 26. loose stone able by the outside stairway which marks the
15 foundation; 27. ground northern front.