SOMMARIO
ILLUSTRAZIONE SINTETICA DEGLI ELEMENTI ESSENZIALI DEL PROGETTO STRUTTURALE ............................................ 3
1. DESCRIZIONE DEL CONTESTO EDILIZIO E DELLE CARATTERISTICHE GEOLOGICHE,
MORFOLOGICHE E IDROGEOLOGICHE DEL SITO DI INTERVENTO .......................................................... 3
2. DESCRIZIONE GENERALE DELLA STRUTTURA ................................................................................... 6
3. NORMATIVA TECNICA E RIFERIMENTI TECNICI UTILIZZATI .............................................................. 7
4. PARAMETRI DI PROGETTO E AZIONI SULLA COSTRUZIONE ............................................................ 8
4.1 CARICHI VERTICALI ........................................................................................................................................................ 8
4.2 CARICO DEL VENTO ........................................................................................................................................................ 9
4.3 PARAMETRI DI PROGETTO NECESSARI ALLA DEFINIZIONE DELL’AZIONE SISMICA DI BASE DEL SITO .................................................. 10
4.4 AZIONE SISMICA DI RIFERIMENTO .................................................................................................................................... 11
4.4.1 DETERMINAZIONE DEI PARAMETRI AG, F0, TC* ............................................................................................................... 11
4.4.2 CATEGORIA DI SOTTOSUOLO E CONDIZIONI TOPOGRAFICHE ............................................................................................... 12
4.4.3 SPETTRO DI RISPOSTA ELASTICO IN ACCELERAZIONE COMPONENTI ORIZZONTALI ..................................................................... 12
4.4.4 SPETTRO DI PROGETTO PER GLI STATI LIMITE DI ESERCIZIO ................................................................................................. 15
4.4.5 SPETTRO DI PROGETTO PER GLI STATI LIMITE ULTIMI ........................................................................................................ 15
5. PROPRIETÀ DEI MATERIALI ................................................................................................................... 16
6. CRITERI DI PROGETTAZIONE E MODELLAZIONE .............................................................................. 17
6.1 CRITERI DI PROGETTAZIONE ........................................................................................................................................... 17
6.2 MODELLAZIONE DELLA GEOMETRIA E DELLE PROPRIETÀ MECCANICHE .................................................................................... 17
7. CASI DI CARICO E COMBINAZIONI DELLE AZIONI ............................................................................. 20
8. ANALISI EFFETTUATE ............................................................................................................................. 31
9. CRITERI DI VERIFICA IN PRESENZA DI AZIONE SISMICA ................................................................. 44
9.1 CRITERI DI VERIFICA – S.L.V. ......................................................................................................................................... 44
9.2 CRITERI DI VERIFICA – S.L.D. ......................................................................................................................................... 44
10. SINTESI DEI RISULTATI E DELLE VERIFICHE ................................................................................... 45
10.1 PRINCIPALI CONFIGURAZIONI DEFORMATE ...................................................................................................................... 45
10.2 INVILUPPI DELLE SOLLECITAZIONI .................................................................................................................................. 47
10.3 RISULTATI VERIFICHE S.L.U. ........................................................................................................................................ 52
10.4 VERIFICHE SLE – NO SISMA ......................................................................................................................................... 57
11. CARATTERISTICHE E AFFIDABILITÀ DEL CODICE DI CALCOLO ................................................. 62
11.1 GIUDIZIO MOTIVATO SULL’ACCETTABILITÀ DEI RISULTATI ................................................................................................... 62
12. VERIFICHE DI SICUREZZA GEOTECNICHE........................................................................................ 63
12.1 MODELLAZIONE GEOTECNICA E DETERMINAZIONE DELLE COSTANTI DI WINKLER ..................................................................... 63
12.2 VALORI DELLE MASSIME PRESSIONI ATTESE ..................................................................................................................... 64
12.3 VALORI DI CALCOLO DELLA PORTANZA PER FONDAZIONI SUPERFICIALI ................................................................................... 64
12.4 VALORI DI CALCOLO DEI CEDIMENTI PER FONDAZIONI SUPERFICIALI ...................................................................................... 69
13. DESCRIZIONE DEL MODELLO DI CALCOLO AD ELEMENTI FINITI ................................................ 72
13.1 CARATTERISTICHE MATERIALI UTILIZZATI .................................................................................................................... 72
MANDANTE:
1
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
13.2 MODELLAZIONE DELLE SEZIONI ................................................................................................................................ 73
13.3 MODELLAZIONE STRUTTURA: NODI .......................................................................................................................... 74
13.4 MODELLAZIONE STRUTTURA: ELEMENTI TRAVE ........................................................................................................... 76
13.5 MODELLAZIONE STRUTTURA: ELEMENTI SHELL ............................................................................................................ 79
13.6 MODELLAZIONE STRUTTURA: ELEMENTI SOLAIO .......................................................................................................... 83
14. VERIFICA NODI ....................................................................................................................................... 87
MANDANTE:
2
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
3
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Gli acquiferi più profondi, sono ospitati nelle formazioni consolidate pre-Plioceniche che,
unitamente a quelli rinvenibili nei depositi sabbiosi Pliocenici e Pleistocenici sovrastanti, sono di
ambiente lagunare e marino, con acque salmastre o salate, di scarso interesse pratico.
Nelle successioni Oloceniche, l’ambiente deposizionale è di tipo continentale e si osserva una
successione di livelli a sabbia fine e grossolana, intercalati a livelli argillosi con frequenti tracce di
torba.
Falda
Categoria di Sottosuolo
La prova SCPTU ha permesso una valutazione diretta della velocità di propagazione delle onde
sismiche (v. all. 2) dall’elaborazione dei dati registrati è emersa una Vs30 variabile tra 176,88 e
177,79 m/s e di conseguenza il suolo risulta appartenente alla Categoria D Depositi di terreni a
grana grossa scarsamente addensati o di terreni a grana fina scarsamente consistenti, con spessori
superiori a 30 m, caratterizzati da un graduale miglioramento delle proprietà meccaniche con la
profondità e da valori di Vs,30 inferiori a 180 m/s (ovvero NSPT,30 < 15 nei terreni a grana grossa
e cu,30 < 70 kPa nei terreni a grana fina).
Categoria Topografica: T1
Inquadramento Litostratigrafico
MANDANTE:
4
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Per informazioni più dettagliate in merito alla natura del terreno, alle prove eseguite e alla
definizione della sismicità locale, si rimanda alla relazione geologica in allegato al deposito
sismico.
MANDANTE:
5
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
6
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Circolare 2 febbraio 2009, n. 617 del Ministero delle Infrastrutture e dei Trasporti approvata
dal Consiglio Superiore dei Lavori Pubblici - Istruzioni per l'applicazione delle "Nuove norme
tecniche per le costruzioni" di cui al D.M. 14/01/2008;
MANDANTE:
7
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
SOLAIO "SERBATOI"
Accidentali (Qk)
Serbatoio 15.00 kN/m2
Accidentali (Qk)
Neve(*) 0.80 kN/m2
COPERTURA TETTOIA
MANDANTE:
8
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Accidentali (Qk)
Neve(*) 0.80 kN/m2
( )
* carico neve (§3.4.1 D.M. 2008)
Il carico provocato dalla neve sulla copertura è stato valutato mediante la seguente espressione:
q s i q sk C E C t
dove:
qs è il carico neve sulla copertura
μi è il coefficiente di forma della copertura, pari a 0,8 (0° ≤ α ≤ 30° α: angolo formato dalla falda
con l’orizzontale)
qsk è il valore caratteristico di riferimento del carico neve al suolo per un periodo di ritorno di 50
anni, pari a 1,0 kN/m2 (Zona II)
CE è il coefficiente di esposizione, pari a 1
Ct è il coefficiente termico, pari a 1
MANDANTE:
9
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
4.3 Parametri di progetto necessari alla definizione dell’azione sismica di base del
sito
MANDANTE:
10
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Tali valori sono forniti in allegato al D.M. 2008 in funzione della latitudine e longitudine del sito
e del periodo di ritorno TR della costruzione in esame, definito nell’allegato CA delle Istruzioni
per l’applicazione delle “Norme tecniche per le costruzioni” di cui al D.M. 14 gennaio 2008
come:
VR
TR
ln(1 PVR )
Dove:
VR è il periodo di riferimento per l’azione sismica:
VR VN CU 50 1.0 50 anni
VN è la vita nominale dell’opera:
PvR è la probabilità di superamento nel periodo VR relativa allo stato limite considerato:
MANDANTE:
11
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
I valori dei parametri (ag, F0, TC*) relativi all’edificio oggetto di studio risultano:
SLV SLD
PVR [% ] 10 PVR [% ] 63
TR [anni] 475 TR [anni] 50
latitudine 44.8360 latitudine 44.8360
longitudine 11,6180 longitudine 11,6180
ag 0,132g ag 0,046g
F0 [-] 2,600 F0 [-] 2,510
Tc* [s] 0,270 Tc* [s] 0,280
4.4.2 Categoria di sottosuolo e condizioni topografiche
Con riferimento rispettivamente alla Tabella 3.2.II e 3.2.IV del D.M. 2008 si afferma che il sito
sul quale sorge la costruzione ricade in:
MANDANTE:
12
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
dove:
S è il coefficiente che tiene conto della categoria di sottosuolo e delle condizioni topografiche
mediante la relazione seguente:
S S S ST
con:
SS: coefficiente di amplificazione stratigrafica:
h è il fattore che altera lo spettro elastico, pari ad 1 per smorzamento viscoso ξ = 5%;
TC è il periodo corrispondente all’inizio del tratto a velocità costante dello spettro, dato da:
MANDANTE:
13
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
TC C C TC*
con:
CC: coefficiente funzione della categoria di sottosuolo:
TB è il periodo corrispondente all’inizio del tratto dello spettro ad accelerazione costante, dato da:
TB TC 3
TD è il periodo corrispondente all’inizio del tratto a spostamento costante dello spettro, espresso in
secondi mediante la relazione:
ag
TD 4,0 1,6
g
Si riportano per gli stati limite considerati i valori dei parametri spettrali:
MANDANTE:
14
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
15
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
16
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Classe di duttilità: B
Regolarità in pianta: NO
Regolarità in altezza: NO
Tipologia strutturale:
Fattore di struttura:
q = qo*KR = 1
Giunti di separazione: Trattasi di fabbricato isolato, non è dunque necessario prevedere giunti di
separazione.
MANDANTE:
17
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
I pilastri e le travi sono stati modellati con elementi D2 tipo trave (6 g.d.l. per nodo)
I carichi (permanenti e accidentali) sono trasmessi alle travi da elementi solaio monodirezionali
infinitamente rigidi nel piano.
Per le verifiche strutturali e geotecniche della platea di fondazione è stata effettuata l’analisi
sull’intero complesso struttura-fondazione, modellando quest’ultima con elementi D3 tipo gusci di
fondazione di spessore 30 cm
MODELLO 1 – Assonometria
MANDANTE:
18
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
19
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Sono di tipo automatico A (ossia non prevedono introduzione dati da parte dell’utente) i seguenti
casi di carico: 1-Ggk; 4-Gsk; 5-Qsk; 6-Qnk.
Sono di tipo semi-automatico SA (ossia prevedono una minima introduzione dati da parte
dell’utente) i seguenti casi di carico:
7-Qtk, in quanto richiede solo il valore della variazione termica;
9-Esk e 10-Edk, in quanto richiedono il valore dell’angolo di ingresso del sisma e l’individuazione
dei casi di carico partecipanti alla definizione delle masse.
Sono di tipo non automatico NA ossia prevedono la diretta applicazione di carichi generici agli
elementi strutturali (si veda il precedente punto Modellazione delle Azioni) i restanti casi di carico.
Nella tabella successiva vengono riportati i casi di carico agenti sulla struttura, con l’indicazione dei
dati relativi al caso di carico stesso:
Numero Tipo e Sigla identificativa, Valore di riferimento del caso di carico (se previsto).
In successione, per i casi di carico non automatici, viene riportato l’elenco di nodi ed elementi
direttamente caricati con la sigla identificativa del carico.
Per i casi di carico di tipo sismico (9-Esk e 10-Edk), viene riportata la tabella di definizione delle
masse: per ogni caso di carico partecipante alla definizione delle masse viene indicata la relativa
aliquota (partecipazione) considerata. Si precisa che per i caso di carico 5-Qsk e 6-Qnk la
partecipazione è prevista localmente per ogni elemento solaio o copertura presente nel modello (si
confronti il valore Sksol nel capitolo relativo agli elementi solaio) e pertanto la loro partecipazione
è di norma pari a uno.
MANDANTE:
20
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Come previsto al § 2.5.3 delle NTC 2008, le combinazioni delle azioni per gli stati limite
considerati sono:
G1 G1 G 2 G 2 P P Q1 Q k 1 Q 2 02 Q k 2 Q 3 03 Q k 3 ...
- Combinazione sismica, impiegata per gli stati limite ultimi e di esercizio connessi
all’azione sismica E:
E G1 G2 P 21 Qk1 22 Qk 2 ...
Dove:
MANDANTE:
21
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
E = Ex ± 0,3*Ey E =0,3*Ex ± Ey
γ Gi, γQi Coefficienti parziali di sicurezza, definiti in Tabella 2.6.I del D.M. 2008
ψ0j, ψ1j, ψ2j Coefficienti di combinazione, definiti in Tabella 2.5.I del D.M.
MANDANTE:
22
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
23
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
24
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Cmb CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC
1/15... 2/16... 3/17... 4/18... 5/19... 6/20... 7/21... 8/22... 9/23... 10/24... 11/25... 12/26... 13/27... 14/28...
1 1.30 1.30 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.90
2 1.30 1.30 1.50 0.0 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.90
3 1.30 1.30 1.50 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.90
4 1.30 1.30 1.50 1.50 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.90
5 1.00 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.90
6 1.00 1.00 0.0 0.0 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.90
7 1.00 1.00 0.0 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.90
8 1.00 1.00 0.0 1.50 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.90
9 1.30 1.30 1.50 0.0 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.90
10 1.30 1.30 1.50 1.05 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.90
11 1.30 1.30 1.50 1.05 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.90
12 1.00 1.00 0.0 0.0 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.90
MANDANTE:
25
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Cmb CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC
1/15... 2/16... 3/17... 4/18... 5/19... 6/20... 7/21... 8/22... 9/23... 10/24... 11/25... 12/26... 13/27... 14/28...
13 1.00 1.00 0.0 1.05 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.90
14 1.00 1.00 0.0 1.05 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.90
15 1.30 1.30 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
1.50
16 1.30 1.30 1.50 0.0 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
1.50
17 1.30 1.30 1.50 1.05 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
1.50
18 1.30 1.30 1.50 1.05 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
1.50
19 1.00 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
1.50
20 1.00 1.00 0.0 0.0 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
1.50
21 1.00 1.00 0.0 1.05 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
1.50
22 1.00 1.00 0.0 1.05 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
1.50
23 1.30 1.30 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.90
0.0
24 1.30 1.30 1.50 0.0 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.90
0.0
25 1.30 1.30 1.50 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.90
0.0
26 1.30 1.30 1.50 1.50 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.90
0.0
27 1.00 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.90
0.0
28 1.00 1.00 0.0 0.0 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.90
0.0
29 1.00 1.00 0.0 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.90
0.0
30 1.00 1.00 0.0 1.50 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.90
0.0
31 1.30 1.30 1.50 0.0 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.90
0.0
32 1.30 1.30 1.50 1.05 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.90
0.0
33 1.30 1.30 1.50 1.05 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.90
0.0
34 1.00 1.00 0.0 0.0 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.90
0.0
35 1.00 1.00 0.0 1.05 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.90
0.0
36 1.00 1.00 0.0 1.05 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.90
0.0
37 1.30 1.30 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.50
0.0
38 1.30 1.30 1.50 0.0 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.50
0.0
39 1.30 1.30 1.50 1.05 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.50
0.0
40 1.30 1.30 1.50 1.05 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.50
0.0
41 1.00 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.50
0.0
42 1.00 1.00 0.0 0.0 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.50
0.0
43 1.00 1.00 0.0 1.05 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.50
0.0
MANDANTE:
26
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Cmb CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC
1/15... 2/16... 3/17... 4/18... 5/19... 6/20... 7/21... 8/22... 9/23... 10/24... 11/25... 12/26... 13/27... 14/28...
44 1.00 1.00 0.0 1.05 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.50
0.0
45 1.30 1.30 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
46 1.30 1.30 1.50 0.0 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
47 1.30 1.30 1.50 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
48 1.30 1.30 1.50 1.50 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
49 1.00 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
50 1.00 1.00 0.0 0.0 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
51 1.00 1.00 0.0 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
52 1.00 1.00 0.0 1.50 0.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
53 1.30 1.30 1.50 0.0 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
54 1.30 1.30 1.50 1.05 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
55 1.30 1.30 1.50 1.05 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
56 1.00 1.00 0.0 0.0 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
57 1.00 1.00 0.0 1.05 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
58 1.00 1.00 0.0 1.05 1.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
59 1.00 1.00 1.00 0.30 0.0 -1.00 0.0 -0.30 0.0 0.0 0.0 0.0 0.0 0.0
0.0
60 1.00 1.00 1.00 0.30 0.0 -1.00 0.0 0.30 0.0 0.0 0.0 0.0 0.0 0.0
0.0
61 1.00 1.00 1.00 0.30 0.0 1.00 0.0 -0.30 0.0 0.0 0.0 0.0 0.0 0.0
0.0
62 1.00 1.00 1.00 0.30 0.0 1.00 0.0 0.30 0.0 0.0 0.0 0.0 0.0 0.0
0.0
63 1.00 1.00 1.00 0.30 0.0 -1.00 0.0 0.0 -0.30 0.0 0.0 0.0 0.0 0.0
0.0
64 1.00 1.00 1.00 0.30 0.0 -1.00 0.0 0.0 0.30 0.0 0.0 0.0 0.0 0.0
0.0
65 1.00 1.00 1.00 0.30 0.0 1.00 0.0 0.0 -0.30 0.0 0.0 0.0 0.0 0.0
0.0
66 1.00 1.00 1.00 0.30 0.0 1.00 0.0 0.0 0.30 0.0 0.0 0.0 0.0 0.0
0.0
67 1.00 1.00 1.00 0.30 0.0 0.0 -1.00 -0.30 0.0 0.0 0.0 0.0 0.0 0.0
0.0
68 1.00 1.00 1.00 0.30 0.0 0.0 -1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0
0.0
69 1.00 1.00 1.00 0.30 0.0 0.0 1.00 -0.30 0.0 0.0 0.0 0.0 0.0 0.0
0.0
70 1.00 1.00 1.00 0.30 0.0 0.0 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0
0.0
71 1.00 1.00 1.00 0.30 0.0 0.0 -1.00 0.0 -0.30 0.0 0.0 0.0 0.0 0.0
0.0
72 1.00 1.00 1.00 0.30 0.0 0.0 -1.00 0.0 0.30 0.0 0.0 0.0 0.0 0.0
0.0
73 1.00 1.00 1.00 0.30 0.0 0.0 1.00 0.0 -0.30 0.0 0.0 0.0 0.0 0.0
0.0
74 1.00 1.00 1.00 0.30 0.0 0.0 1.00 0.0 0.30 0.0 0.0 0.0 0.0 0.0
0.0
MANDANTE:
27
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Cmb CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC
1/15... 2/16... 3/17... 4/18... 5/19... 6/20... 7/21... 8/22... 9/23... 10/24... 11/25... 12/26... 13/27... 14/28...
75 1.00 1.00 1.00 0.30 0.0 -0.30 0.0 -1.00 0.0 0.0 0.0 0.0 0.0 0.0
0.0
76 1.00 1.00 1.00 0.30 0.0 -0.30 0.0 1.00 0.0 0.0 0.0 0.0 0.0 0.0
0.0
77 1.00 1.00 1.00 0.30 0.0 0.30 0.0 -1.00 0.0 0.0 0.0 0.0 0.0 0.0
0.0
78 1.00 1.00 1.00 0.30 0.0 0.30 0.0 1.00 0.0 0.0 0.0 0.0 0.0 0.0
0.0
79 1.00 1.00 1.00 0.30 0.0 0.0 -0.30 -1.00 0.0 0.0 0.0 0.0 0.0 0.0
0.0
80 1.00 1.00 1.00 0.30 0.0 0.0 -0.30 1.00 0.0 0.0 0.0 0.0 0.0 0.0
0.0
81 1.00 1.00 1.00 0.30 0.0 0.0 0.30 -1.00 0.0 0.0 0.0 0.0 0.0 0.0
0.0
82 1.00 1.00 1.00 0.30 0.0 0.0 0.30 1.00 0.0 0.0 0.0 0.0 0.0 0.0
0.0
83 1.00 1.00 1.00 0.30 0.0 -0.30 0.0 0.0 -1.00 0.0 0.0 0.0 0.0 0.0
0.0
84 1.00 1.00 1.00 0.30 0.0 -0.30 0.0 0.0 1.00 0.0 0.0 0.0 0.0 0.0
0.0
85 1.00 1.00 1.00 0.30 0.0 0.30 0.0 0.0 -1.00 0.0 0.0 0.0 0.0 0.0
0.0
86 1.00 1.00 1.00 0.30 0.0 0.30 0.0 0.0 1.00 0.0 0.0 0.0 0.0 0.0
0.0
87 1.00 1.00 1.00 0.30 0.0 0.0 -0.30 0.0 -1.00 0.0 0.0 0.0 0.0 0.0
0.0
88 1.00 1.00 1.00 0.30 0.0 0.0 -0.30 0.0 1.00 0.0 0.0 0.0 0.0 0.0
0.0
89 1.00 1.00 1.00 0.30 0.0 0.0 0.30 0.0 -1.00 0.0 0.0 0.0 0.0 0.0
0.0
90 1.00 1.00 1.00 0.30 0.0 0.0 0.30 0.0 1.00 0.0 0.0 0.0 0.0 0.0
0.0
91 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 -1.00 0.0 -0.30 0.0 0.0
0.0
92 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 -1.00 0.0 0.30 0.0 0.0
0.0
93 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 1.00 0.0 -0.30 0.0 0.0
0.0
94 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 1.00 0.0 0.30 0.0 0.0
0.0
95 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 -1.00 0.0 0.0 -0.30 0.0
0.0
96 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 -1.00 0.0 0.0 0.30 0.0
0.0
97 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 1.00 0.0 0.0 -0.30 0.0
0.0
98 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 1.00 0.0 0.0 0.30 0.0
0.0
99 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 -1.00 -0.30 0.0 0.0
0.0
100 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 -1.00 0.30 0.0 0.0
0.0
101 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 1.00 -0.30 0.0 0.0
0.0
102 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 1.00 0.30 0.0 0.0
0.0
103 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 -1.00 0.0 -0.30 0.0
0.0
104 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 -1.00 0.0 0.30 0.0
0.0
105 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 1.00 0.0 -0.30 0.0
0.0
MANDANTE:
28
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Cmb CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC
1/15... 2/16... 3/17... 4/18... 5/19... 6/20... 7/21... 8/22... 9/23... 10/24... 11/25... 12/26... 13/27... 14/28...
106 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 1.00 0.0 0.30 0.0
0.0
107 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 -0.30 0.0 -1.00 0.0 0.0
0.0
108 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 -0.30 0.0 1.00 0.0 0.0
0.0
109 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.30 0.0 -1.00 0.0 0.0
0.0
110 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.30 0.0 1.00 0.0 0.0
0.0
111 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 -0.30 -1.00 0.0 0.0
0.0
112 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 -0.30 1.00 0.0 0.0
0.0
113 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 0.30 -1.00 0.0 0.0
0.0
114 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 0.30 1.00 0.0 0.0
0.0
115 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 -0.30 0.0 0.0 -1.00 0.0
0.0
116 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 -0.30 0.0 0.0 1.00 0.0
0.0
117 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.30 0.0 0.0 -1.00 0.0
0.0
118 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.30 0.0 0.0 1.00 0.0
0.0
119 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 -0.30 0.0 -1.00 0.0
0.0
120 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 -0.30 0.0 1.00 0.0
0.0
121 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 0.30 0.0 -1.00 0.0
0.0
122 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 0.30 0.0 1.00 0.0
0.0
123 1.00 1.00 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.60
124 1.00 1.00 1.00 0.0 0.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.60
125 1.00 1.00 1.00 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.60
126 1.00 1.00 1.00 1.00 0.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.60
127 1.00 1.00 1.00 0.0 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.60
128 1.00 1.00 1.00 0.70 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.60
129 1.00 1.00 1.00 0.70 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.60
130 1.00 1.00 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
1.00
131 1.00 1.00 1.00 0.0 0.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
1.00
132 1.00 1.00 1.00 0.70 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
1.00
133 1.00 1.00 1.00 0.70 0.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
1.00
134 1.00 1.00 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.60
0.0
135 1.00 1.00 1.00 0.0 0.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.60
0.0
136 1.00 1.00 1.00 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.60
0.0
MANDANTE:
29
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Cmb CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC CDC
1/15... 2/16... 3/17... 4/18... 5/19... 6/20... 7/21... 8/22... 9/23... 10/24... 11/25... 12/26... 13/27... 14/28...
137 1.00 1.00 1.00 1.00 0.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.60
0.0
138 1.00 1.00 1.00 0.0 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.60
0.0
139 1.00 1.00 1.00 0.70 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.60
0.0
140 1.00 1.00 1.00 0.70 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.60
0.0
141 1.00 1.00 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.00
0.0
142 1.00 1.00 1.00 0.0 0.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.00
0.0
143 1.00 1.00 1.00 0.70 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.00
0.0
144 1.00 1.00 1.00 0.70 0.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.00
0.0
145 1.00 1.00 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
146 1.00 1.00 1.00 0.0 0.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
147 1.00 1.00 1.00 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
148 1.00 1.00 1.00 1.00 0.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
149 1.00 1.00 1.00 0.0 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
150 1.00 1.00 1.00 0.70 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
151 1.00 1.00 1.00 0.70 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
152 1.00 1.00 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
153 1.00 1.00 1.00 0.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
154 1.00 1.00 1.00 0.0 0.20 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
155 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
156 1.00 1.00 1.00 0.30 0.20 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
157 1.00 1.00 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.20
158 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.20
159 1.00 1.00 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.20
0.0
160 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.20
0.0
161 1.00 1.00 1.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
162 1.00 1.00 1.00 0.30 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
0.0
MANDANTE:
30
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
8. Analisi effettuate
Le sollecitazioni dovute all’azione sismica sono state determinate attraverso un’analisi lineare
dinamica (§ 7.3.3.1 D.M. 2008).
Per ciascun caso di carico sismico viene riportato l’insieme di dati sottoriportati (le masse sono
espresse in unità di forza):
quota, posizione del centro di massa e massa risultante, posizione del baricentro delle rigidezze,
rapporto r/Ls (per strutture a nucleo) , indici di regolarità e/r secondo EC8 4.2.3.2
frequenza, periodo,accelerazione spettrale, massa eccitata nelle tre direzioni globali per tutti i modi
massa complessiva ed aliquota di massa complessiva eccitata.
Quota M Sismica x g Pos. GX Pos. GY E agg. X-X E agg. Y-Y Pos. KX Pos. KY rapp. r/Ls rapp. ex/rx rapp. ey/ry
cm daN cm cm cm cm cm cm
631.69 1418.71 1282.50 702.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0
613.00 739.88 1282.50 662.50 0.0 0.0 1282.50 662.50 1.225 0.0 0.0
549.34 2732.72 1282.50 526.25 0.0 0.0 0.0 0.0 0.0 0.0 0.0
467.00 2771.97 1282.50 350.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0
384.66 2732.72 1282.50 173.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0
321.00 427.95 1282.50 37.50 0.0 0.0 1282.50 37.50 1.225 0.0 0.0
302.31 1418.71 1282.50 -2.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0
290.00 1.053e+04 175.00 350.00 0.0 -31.25 175.00 350.00 0.837 0.0 0.0
MANDANTE:
31
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Quota M Sismica x g Pos. GX Pos. GY E agg. X-X E agg. Y-Y Pos. KX Pos. KY rapp. r/Ls rapp. ex/rx rapp. ey/ry
225.00 1.056e+04 175.96 362.02 0.0 -31.25 175.00 366.94 0.830 0.006 0.009
190.00 2.507e+04 1250.00 350.00 0.0 -17.50 1250.00 350.00 0.762 0.0 0.0
95.00 2.812e+04 865.70 361.20 0.0 -31.25 856.21 350.09 0.577 0.005 0.029
Risulta 8.653e+04
Modo Frequenza Periodo Acc. Spettrale M efficace X % M efficace Y % M efficace Z % Energia Energia x v
xg xg xg
Hz sec g daN daN daN
1 1.825 0.548 0.619 6.47 7.48e-03 6.175e+04 71.4 13.49 1.56e-02 0.0 0.0
2 2.198 0.455 0.619 6.583e+04 76.1 3.92 4.53e-03 814.06 0.9 0.0 0.0
3 2.457 0.407 0.619 182.83 0.2 8879.53 10.3 35.85 4.14e-02 0.0 0.0
4 3.312 0.302 0.619 283.70 0.3 93.58 0.1 3.372e+04 39.0 0.0 0.0
5 3.405 0.294 0.619 1.985e+04 22.9 3.29 3.81e-03 1.012e+04 11.7 0.0 0.0
6 4.227 0.237 0.619 0.27 3.08e-04 1.552e+04 17.9 23.44 2.71e-02 0.0 0.0
7 4.794 0.209 0.604 342.39 0.4 28.38 3.28e-02 3.982e+04 46.0 0.0 0.0
8 6.840 0.146 0.494 0.08 8.73e-05 9.94 1.15e-02 724.13 0.8 0.0 0.0
9 7.200 0.139 0.482 9.86 1.14e-02 0.31 3.55e-04 727.00 0.8 0.0 0.0
10 7.284 0.137 0.479 0.49 5.68e-04 0.47 5.41e-04 100.65 0.1 0.0 0.0
11 8.372 0.119 0.448 0.12 1.41e-04 4.67 5.39e-03 0.52 6.02e-04 0.0 0.0
12 8.525 0.117 0.444 1.11 1.28e-03 5.24 6.06e-03 6.63 7.66e-03 0.0 0.0
13 9.104 0.110 0.431 5.63e-03 6.50e-06 36.65 4.24e-02 9.97 1.15e-02 0.0 0.0
14 9.679 0.103 0.419 0.22 2.54e-04 13.57 1.57e-02 25.70 2.97e-02 0.0 0.0
15 9.724 0.103 0.418 0.30 3.47e-04 17.52 2.03e-02 35.66 4.12e-02 0.0 0.0
16 9.984 0.100 0.414 4.28 4.94e-03 2.08 2.40e-03 296.24 0.3 0.0 0.0
17 10.189 0.098 0.410 0.06 7.29e-05 90.86 0.1 2.56 2.96e-03 0.0 0.0
18 11.269 0.089 0.394 0.10 1.15e-04 1.26 1.45e-03 0.03 3.93e-05 0.0 0.0
19 11.763 0.085 0.387 1.36e-03 1.57e-06 2.05 2.37e-03 1.01 1.17e-03 0.0 0.0
20 11.984 0.083 0.384 0.21 2.41e-04 11.69 1.35e-02 34.50 3.99e-02 0.0 0.0
21 12.239 0.082 0.381 1.23e-03 1.42e-06 0.33 3.80e-04 0.31 3.64e-04 0.0 0.0
22 12.398 0.081 0.379 0.01 1.30e-05 2.58 2.99e-03 7.74 8.95e-03 0.0 0.0
23 13.558 0.074 0.367 0.10 1.11e-04 1.23 1.42e-03 1.02 1.18e-03 0.0 0.0
24 14.107 0.071 0.362 0.95 1.10e-03 15.25 1.76e-02 2.81 3.25e-03 0.0 0.0
25 14.808 0.068 0.356 0.88 1.02e-03 1.37 1.58e-03 0.06 6.74e-05 0.0 0.0
26 15.299 0.065 0.353 0.53 6.18e-04 11.82 1.37e-02 1.35 1.56e-03 0.0 0.0
27 17.848 0.056 0.336 5.54 6.40e-03 11.47 1.33e-02 3.10 3.58e-03 0.0 0.0
28 18.720 0.053 0.332 9.41 1.09e-02 6.05 6.99e-03 0.49 5.66e-04 0.0 0.0
29 22.008 0.045 0.318 5.70e-04 0.0 2.87e-03 3.31e-06 0.04 4.38e-05 0.0 0.0
30 22.267 0.045 0.317 9.61e-03 1.11e-05 7.44e-03 8.59e-06 0.02 2.16e-05 0.0 0.0
31 23.939 0.042 0.311 0.02 1.98e-05 0.95 1.10e-03 0.33 3.83e-04 0.0 0.0
32 27.415 0.036 0.302 5.46 6.31e-03 6.11e-03 7.07e-06 0.02 1.84e-05 0.0 0.0
33 28.410 0.035 0.300 3.69e-03 4.27e-06 0.40 4.59e-04 0.08 8.77e-05 0.0 0.0
34 30.448 0.033 0.296 0.02 2.10e-05 8.46e-03 9.78e-06 1.33e-03 1.54e-06 0.0 0.0
35 34.131 0.029 0.289 0.01 1.16e-05 0.01 1.57e-05 6.45e-05 0.0 0.0 0.0
36 43.082 0.023 0.279 0.13 1.46e-04 9.89e-05 0.0 0.09 1.02e-04 0.0 0.0
37 46.546 0.021 0.276 9.86e-04 1.14e-06 7.18e-04 0.0 4.68e-03 5.41e-06 0.0 0.0
38 47.621 0.021 0.275 6.24e-03 7.21e-06 9.22e-04 1.07e-06 3.18e-03 3.68e-06 0.0 0.0
39 49.244 0.020 0.274 1.62e-03 1.87e-06 5.64e-03 6.52e-06 0.08 9.32e-05 0.0 0.0
40 50.129 0.020 0.273 2.29e-04 0.0 4.17e-03 4.82e-06 8.67e-03 1.00e-05 0.0 0.0
41 51.145 0.020 0.272 2.47e-03 2.86e-06 5.46e-05 0.0 4.94e-03 5.71e-06 0.0 0.0
42 58.435 0.017 0.268 1.06e-06 0.0 9.57e-04 1.11e-06 5.99e-04 0.0 0.0 0.0
43 58.754 0.017 0.268 8.74e-05 0.0 6.56e-06 0.0 1.06e-04 0.0 0.0 0.0
44 58.844 0.017 0.268 1.62e-03 1.87e-06 1.10e-04 0.0 4.11e-05 0.0 0.0 0.0
45 60.831 0.016 0.267 0.03 3.15e-05 0.0 0.0 4.98e-03 5.75e-06 0.0 0.0
46 62.190 0.016 0.266 4.85e-04 0.0 6.52e-03 7.54e-06 3.87e-03 4.47e-06 0.0 0.0
47 63.864 0.016 0.265 7.85e-04 0.0 8.38e-04 0.0 1.88e-03 2.17e-06 0.0 0.0
48 64.767 0.015 0.265 5.66e-04 0.0 7.58e-05 0.0 2.49e-03 2.88e-06 0.0 0.0
49 66.234 0.015 0.264 5.08e-04 0.0 0.02 1.75e-05 1.66e-04 0.0 0.0 0.0
50 67.388 0.015 0.264 3.25e-04 0.0 3.98e-04 0.0 2.97e-05 0.0 0.0 0.0
Risulta 8.653e+04 8.653e+04 8.653e+04
In percentuale 100.00 100.00 100.00
MANDANTE:
32
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Quota M Sismica x g Pos. GX Pos. GY E agg. X-X E agg. Y-Y Pos. KX Pos. KY rapp. r/Ls rapp. ex/rx rapp. ey/ry
cm daN cm cm cm cm cm cm
631.69 1418.71 1282.50 702.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0
613.00 739.88 1282.50 662.50 0.0 0.0 1282.50 662.50 1.225 0.0 0.0
549.34 2732.72 1282.50 526.25 0.0 0.0 0.0 0.0 0.0 0.0 0.0
467.00 2771.97 1282.50 350.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0
384.66 2732.72 1282.50 173.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0
321.00 427.95 1282.50 37.50 0.0 0.0 1282.50 37.50 1.225 0.0 0.0
302.31 1418.71 1282.50 -2.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0
290.00 1.053e+04 175.00 350.00 0.0 31.25 175.00 350.00 0.837 0.0 0.0
225.00 1.056e+04 175.96 362.02 0.0 31.25 175.00 366.94 0.830 0.006 0.009
190.00 2.507e+04 1250.00 350.00 0.0 17.50 1250.00 350.00 0.762 0.0 0.0
95.00 2.812e+04 865.70 361.20 0.0 31.25 856.21 350.09 0.577 0.005 0.029
Risulta 8.653e+04
Modo Frequenza Periodo Acc. Spettrale M efficace X % M efficace Y % M efficace Z % Energia Energia x v
xg xg xg
Hz sec g daN daN daN
1 1.824 0.548 0.619 288.40 0.3 6.146e+04 71.0 7.52 8.69e-03 0.0 0.0
2 2.195 0.456 0.619 6.429e+04 74.3 864.86 1.0 841.35 1.0 0.0 0.0
3 2.467 0.405 0.619 1261.79 1.5 8296.56 9.6 1.26e-03 1.46e-06 0.0 0.0
4 3.310 0.302 0.619 573.89 0.7 86.10 9.95e-02 3.174e+04 36.7 0.0 0.0
5 3.396 0.294 0.619 1.971e+04 22.8 12.60 1.46e-02 1.215e+04 14.0 0.0 0.0
6 4.227 0.237 0.619 9.09 1.05e-02 1.553e+04 17.9 14.28 1.65e-02 0.0 0.0
7 4.795 0.209 0.604 358.03 0.4 26.16 3.02e-02 3.980e+04 46.0 0.0 0.0
8 6.841 0.146 0.494 0.20 2.36e-04 9.99 1.15e-02 720.89 0.8 0.0 0.0
9 7.200 0.139 0.482 5.28 6.10e-03 0.33 3.81e-04 730.68 0.8 0.0 0.0
10 7.284 0.137 0.479 0.27 3.12e-04 0.47 5.45e-04 100.39 0.1 0.0 0.0
11 8.373 0.119 0.448 0.08 9.75e-05 4.74 5.48e-03 0.45 5.21e-04 0.0 0.0
12 8.524 0.117 0.444 0.02 2.83e-05 5.52 6.38e-03 7.47 8.64e-03 0.0 0.0
13 9.109 0.110 0.431 0.47 5.49e-04 35.61 4.12e-02 8.43 9.74e-03 0.0 0.0
14 9.677 0.103 0.419 0.10 1.16e-04 15.01 1.73e-02 31.85 3.68e-02 0.0 0.0
15 9.724 0.103 0.418 0.18 2.13e-04 16.72 1.93e-02 32.16 3.72e-02 0.0 0.0
16 10.006 0.100 0.413 5.81 6.71e-03 5.67 6.55e-03 294.95 0.3 0.0 0.0
17 10.205 0.098 0.410 1.83 2.12e-03 86.97 0.1 0.16 1.88e-04 0.0 0.0
18 11.219 0.089 0.394 0.20 2.27e-04 0.79 9.07e-04 0.03 3.42e-05 0.0 0.0
19 11.763 0.085 0.387 9.14e-03 1.06e-05 1.97 2.27e-03 0.97 1.12e-03 0.0 0.0
20 11.999 0.083 0.384 3.00e-03 3.47e-06 12.77 1.48e-02 33.95 3.92e-02 0.0 0.0
21 12.237 0.082 0.381 2.37e-04 0.0 0.36 4.12e-04 0.58 6.75e-04 0.0 0.0
22 12.388 0.081 0.380 0.01 1.19e-05 2.55 2.94e-03 8.01 9.25e-03 0.0 0.0
23 13.498 0.074 0.368 0.19 2.25e-04 0.73 8.48e-04 0.13 1.52e-04 0.0 0.0
24 14.208 0.070 0.361 6.38e-03 7.37e-06 17.91 2.07e-02 4.70 5.43e-03 0.0 0.0
25 14.825 0.067 0.356 0.94 1.08e-03 1.45 1.68e-03 0.13 1.55e-04 0.0 0.0
MANDANTE:
33
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Modo Frequenza Periodo Acc. Spettrale M efficace X % M efficace Y % M efficace Z % Energia Energia x v
xg xg xg
26 15.245 0.066 0.353 0.97 1.13e-03 7.86 9.09e-03 0.08 9.34e-05 0.0 0.0
27 17.963 0.056 0.336 4.93 5.70e-03 15.19 1.76e-02 2.87 3.32e-03 0.0 0.0
28 18.626 0.054 0.332 10.01 1.16e-02 3.51 4.06e-03 0.63 7.32e-04 0.0 0.0
29 22.009 0.045 0.318 3.56e-03 4.12e-06 2.57e-03 2.97e-06 0.04 4.26e-05 0.0 0.0
30 22.266 0.045 0.317 3.82e-03 4.41e-06 7.94e-03 9.17e-06 0.02 2.23e-05 0.0 0.0
31 23.938 0.042 0.311 8.46e-03 9.77e-06 0.94 1.08e-03 0.33 3.80e-04 0.0 0.0
32 27.417 0.036 0.302 5.49 6.35e-03 0.01 1.36e-05 0.02 1.96e-05 0.0 0.0
33 28.417 0.035 0.300 0.01 1.41e-05 0.40 4.63e-04 0.08 9.53e-05 0.0 0.0
34 30.449 0.033 0.296 0.02 2.79e-05 7.96e-03 9.20e-06 1.28e-03 1.48e-06 0.0 0.0
35 34.128 0.029 0.289 0.01 1.53e-05 0.01 1.55e-05 3.64e-05 0.0 0.0 0.0
36 43.104 0.023 0.279 0.12 1.36e-04 2.86e-04 0.0 0.09 9.87e-05 0.0 0.0
37 46.550 0.021 0.276 5.72e-04 0.0 6.91e-04 0.0 4.51e-03 5.22e-06 0.0 0.0
38 47.645 0.021 0.275 9.85e-03 1.14e-05 8.78e-04 1.01e-06 2.94e-03 3.40e-06 0.0 0.0
39 49.258 0.020 0.274 1.60e-03 1.85e-06 5.58e-03 6.45e-06 0.08 9.35e-05 0.0 0.0
40 50.129 0.020 0.273 3.76e-04 0.0 4.35e-03 5.03e-06 9.29e-03 1.07e-05 0.0 0.0
41 51.175 0.020 0.272 3.54e-04 0.0 4.54e-05 0.0 4.86e-03 5.61e-06 0.0 0.0
42 58.406 0.017 0.268 2.74e-04 0.0 9.82e-04 1.14e-06 6.06e-04 0.0 0.0 0.0
43 58.762 0.017 0.268 1.42e-03 1.65e-06 1.36e-05 0.0 6.55e-05 0.0 0.0 0.0
44 58.832 0.017 0.268 1.38e-03 1.59e-06 1.16e-04 0.0 8.62e-05 0.0 0.0 0.0
45 60.903 0.016 0.267 0.02 2.76e-05 0.0 0.0 5.60e-03 6.48e-06 0.0 0.0
46 62.446 0.016 0.266 2.78e-04 0.0 8.19e-03 9.46e-06 3.53e-03 4.08e-06 0.0 0.0
47 63.883 0.016 0.265 4.86e-04 0.0 4.67e-04 0.0 1.77e-03 2.04e-06 0.0 0.0
48 64.795 0.015 0.265 5.01e-04 0.0 6.67e-06 0.0 2.40e-03 2.78e-06 0.0 0.0
49 66.245 0.015 0.264 2.54e-04 0.0 0.02 1.83e-05 1.28e-04 0.0 0.0 0.0
50 67.305 0.015 0.264 1.22e-04 0.0 0.0 0.0 2.24e-04 0.0 0.0 0.0
Risulta 8.653e+04 8.653e+04 8.653e+04
In percentuale 100.00 100.00 100.00
Quota M Sismica x g Pos. GX Pos. GY E agg. X-X E agg. Y-Y Pos. KX Pos. KY rapp. r/Ls rapp. ex/rx rapp. ey/ry
cm daN cm cm cm cm cm cm
631.69 1418.71 1282.50 702.50 93.00 0.0 0.0 0.0 0.0 0.0 0.0
613.00 739.88 1282.50 662.50 93.00 0.0 1282.50 662.50 1.225 0.0 0.0
549.34 2732.72 1282.50 526.25 93.00 0.0 0.0 0.0 0.0 0.0 0.0
467.00 2771.97 1282.50 350.00 93.00 0.0 0.0 0.0 0.0 0.0 0.0
384.66 2732.72 1282.50 173.75 93.00 0.0 0.0 0.0 0.0 0.0 0.0
321.00 427.95 1282.50 37.50 93.00 0.0 1282.50 37.50 1.225 0.0 0.0
302.31 1418.71 1282.50 -2.50 93.00 0.0 0.0 0.0 0.0 0.0 0.0
290.00 1.053e+04 175.00 350.00 13.75 0.0 175.00 350.00 0.837 0.0 0.0
225.00 1.056e+04 175.96 362.02 13.75 0.0 175.00 366.94 0.830 0.006 0.009
190.00 2.507e+04 1250.00 350.00 77.50 0.0 1250.00 350.00 0.762 0.0 0.0
95.00 2.812e+04 865.70 361.20 108.75 0.0 856.21 350.09 0.577 0.005 0.029
Risulta 8.653e+04
MANDANTE:
34
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Modo Frequenza Periodo Acc. Spettrale M efficace X % M efficace Y % M efficace Z % Energia Energia x v
xg xg xg
Hz sec g daN daN daN
1 1.882 0.531 0.619 56.33 6.51e-02 6.141e+04 71.0 12.85 1.49e-02 0.0 0.0
2 2.195 0.456 0.619 6.386e+04 73.8 548.23 0.6 831.47 1.0 0.0 0.0
3 2.343 0.427 0.619 2001.75 2.3 8808.63 10.2 0.74 8.54e-04 0.0 0.0
4 3.311 0.302 0.619 423.59 0.5 74.90 8.66e-02 3.269e+04 37.8 0.0 0.0
5 3.399 0.294 0.619 1.979e+04 22.9 12.92 1.49e-02 1.120e+04 12.9 0.0 0.0
6 4.190 0.239 0.619 5.82 6.72e-03 1.538e+04 17.8 33.62 3.89e-02 0.0 0.0
7 4.793 0.209 0.604 349.15 0.4 39.75 4.59e-02 3.971e+04 45.9 0.0 0.0
8 6.886 0.145 0.493 0.13 1.45e-04 14.52 1.68e-02 1090.66 1.3 0.0 0.0
9 7.076 0.141 0.486 8.14 9.41e-03 3.11 3.59e-03 509.68 0.6 0.0 0.0
10 7.308 0.137 0.478 0.26 3.01e-04 0.12 1.41e-04 4.77 5.51e-03 0.0 0.0
11 8.196 0.122 0.452 0.04 4.92e-05 21.01 2.43e-02 2.14 2.48e-03 0.0 0.0
12 8.635 0.116 0.441 0.14 1.62e-04 13.84 1.60e-02 16.65 1.92e-02 0.0 0.0
13 9.114 0.110 0.430 5.98e-03 6.91e-06 4.88 5.64e-03 7.73e-03 8.94e-06 0.0 0.0
14 9.441 0.106 0.424 0.01 1.72e-05 46.06 5.32e-02 4.62 5.34e-03 0.0 0.0
15 9.815 0.102 0.417 2.41 2.79e-03 43.92 5.08e-02 250.27 0.3 0.0 0.0
16 10.051 0.099 0.413 3.79 4.38e-03 21.51 2.49e-02 121.26 0.1 0.0 0.0
17 10.541 0.095 0.404 3.45e-03 3.99e-06 0.13 1.52e-04 0.05 6.00e-05 0.0 0.0
18 11.031 0.091 0.397 0.04 4.11e-05 24.29 2.81e-02 13.82 1.60e-02 0.0 0.0
19 11.472 0.087 0.391 0.03 3.56e-05 15.95 1.84e-02 16.51 1.91e-02 0.0 0.0
20 11.829 0.085 0.386 0.03 3.07e-05 2.94 3.39e-03 9.50 1.10e-02 0.0 0.0
21 12.275 0.081 0.381 3.07e-03 3.55e-06 4.48 5.18e-03 8.10 9.36e-03 0.0 0.0
22 13.787 0.073 0.365 3.99e-03 4.61e-06 1.18 1.37e-03 0.45 5.22e-04 0.0 0.0
23 13.916 0.072 0.364 0.17 1.97e-04 0.64 7.37e-04 0.35 4.05e-04 0.0 0.0
24 14.410 0.069 0.360 0.12 1.42e-04 6.99 8.07e-03 4.58 5.30e-03 0.0 0.0
25 14.500 0.069 0.359 0.03 3.98e-05 2.87 3.31e-03 1.11 1.29e-03 0.0 0.0
26 15.181 0.066 0.354 2.17e-03 2.51e-06 11.79 1.36e-02 0.90 1.04e-03 0.0 0.0
27 17.521 0.057 0.338 3.67 4.24e-03 11.31 1.31e-02 2.82 3.26e-03 0.0 0.0
28 18.443 0.054 0.333 12.70 1.47e-02 1.97 2.27e-03 1.12 1.30e-03 0.0 0.0
29 21.932 0.046 0.318 3.82e-03 4.42e-06 0.04 4.72e-05 0.02 1.98e-05 0.0 0.0
30 22.503 0.044 0.316 7.43e-03 8.58e-06 0.03 3.67e-05 0.02 2.13e-05 0.0 0.0
31 23.544 0.042 0.312 6.45e-03 7.45e-06 0.48 5.54e-04 0.33 3.84e-04 0.0 0.0
32 27.393 0.037 0.302 5.46 6.31e-03 2.21e-03 2.55e-06 0.02 2.45e-05 0.0 0.0
33 28.064 0.036 0.300 0.03 3.85e-05 0.40 4.62e-04 0.09 1.00e-04 0.0 0.0
34 31.162 0.032 0.294 0.01 1.72e-05 5.57e-03 6.44e-06 1.72e-03 1.99e-06 0.0 0.0
35 33.699 0.030 0.290 0.01 1.41e-05 0.04 4.89e-05 9.26e-05 0.0 0.0 0.0
36 43.022 0.023 0.279 0.12 1.39e-04 1.74e-04 0.0 0.09 1.05e-04 0.0 0.0
37 46.527 0.021 0.276 4.86e-03 5.62e-06 5.73e-04 0.0 4.67e-04 0.0 0.0 0.0
38 47.301 0.021 0.275 5.81e-03 6.72e-06 1.87e-03 2.16e-06 3.86e-04 0.0 0.0 0.0
39 48.901 0.020 0.274 3.44e-06 0.0 5.62e-03 6.50e-06 0.04 4.57e-05 0.0 0.0
40 49.429 0.020 0.273 1.40e-03 1.62e-06 2.14e-03 2.47e-06 0.06 6.96e-05 0.0 0.0
41 51.040 0.020 0.272 1.03e-03 1.19e-06 2.20e-05 0.0 8.25e-04 0.0 0.0 0.0
42 57.605 0.017 0.268 9.40e-04 1.09e-06 3.04e-04 0.0 3.98e-04 0.0 0.0 0.0
43 58.555 0.017 0.268 1.16e-04 0.0 3.93e-04 0.0 0.0 0.0 0.0 0.0
44 59.011 0.017 0.268 7.20e-03 8.32e-06 1.56e-05 0.0 1.56e-04 0.0 0.0 0.0
45 60.435 0.017 0.267 0.02 2.32e-05 2.71e-04 0.0 2.21e-03 2.56e-06 0.0 0.0
46 61.625 0.016 0.266 3.73e-04 0.0 5.26e-03 6.08e-06 6.35e-03 7.34e-06 0.0 0.0
47 63.446 0.016 0.266 6.07e-04 0.0 0.0 0.0 2.12e-03 2.45e-06 0.0 0.0
48 65.157 0.015 0.265 1.26e-03 1.45e-06 9.22e-03 1.07e-05 1.08e-03 1.24e-06 0.0 0.0
49 65.625 0.015 0.265 0.0 0.0 0.02 1.77e-05 2.57e-04 0.0 0.0 0.0
50 67.422 0.015 0.264 8.38e-06 0.0 1.34e-05 0.0 2.94e-03 3.40e-06 0.0 0.0
Risulta 8.653e+04 8.653e+04 8.653e+04
In percentuale 100.00 100.00 100.00
MANDANTE:
35
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Quota M Sismica x g Pos. GX Pos. GY E agg. X-X E agg. Y-Y Pos. KX Pos. KY rapp. r/Ls rapp. ex/rx rapp. ey/ry
cm daN cm cm cm cm cm cm
631.69 1418.71 1282.50 702.50 -93.00 0.0 0.0 0.0 0.0 0.0 0.0
613.00 739.88 1282.50 662.50 -93.00 0.0 1282.50 662.50 1.225 0.0 0.0
549.34 2732.72 1282.50 526.25 -93.00 0.0 0.0 0.0 0.0 0.0 0.0
467.00 2771.97 1282.50 350.00 -93.00 0.0 0.0 0.0 0.0 0.0 0.0
384.66 2732.72 1282.50 173.75 -93.00 0.0 0.0 0.0 0.0 0.0 0.0
321.00 427.95 1282.50 37.50 -93.00 0.0 1282.50 37.50 1.225 0.0 0.0
302.31 1418.71 1282.50 -2.50 -93.00 0.0 0.0 0.0 0.0 0.0 0.0
290.00 1.053e+04 175.00 350.00 -13.75 0.0 175.00 350.00 0.837 0.0 0.0
225.00 1.056e+04 175.96 362.02 -13.75 0.0 175.00 366.94 0.830 0.006 0.009
190.00 2.507e+04 1250.00 350.00 -77.50 0.0 1250.00 350.00 0.762 0.0 0.0
95.00 2.812e+04 865.70 361.20 -108.75 0.0 856.21 350.09 0.577 0.005 0.029
Risulta 8.653e+04
Modo Frequenza Periodo Acc. Spettrale M efficace X % M efficace Y % M efficace Z % Energia Energia x v
xg xg xg
Hz sec g daN daN daN
1 1.770 0.565 0.619 44.29 5.12e-02 6.358e+04 73.5 8.79 1.02e-02 0.0 0.0
2 2.198 0.455 0.619 6.560e+04 75.8 144.23 0.2 831.83 1.0 0.0 0.0
3 2.600 0.385 0.619 278.31 0.3 6762.62 7.8 36.42 4.21e-02 0.0 0.0
4 3.311 0.302 0.619 462.76 0.5 104.12 0.1 3.244e+04 37.5 0.0 0.0
5 3.399 0.294 0.619 1.976e+04 22.8 3.56 4.12e-03 1.139e+04 13.2 0.0 0.0
6 4.285 0.233 0.619 1.51 1.75e-03 1.564e+04 18.1 10.21 1.18e-02 0.0 0.0
7 4.796 0.209 0.604 350.70 0.4 18.63 2.15e-02 3.989e+04 46.1 0.0 0.0
8 6.764 0.148 0.497 0.27 3.15e-04 14.48 1.67e-02 633.54 0.7 0.0 0.0
9 7.227 0.138 0.481 1.85 2.14e-03 0.09 1.08e-04 200.08 0.2 0.0 0.0
10 7.364 0.136 0.476 5.10 5.89e-03 0.63 7.23e-04 631.94 0.7 0.0 0.0
11 8.036 0.124 0.456 0.02 1.92e-05 58.41 6.75e-02 29.58 3.42e-02 0.0 0.0
12 8.727 0.115 0.439 0.07 8.19e-05 7.29 8.42e-03 1.19 1.38e-03 0.0 0.0
13 8.997 0.111 0.433 1.17 1.36e-03 7.42 8.57e-03 61.54 7.11e-02 0.0 0.0
14 9.137 0.109 0.430 0.01 1.54e-05 0.50 5.74e-04 2.31 2.67e-03 0.0 0.0
15 10.050 0.100 0.413 5.31 6.13e-03 2.18 2.52e-03 285.25 0.3 0.0 0.0
16 10.184 0.098 0.410 0.12 1.37e-04 75.08 8.68e-02 3.04 3.52e-03 0.0 0.0
17 10.627 0.094 0.403 5.82e-03 6.72e-06 13.23 1.53e-02 3.22 3.73e-03 0.0 0.0
18 10.925 0.092 0.399 4.72e-03 5.45e-06 37.44 4.33e-02 17.08 1.97e-02 0.0 0.0
19 11.402 0.088 0.392 0.02 2.39e-05 0.68 7.86e-04 3.23 3.74e-03 0.0 0.0
20 11.872 0.084 0.386 1.35e-03 1.56e-06 4.69 5.42e-03 7.05 8.15e-03 0.0 0.0
21 12.258 0.082 0.381 0.03 3.65e-05 2.21 2.56e-03 24.76 2.86e-02 0.0 0.0
22 13.340 0.075 0.369 8.00e-03 9.25e-06 7.68 8.88e-03 6.45 7.46e-03 0.0 0.0
23 13.935 0.072 0.364 0.17 1.98e-04 0.29 3.34e-04 1.91 2.21e-03 0.0 0.0
24 14.265 0.070 0.361 0.18 2.13e-04 4.71 5.45e-03 0.18 2.10e-04 0.0 0.0
25 14.597 0.069 0.358 0.11 1.33e-04 2.78 3.21e-03 0.01 1.27e-05 0.0 0.0
26 15.335 0.065 0.352 0.08 9.26e-05 14.50 1.68e-02 6.50e-03 7.51e-06 0.0 0.0
27 18.117 0.055 0.335 13.18 1.52e-02 6.38 7.38e-03 3.31 3.83e-03 0.0 0.0
28 19.015 0.053 0.330 3.00 3.47e-03 15.98 1.85e-02 4.98e-05 0.0 0.0 0.0
29 21.994 0.045 0.318 1.72e-03 1.99e-06 0.02 2.19e-05 0.07 7.72e-05 0.0 0.0
30 22.149 0.045 0.317 3.81e-03 4.40e-06 0.03 3.39e-05 6.83e-03 7.90e-06 0.0 0.0
31 24.448 0.041 0.310 0.03 3.16e-05 1.83 2.12e-03 0.33 3.80e-04 0.0 0.0
MANDANTE:
36
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Modo Frequenza Periodo Acc. Spettrale M efficace X % M efficace Y % M efficace Z % Energia Energia x v
xg xg xg
32 27.429 0.036 0.302 5.43 6.27e-03 0.02 2.35e-05 0.01 1.54e-05 0.0 0.0
33 28.761 0.035 0.299 3.09e-03 3.57e-06 0.36 4.18e-04 0.07 8.09e-05 0.0 0.0
34 29.793 0.034 0.297 0.03 3.66e-05 0.02 2.24e-05 2.66e-04 0.0 0.0 0.0
35 34.638 0.029 0.289 0.01 1.21e-05 0.0 0.0 1.32e-04 0.0 0.0 0.0
36 43.132 0.023 0.279 0.12 1.40e-04 2.21e-04 0.0 0.08 9.25e-05 0.0 0.0
37 46.470 0.022 0.276 6.60e-05 0.0 7.94e-04 0.0 0.01 1.42e-05 0.0 0.0
38 47.985 0.021 0.275 8.64e-03 9.98e-06 4.77e-04 0.0 8.55e-03 9.88e-06 0.0 0.0
39 49.154 0.020 0.274 1.41e-03 1.63e-06 7.18e-03 8.29e-06 0.07 7.83e-05 0.0 0.0
40 51.139 0.020 0.272 7.05e-05 0.0 3.80e-03 4.39e-06 1.60e-04 0.0 0.0 0.0
41 51.440 0.019 0.272 1.54e-03 1.78e-06 2.48e-03 2.87e-06 0.02 1.96e-05 0.0 0.0
42 58.788 0.017 0.268 2.99e-04 0.0 7.07e-05 0.0 6.06e-05 0.0 0.0 0.0
43 58.878 0.017 0.268 1.23e-03 1.42e-06 3.25e-04 0.0 1.57e-04 0.0 0.0 0.0
44 59.487 0.017 0.267 7.03e-06 0.0 2.07e-03 2.39e-06 1.05e-03 1.21e-06 0.0 0.0
45 61.329 0.016 0.267 0.02 2.79e-05 2.36e-04 0.0 8.15e-03 9.42e-06 0.0 0.0
46 62.630 0.016 0.266 1.36e-04 0.0 4.51e-04 0.0 2.66e-04 0.0 0.0 0.0
47 63.234 0.016 0.266 1.59e-03 1.84e-06 0.01 1.53e-05 2.72e-03 3.15e-06 0.0 0.0
48 66.092 0.015 0.265 9.22e-04 1.07e-06 1.07e-03 1.23e-06 3.78e-03 4.37e-06 0.0 0.0
49 66.794 0.015 0.264 9.11e-05 0.0 6.51e-03 7.52e-06 0.0 0.0 0.0 0.0
50 68.381 0.015 0.264 2.96e-03 3.42e-06 6.98e-03 8.07e-06 8.82e-04 1.02e-06 0.0 0.0
Risulta 8.653e+04 8.653e+04 8.653e+04
In percentuale 100.00 100.00 100.00
Quota M Sismica x g Pos. GX Pos. GY E agg. X-X E agg. Y-Y Pos. KX Pos. KY rapp. r/Ls rapp. ex/rx rapp. ey/ry
cm daN cm cm cm cm cm cm
631.69 1418.71 1282.50 702.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0
613.00 739.88 1282.50 662.50 0.0 0.0 1282.50 662.50 1.225 0.0 0.0
549.34 2732.72 1282.50 526.25 0.0 0.0 0.0 0.0 0.0 0.0 0.0
467.00 2771.97 1282.50 350.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0
384.66 2732.72 1282.50 173.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0
321.00 427.95 1282.50 37.50 0.0 0.0 1282.50 37.50 1.225 0.0 0.0
302.31 1418.71 1282.50 -2.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0
290.00 1.053e+04 175.00 350.00 0.0 -31.25 175.00 350.00 0.837 0.0 0.0
225.00 1.056e+04 175.96 362.02 0.0 -31.25 175.00 366.94 0.830 0.006 0.009
190.00 2.507e+04 1250.00 350.00 0.0 -17.50 1250.00 350.00 0.762 0.0 0.0
95.00 2.812e+04 865.70 361.20 0.0 -31.25 856.21 350.09 0.577 0.005 0.029
Risulta 8.653e+04
Modo Frequenza Periodo Acc. Spettrale M efficace X % M efficace Y % M efficace Z % Energia Energia x v
xg xg xg
Hz sec g daN daN daN
1 1.825 0.548 0.207 6.47 7.48e-03 6.175e+04 71.4 13.49 1.56e-02 0.0 0.0
2 2.198 0.455 0.207 6.583e+04 76.1 3.92 4.53e-03 814.06 0.9 0.0 0.0
3 2.457 0.407 0.207 182.83 0.2 8879.53 10.3 35.85 4.14e-02 0.0 0.0
4 3.312 0.302 0.207 283.70 0.3 93.58 0.1 3.372e+04 39.0 0.0 0.0
5 3.405 0.294 0.207 1.985e+04 22.9 3.29 3.81e-03 1.012e+04 11.7 0.0 0.0
MANDANTE:
37
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Modo Frequenza Periodo Acc. Spettrale M efficace X % M efficace Y % M efficace Z % Energia Energia x v
xg xg xg
6 4.227 0.237 0.207 0.27 3.08e-04 1.552e+04 17.9 23.44 2.71e-02 0.0 0.0
7 4.794 0.209 0.200 342.39 0.4 28.38 3.28e-02 3.982e+04 46.0 0.0 0.0
8 6.840 0.146 0.165 0.08 8.73e-05 9.94 1.15e-02 724.13 0.8 0.0 0.0
9 7.200 0.139 0.161 9.86 1.14e-02 0.31 3.55e-04 727.00 0.8 0.0 0.0
10 7.284 0.137 0.160 0.49 5.68e-04 0.47 5.41e-04 100.65 0.1 0.0 0.0
11 8.372 0.119 0.150 0.12 1.41e-04 4.67 5.39e-03 0.52 6.02e-04 0.0 0.0
12 8.525 0.117 0.149 1.11 1.28e-03 5.24 6.06e-03 6.63 7.66e-03 0.0 0.0
13 9.104 0.110 0.145 5.63e-03 6.50e-06 36.65 4.24e-02 9.97 1.15e-02 0.0 0.0
14 9.679 0.103 0.141 0.22 2.54e-04 13.57 1.57e-02 25.70 2.97e-02 0.0 0.0
15 9.724 0.103 0.141 0.30 3.47e-04 17.52 2.03e-02 35.66 4.12e-02 0.0 0.0
16 9.984 0.100 0.139 4.28 4.94e-03 2.08 2.40e-03 296.24 0.3 0.0 0.0
17 10.189 0.098 0.138 0.06 7.29e-05 90.86 0.1 2.56 2.96e-03 0.0 0.0
18 11.269 0.089 0.133 0.10 1.15e-04 1.26 1.45e-03 0.03 3.93e-05 0.0 0.0
19 11.763 0.085 0.131 1.36e-03 1.57e-06 2.05 2.37e-03 1.01 1.17e-03 0.0 0.0
20 11.984 0.083 0.130 0.21 2.41e-04 11.69 1.35e-02 34.50 3.99e-02 0.0 0.0
21 12.239 0.082 0.129 1.23e-03 1.42e-06 0.33 3.80e-04 0.31 3.64e-04 0.0 0.0
22 12.398 0.081 0.128 0.01 1.30e-05 2.58 2.99e-03 7.74 8.95e-03 0.0 0.0
23 13.558 0.074 0.124 0.10 1.11e-04 1.23 1.42e-03 1.02 1.18e-03 0.0 0.0
24 14.107 0.071 0.123 0.95 1.10e-03 15.25 1.76e-02 2.81 3.25e-03 0.0 0.0
25 14.808 0.068 0.121 0.88 1.02e-03 1.37 1.58e-03 0.06 6.74e-05 0.0 0.0
26 15.299 0.065 0.119 0.53 6.18e-04 11.82 1.37e-02 1.35 1.56e-03 0.0 0.0
27 17.848 0.056 0.114 5.54 6.40e-03 11.47 1.33e-02 3.10 3.58e-03 0.0 0.0
28 18.720 0.053 0.113 9.41 1.09e-02 6.05 6.99e-03 0.49 5.66e-04 0.0 0.0
29 22.008 0.045 0.108 5.70e-04 0.0 2.87e-03 3.31e-06 0.04 4.38e-05 0.0 0.0
30 22.267 0.045 0.108 9.61e-03 1.11e-05 7.44e-03 8.59e-06 0.02 2.16e-05 0.0 0.0
31 23.939 0.042 0.106 0.02 1.98e-05 0.95 1.10e-03 0.33 3.83e-04 0.0 0.0
32 27.415 0.036 0.103 5.46 6.31e-03 6.11e-03 7.07e-06 0.02 1.84e-05 0.0 0.0
33 28.410 0.035 0.102 3.69e-03 4.27e-06 0.40 4.59e-04 0.08 8.77e-05 0.0 0.0
34 30.448 0.033 0.101 0.02 2.10e-05 8.46e-03 9.78e-06 1.33e-03 1.54e-06 0.0 0.0
35 34.131 0.029 0.099 0.01 1.16e-05 0.01 1.57e-05 6.45e-05 0.0 0.0 0.0
36 43.082 0.023 0.096 0.13 1.46e-04 9.89e-05 0.0 0.09 1.02e-04 0.0 0.0
37 46.546 0.021 0.095 9.86e-04 1.14e-06 7.18e-04 0.0 4.68e-03 5.41e-06 0.0 0.0
38 47.621 0.021 0.094 6.24e-03 7.21e-06 9.22e-04 1.07e-06 3.18e-03 3.68e-06 0.0 0.0
39 49.244 0.020 0.094 1.62e-03 1.87e-06 5.64e-03 6.52e-06 0.08 9.32e-05 0.0 0.0
40 50.129 0.020 0.094 2.29e-04 0.0 4.17e-03 4.82e-06 8.67e-03 1.00e-05 0.0 0.0
41 51.145 0.020 0.094 2.47e-03 2.86e-06 5.46e-05 0.0 4.94e-03 5.71e-06 0.0 0.0
42 58.435 0.017 0.092 1.06e-06 0.0 9.57e-04 1.11e-06 5.99e-04 0.0 0.0 0.0
43 58.754 0.017 0.092 8.74e-05 0.0 6.56e-06 0.0 1.06e-04 0.0 0.0 0.0
44 58.844 0.017 0.092 1.62e-03 1.87e-06 1.10e-04 0.0 4.11e-05 0.0 0.0 0.0
45 60.831 0.016 0.092 0.03 3.15e-05 0.0 0.0 4.98e-03 5.75e-06 0.0 0.0
46 62.190 0.016 0.092 4.85e-04 0.0 6.52e-03 7.54e-06 3.87e-03 4.47e-06 0.0 0.0
47 63.864 0.016 0.091 7.85e-04 0.0 8.38e-04 0.0 1.88e-03 2.17e-06 0.0 0.0
48 64.767 0.015 0.091 5.66e-04 0.0 7.58e-05 0.0 2.49e-03 2.88e-06 0.0 0.0
49 66.234 0.015 0.091 5.08e-04 0.0 0.02 1.75e-05 1.66e-04 0.0 0.0 0.0
50 67.388 0.015 0.091 3.25e-04 0.0 3.98e-04 0.0 2.97e-05 0.0 0.0 0.0
Risulta 8.653e+04 8.653e+04 8.653e+04
In percentuale 100.00 100.00 100.00
MANDANTE:
38
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Quota M Sismica x g Pos. GX Pos. GY E agg. X-X E agg. Y-Y Pos. KX Pos. KY rapp. r/Ls rapp. ex/rx rapp. ey/ry
cm daN cm cm cm cm cm cm
631.69 1418.71 1282.50 702.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0
613.00 739.88 1282.50 662.50 0.0 0.0 1282.50 662.50 1.225 0.0 0.0
549.34 2732.72 1282.50 526.25 0.0 0.0 0.0 0.0 0.0 0.0 0.0
467.00 2771.97 1282.50 350.00 0.0 0.0 0.0 0.0 0.0 0.0 0.0
384.66 2732.72 1282.50 173.75 0.0 0.0 0.0 0.0 0.0 0.0 0.0
321.00 427.95 1282.50 37.50 0.0 0.0 1282.50 37.50 1.225 0.0 0.0
302.31 1418.71 1282.50 -2.50 0.0 0.0 0.0 0.0 0.0 0.0 0.0
290.00 1.053e+04 175.00 350.00 0.0 31.25 175.00 350.00 0.837 0.0 0.0
225.00 1.056e+04 175.96 362.02 0.0 31.25 175.00 366.94 0.830 0.006 0.009
190.00 2.507e+04 1250.00 350.00 0.0 17.50 1250.00 350.00 0.762 0.0 0.0
95.00 2.812e+04 865.70 361.20 0.0 31.25 856.21 350.09 0.577 0.005 0.029
Risulta 8.653e+04
Modo Frequenza Periodo Acc. Spettrale M efficace X % M efficace Y % M efficace Z % Energia Energia x v
xg xg xg
Hz sec g daN daN daN
1 1.824 0.548 0.207 288.40 0.3 6.146e+04 71.0 7.52 8.69e-03 0.0 0.0
2 2.195 0.456 0.207 6.429e+04 74.3 864.86 1.0 841.35 1.0 0.0 0.0
3 2.467 0.405 0.207 1261.79 1.5 8296.56 9.6 1.26e-03 1.46e-06 0.0 0.0
4 3.310 0.302 0.207 573.89 0.7 86.10 9.95e-02 3.174e+04 36.7 0.0 0.0
5 3.396 0.294 0.207 1.971e+04 22.8 12.60 1.46e-02 1.215e+04 14.0 0.0 0.0
6 4.227 0.237 0.207 9.09 1.05e-02 1.553e+04 17.9 14.28 1.65e-02 0.0 0.0
7 4.795 0.209 0.200 358.03 0.4 26.16 3.02e-02 3.980e+04 46.0 0.0 0.0
8 6.841 0.146 0.165 0.20 2.36e-04 9.99 1.15e-02 720.89 0.8 0.0 0.0
9 7.200 0.139 0.161 5.28 6.10e-03 0.33 3.81e-04 730.68 0.8 0.0 0.0
10 7.284 0.137 0.160 0.27 3.12e-04 0.47 5.45e-04 100.39 0.1 0.0 0.0
11 8.373 0.119 0.150 0.08 9.75e-05 4.74 5.48e-03 0.45 5.21e-04 0.0 0.0
12 8.524 0.117 0.149 0.02 2.83e-05 5.52 6.38e-03 7.47 8.64e-03 0.0 0.0
13 9.109 0.110 0.145 0.47 5.49e-04 35.61 4.12e-02 8.43 9.74e-03 0.0 0.0
14 9.677 0.103 0.141 0.10 1.16e-04 15.01 1.73e-02 31.85 3.68e-02 0.0 0.0
15 9.724 0.103 0.141 0.18 2.13e-04 16.72 1.93e-02 32.16 3.72e-02 0.0 0.0
16 10.006 0.100 0.139 5.81 6.71e-03 5.67 6.55e-03 294.95 0.3 0.0 0.0
17 10.205 0.098 0.138 1.83 2.12e-03 86.97 0.1 0.16 1.88e-04 0.0 0.0
18 11.219 0.089 0.133 0.20 2.27e-04 0.79 9.07e-04 0.03 3.42e-05 0.0 0.0
19 11.763 0.085 0.131 9.14e-03 1.06e-05 1.97 2.27e-03 0.97 1.12e-03 0.0 0.0
20 11.999 0.083 0.130 3.00e-03 3.47e-06 12.77 1.48e-02 33.95 3.92e-02 0.0 0.0
21 12.237 0.082 0.129 2.37e-04 0.0 0.36 4.12e-04 0.58 6.75e-04 0.0 0.0
22 12.388 0.081 0.128 0.01 1.19e-05 2.55 2.94e-03 8.01 9.25e-03 0.0 0.0
23 13.498 0.074 0.124 0.19 2.25e-04 0.73 8.48e-04 0.13 1.52e-04 0.0 0.0
24 14.208 0.070 0.122 6.38e-03 7.37e-06 17.91 2.07e-02 4.70 5.43e-03 0.0 0.0
25 14.825 0.067 0.121 0.94 1.08e-03 1.45 1.68e-03 0.13 1.55e-04 0.0 0.0
26 15.245 0.066 0.120 0.97 1.13e-03 7.86 9.09e-03 0.08 9.34e-05 0.0 0.0
27 17.963 0.056 0.114 4.93 5.70e-03 15.19 1.76e-02 2.87 3.32e-03 0.0 0.0
28 18.626 0.054 0.113 10.01 1.16e-02 3.51 4.06e-03 0.63 7.32e-04 0.0 0.0
29 22.009 0.045 0.108 3.56e-03 4.12e-06 2.57e-03 2.97e-06 0.04 4.26e-05 0.0 0.0
30 22.266 0.045 0.108 3.82e-03 4.41e-06 7.94e-03 9.17e-06 0.02 2.23e-05 0.0 0.0
31 23.938 0.042 0.106 8.46e-03 9.77e-06 0.94 1.08e-03 0.33 3.80e-04 0.0 0.0
32 27.417 0.036 0.103 5.49 6.35e-03 0.01 1.36e-05 0.02 1.96e-05 0.0 0.0
33 28.417 0.035 0.102 0.01 1.41e-05 0.40 4.63e-04 0.08 9.53e-05 0.0 0.0
34 30.449 0.033 0.101 0.02 2.79e-05 7.96e-03 9.20e-06 1.28e-03 1.48e-06 0.0 0.0
35 34.128 0.029 0.099 0.01 1.53e-05 0.01 1.55e-05 3.64e-05 0.0 0.0 0.0
36 43.104 0.023 0.096 0.12 1.36e-04 2.86e-04 0.0 0.09 9.87e-05 0.0 0.0
37 46.550 0.021 0.095 5.72e-04 0.0 6.91e-04 0.0 4.51e-03 5.22e-06 0.0 0.0
38 47.645 0.021 0.094 9.85e-03 1.14e-05 8.78e-04 1.01e-06 2.94e-03 3.40e-06 0.0 0.0
39 49.258 0.020 0.094 1.60e-03 1.85e-06 5.58e-03 6.45e-06 0.08 9.35e-05 0.0 0.0
40 50.129 0.020 0.094 3.76e-04 0.0 4.35e-03 5.03e-06 9.29e-03 1.07e-05 0.0 0.0
41 51.175 0.020 0.093 3.54e-04 0.0 4.54e-05 0.0 4.86e-03 5.61e-06 0.0 0.0
42 58.406 0.017 0.092 2.74e-04 0.0 9.82e-04 1.14e-06 6.06e-04 0.0 0.0 0.0
MANDANTE:
39
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Modo Frequenza Periodo Acc. Spettrale M efficace X % M efficace Y % M efficace Z % Energia Energia x v
xg xg xg
43 58.762 0.017 0.092 1.42e-03 1.65e-06 1.36e-05 0.0 6.55e-05 0.0 0.0 0.0
44 58.832 0.017 0.092 1.38e-03 1.59e-06 1.16e-04 0.0 8.62e-05 0.0 0.0 0.0
45 60.903 0.016 0.092 0.02 2.76e-05 0.0 0.0 5.60e-03 6.48e-06 0.0 0.0
46 62.446 0.016 0.092 2.78e-04 0.0 8.19e-03 9.46e-06 3.53e-03 4.08e-06 0.0 0.0
47 63.883 0.016 0.091 4.86e-04 0.0 4.67e-04 0.0 1.77e-03 2.04e-06 0.0 0.0
48 64.795 0.015 0.091 5.01e-04 0.0 6.67e-06 0.0 2.40e-03 2.78e-06 0.0 0.0
49 66.245 0.015 0.091 2.54e-04 0.0 0.02 1.83e-05 1.28e-04 0.0 0.0 0.0
50 67.305 0.015 0.091 1.22e-04 0.0 0.0 0.0 2.24e-04 0.0 0.0 0.0
Risulta 8.653e+04 8.653e+04 8.653e+04
In percentuale 100.00 100.00 100.00
Quota M Sismica x g Pos. GX Pos. GY E agg. X-X E agg. Y-Y Pos. KX Pos. KY rapp. r/Ls rapp. ex/rx rapp. ey/ry
cm daN cm cm cm cm cm cm
631.69 1418.71 1282.50 702.50 93.00 0.0 0.0 0.0 0.0 0.0 0.0
613.00 739.88 1282.50 662.50 93.00 0.0 1282.50 662.50 1.225 0.0 0.0
549.34 2732.72 1282.50 526.25 93.00 0.0 0.0 0.0 0.0 0.0 0.0
467.00 2771.97 1282.50 350.00 93.00 0.0 0.0 0.0 0.0 0.0 0.0
384.66 2732.72 1282.50 173.75 93.00 0.0 0.0 0.0 0.0 0.0 0.0
321.00 427.95 1282.50 37.50 93.00 0.0 1282.50 37.50 1.225 0.0 0.0
302.31 1418.71 1282.50 -2.50 93.00 0.0 0.0 0.0 0.0 0.0 0.0
290.00 1.053e+04 175.00 350.00 13.75 0.0 175.00 350.00 0.837 0.0 0.0
225.00 1.056e+04 175.96 362.02 13.75 0.0 175.00 366.94 0.830 0.006 0.009
190.00 2.507e+04 1250.00 350.00 77.50 0.0 1250.00 350.00 0.762 0.0 0.0
95.00 2.812e+04 865.70 361.20 108.75 0.0 856.21 350.09 0.577 0.005 0.029
Risulta 8.653e+04
Modo Frequenza Periodo Acc. Spettrale M efficace X % M efficace Y % M efficace Z % Energia Energia x v
xg xg xg
Hz sec g daN daN daN
1 1.882 0.531 0.207 56.33 6.51e-02 6.141e+04 71.0 12.85 1.49e-02 0.0 0.0
2 2.195 0.456 0.207 6.386e+04 73.8 548.23 0.6 831.47 1.0 0.0 0.0
3 2.343 0.427 0.207 2001.75 2.3 8808.63 10.2 0.74 8.54e-04 0.0 0.0
4 3.311 0.302 0.207 423.59 0.5 74.90 8.66e-02 3.269e+04 37.8 0.0 0.0
5 3.399 0.294 0.207 1.979e+04 22.9 12.92 1.49e-02 1.120e+04 12.9 0.0 0.0
6 4.190 0.239 0.207 5.82 6.72e-03 1.538e+04 17.8 33.62 3.89e-02 0.0 0.0
7 4.793 0.209 0.200 349.15 0.4 39.75 4.59e-02 3.971e+04 45.9 0.0 0.0
8 6.886 0.145 0.165 0.13 1.45e-04 14.52 1.68e-02 1090.66 1.3 0.0 0.0
9 7.076 0.141 0.162 8.14 9.41e-03 3.11 3.59e-03 509.68 0.6 0.0 0.0
10 7.308 0.137 0.160 0.26 3.01e-04 0.12 1.41e-04 4.77 5.51e-03 0.0 0.0
11 8.196 0.122 0.151 0.04 4.92e-05 21.01 2.43e-02 2.14 2.48e-03 0.0 0.0
12 8.635 0.116 0.148 0.14 1.62e-04 13.84 1.60e-02 16.65 1.92e-02 0.0 0.0
13 9.114 0.110 0.145 5.98e-03 6.91e-06 4.88 5.64e-03 7.73e-03 8.94e-06 0.0 0.0
14 9.441 0.106 0.142 0.01 1.72e-05 46.06 5.32e-02 4.62 5.34e-03 0.0 0.0
15 9.815 0.102 0.140 2.41 2.79e-03 43.92 5.08e-02 250.27 0.3 0.0 0.0
16 10.051 0.099 0.139 3.79 4.38e-03 21.51 2.49e-02 121.26 0.1 0.0 0.0
MANDANTE:
40
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Modo Frequenza Periodo Acc. Spettrale M efficace X % M efficace Y % M efficace Z % Energia Energia x v
xg xg xg
17 10.541 0.095 0.136 3.45e-03 3.99e-06 0.13 1.52e-04 0.05 6.00e-05 0.0 0.0
18 11.031 0.091 0.134 0.04 4.11e-05 24.29 2.81e-02 13.82 1.60e-02 0.0 0.0
19 11.472 0.087 0.132 0.03 3.56e-05 15.95 1.84e-02 16.51 1.91e-02 0.0 0.0
20 11.829 0.085 0.130 0.03 3.07e-05 2.94 3.39e-03 9.50 1.10e-02 0.0 0.0
21 12.275 0.081 0.129 3.07e-03 3.55e-06 4.48 5.18e-03 8.10 9.36e-03 0.0 0.0
22 13.787 0.073 0.123 3.99e-03 4.61e-06 1.18 1.37e-03 0.45 5.22e-04 0.0 0.0
23 13.916 0.072 0.123 0.17 1.97e-04 0.64 7.37e-04 0.35 4.05e-04 0.0 0.0
24 14.410 0.069 0.122 0.12 1.42e-04 6.99 8.07e-03 4.58 5.30e-03 0.0 0.0
25 14.500 0.069 0.121 0.03 3.98e-05 2.87 3.31e-03 1.11 1.29e-03 0.0 0.0
26 15.181 0.066 0.120 2.17e-03 2.51e-06 11.79 1.36e-02 0.90 1.04e-03 0.0 0.0
27 17.521 0.057 0.115 3.67 4.24e-03 11.31 1.31e-02 2.82 3.26e-03 0.0 0.0
28 18.443 0.054 0.113 12.70 1.47e-02 1.97 2.27e-03 1.12 1.30e-03 0.0 0.0
29 21.932 0.046 0.108 3.82e-03 4.42e-06 0.04 4.72e-05 0.02 1.98e-05 0.0 0.0
30 22.503 0.044 0.108 7.43e-03 8.58e-06 0.03 3.67e-05 0.02 2.13e-05 0.0 0.0
31 23.544 0.042 0.106 6.45e-03 7.45e-06 0.48 5.54e-04 0.33 3.84e-04 0.0 0.0
32 27.393 0.037 0.103 5.46 6.31e-03 2.21e-03 2.55e-06 0.02 2.45e-05 0.0 0.0
33 28.064 0.036 0.103 0.03 3.85e-05 0.40 4.62e-04 0.09 1.00e-04 0.0 0.0
34 31.162 0.032 0.101 0.01 1.72e-05 5.57e-03 6.44e-06 1.72e-03 1.99e-06 0.0 0.0
35 33.699 0.030 0.099 0.01 1.41e-05 0.04 4.89e-05 9.26e-05 0.0 0.0 0.0
36 43.022 0.023 0.096 0.12 1.39e-04 1.74e-04 0.0 0.09 1.05e-04 0.0 0.0
37 46.527 0.021 0.095 4.86e-03 5.62e-06 5.73e-04 0.0 4.67e-04 0.0 0.0 0.0
38 47.301 0.021 0.094 5.81e-03 6.72e-06 1.87e-03 2.16e-06 3.86e-04 0.0 0.0 0.0
39 48.901 0.020 0.094 3.44e-06 0.0 5.62e-03 6.50e-06 0.04 4.57e-05 0.0 0.0
40 49.429 0.020 0.094 1.40e-03 1.62e-06 2.14e-03 2.47e-06 0.06 6.96e-05 0.0 0.0
41 51.040 0.020 0.094 1.03e-03 1.19e-06 2.20e-05 0.0 8.25e-04 0.0 0.0 0.0
42 57.605 0.017 0.092 9.40e-04 1.09e-06 3.04e-04 0.0 3.98e-04 0.0 0.0 0.0
43 58.555 0.017 0.092 1.16e-04 0.0 3.93e-04 0.0 0.0 0.0 0.0 0.0
44 59.011 0.017 0.092 7.20e-03 8.32e-06 1.56e-05 0.0 1.56e-04 0.0 0.0 0.0
45 60.435 0.017 0.092 0.02 2.32e-05 2.71e-04 0.0 2.21e-03 2.56e-06 0.0 0.0
46 61.625 0.016 0.092 3.73e-04 0.0 5.26e-03 6.08e-06 6.35e-03 7.34e-06 0.0 0.0
47 63.446 0.016 0.091 6.07e-04 0.0 0.0 0.0 2.12e-03 2.45e-06 0.0 0.0
48 65.157 0.015 0.091 1.26e-03 1.45e-06 9.22e-03 1.07e-05 1.08e-03 1.24e-06 0.0 0.0
49 65.625 0.015 0.091 0.0 0.0 0.02 1.77e-05 2.57e-04 0.0 0.0 0.0
50 67.422 0.015 0.091 8.38e-06 0.0 1.34e-05 0.0 2.94e-03 3.40e-06 0.0 0.0
Risulta 8.653e+04 8.653e+04 8.653e+04
In percentuale 100.00 100.00 100.00
Quota M Sismica x g Pos. GX Pos. GY E agg. X-X E agg. Y-Y Pos. KX Pos. KY rapp. r/Ls rapp. ex/rx rapp. ey/ry
cm daN cm cm cm cm cm cm
631.69 1418.71 1282.50 702.50 -93.00 0.0 0.0 0.0 0.0 0.0 0.0
613.00 739.88 1282.50 662.50 -93.00 0.0 1282.50 662.50 1.225 0.0 0.0
549.34 2732.72 1282.50 526.25 -93.00 0.0 0.0 0.0 0.0 0.0 0.0
467.00 2771.97 1282.50 350.00 -93.00 0.0 0.0 0.0 0.0 0.0 0.0
384.66 2732.72 1282.50 173.75 -93.00 0.0 0.0 0.0 0.0 0.0 0.0
MANDANTE:
41
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Quota M Sismica x g Pos. GX Pos. GY E agg. X-X E agg. Y-Y Pos. KX Pos. KY rapp. r/Ls rapp. ex/rx rapp. ey/ry
321.00 427.95 1282.50 37.50 -93.00 0.0 1282.50 37.50 1.225 0.0 0.0
302.31 1418.71 1282.50 -2.50 -93.00 0.0 0.0 0.0 0.0 0.0 0.0
290.00 1.053e+04 175.00 350.00 -13.75 0.0 175.00 350.00 0.837 0.0 0.0
225.00 1.056e+04 175.96 362.02 -13.75 0.0 175.00 366.94 0.830 0.006 0.009
190.00 2.507e+04 1250.00 350.00 -77.50 0.0 1250.00 350.00 0.762 0.0 0.0
95.00 2.812e+04 865.70 361.20 -108.75 0.0 856.21 350.09 0.577 0.005 0.029
Risulta 8.653e+04
Modo Frequenza Periodo Acc. Spettrale M efficace X % M efficace Y % M efficace Z % Energia Energia x v
xg xg xg
Hz sec g daN daN daN
1 1.770 0.565 0.207 44.29 5.12e-02 6.358e+04 73.5 8.79 1.02e-02 0.0 0.0
2 2.198 0.455 0.207 6.560e+04 75.8 144.23 0.2 831.83 1.0 0.0 0.0
3 2.600 0.385 0.207 278.31 0.3 6762.62 7.8 36.42 4.21e-02 0.0 0.0
4 3.311 0.302 0.207 462.76 0.5 104.12 0.1 3.244e+04 37.5 0.0 0.0
5 3.399 0.294 0.207 1.976e+04 22.8 3.56 4.12e-03 1.139e+04 13.2 0.0 0.0
6 4.285 0.233 0.207 1.51 1.75e-03 1.564e+04 18.1 10.21 1.18e-02 0.0 0.0
7 4.796 0.209 0.200 350.70 0.4 18.63 2.15e-02 3.989e+04 46.1 0.0 0.0
8 6.764 0.148 0.166 0.27 3.15e-04 14.48 1.67e-02 633.54 0.7 0.0 0.0
9 7.227 0.138 0.161 1.85 2.14e-03 0.09 1.08e-04 200.08 0.2 0.0 0.0
10 7.364 0.136 0.159 5.10 5.89e-03 0.63 7.23e-04 631.94 0.7 0.0 0.0
11 8.036 0.124 0.153 0.02 1.92e-05 58.41 6.75e-02 29.58 3.42e-02 0.0 0.0
12 8.727 0.115 0.147 0.07 8.19e-05 7.29 8.42e-03 1.19 1.38e-03 0.0 0.0
13 8.997 0.111 0.145 1.17 1.36e-03 7.42 8.57e-03 61.54 7.11e-02 0.0 0.0
14 9.137 0.109 0.144 0.01 1.54e-05 0.50 5.74e-04 2.31 2.67e-03 0.0 0.0
15 10.050 0.100 0.139 5.31 6.13e-03 2.18 2.52e-03 285.25 0.3 0.0 0.0
16 10.184 0.098 0.138 0.12 1.37e-04 75.08 8.68e-02 3.04 3.52e-03 0.0 0.0
17 10.627 0.094 0.136 5.82e-03 6.72e-06 13.23 1.53e-02 3.22 3.73e-03 0.0 0.0
18 10.925 0.092 0.134 4.72e-03 5.45e-06 37.44 4.33e-02 17.08 1.97e-02 0.0 0.0
19 11.402 0.088 0.132 0.02 2.39e-05 0.68 7.86e-04 3.23 3.74e-03 0.0 0.0
20 11.872 0.084 0.130 1.35e-03 1.56e-06 4.69 5.42e-03 7.05 8.15e-03 0.0 0.0
21 12.258 0.082 0.129 0.03 3.65e-05 2.21 2.56e-03 24.76 2.86e-02 0.0 0.0
22 13.340 0.075 0.125 8.00e-03 9.25e-06 7.68 8.88e-03 6.45 7.46e-03 0.0 0.0
23 13.935 0.072 0.123 0.17 1.98e-04 0.29 3.34e-04 1.91 2.21e-03 0.0 0.0
24 14.265 0.070 0.122 0.18 2.13e-04 4.71 5.45e-03 0.18 2.10e-04 0.0 0.0
25 14.597 0.069 0.121 0.11 1.33e-04 2.78 3.21e-03 0.01 1.27e-05 0.0 0.0
26 15.335 0.065 0.119 0.08 9.26e-05 14.50 1.68e-02 6.50e-03 7.51e-06 0.0 0.0
27 18.117 0.055 0.114 13.18 1.52e-02 6.38 7.38e-03 3.31 3.83e-03 0.0 0.0
28 19.015 0.053 0.112 3.00 3.47e-03 15.98 1.85e-02 4.98e-05 0.0 0.0 0.0
29 21.994 0.045 0.108 1.72e-03 1.99e-06 0.02 2.19e-05 0.07 7.72e-05 0.0 0.0
30 22.149 0.045 0.108 3.81e-03 4.40e-06 0.03 3.39e-05 6.83e-03 7.90e-06 0.0 0.0
31 24.448 0.041 0.106 0.03 3.16e-05 1.83 2.12e-03 0.33 3.80e-04 0.0 0.0
32 27.429 0.036 0.103 5.43 6.27e-03 0.02 2.35e-05 0.01 1.54e-05 0.0 0.0
33 28.761 0.035 0.102 3.09e-03 3.57e-06 0.36 4.18e-04 0.07 8.09e-05 0.0 0.0
34 29.793 0.034 0.101 0.03 3.66e-05 0.02 2.24e-05 2.66e-04 0.0 0.0 0.0
35 34.638 0.029 0.099 0.01 1.21e-05 0.0 0.0 1.32e-04 0.0 0.0 0.0
36 43.132 0.023 0.096 0.12 1.40e-04 2.21e-04 0.0 0.08 9.25e-05 0.0 0.0
37 46.470 0.022 0.095 6.60e-05 0.0 7.94e-04 0.0 0.01 1.42e-05 0.0 0.0
38 47.985 0.021 0.094 8.64e-03 9.98e-06 4.77e-04 0.0 8.55e-03 9.88e-06 0.0 0.0
39 49.154 0.020 0.094 1.41e-03 1.63e-06 7.18e-03 8.29e-06 0.07 7.83e-05 0.0 0.0
40 51.139 0.020 0.094 7.05e-05 0.0 3.80e-03 4.39e-06 1.60e-04 0.0 0.0 0.0
41 51.440 0.019 0.093 1.54e-03 1.78e-06 2.48e-03 2.87e-06 0.02 1.96e-05 0.0 0.0
42 58.788 0.017 0.092 2.99e-04 0.0 7.07e-05 0.0 6.06e-05 0.0 0.0 0.0
43 58.878 0.017 0.092 1.23e-03 1.42e-06 3.25e-04 0.0 1.57e-04 0.0 0.0 0.0
44 59.487 0.017 0.092 7.03e-06 0.0 2.07e-03 2.39e-06 1.05e-03 1.21e-06 0.0 0.0
45 61.329 0.016 0.092 0.02 2.79e-05 2.36e-04 0.0 8.15e-03 9.42e-06 0.0 0.0
46 62.630 0.016 0.091 1.36e-04 0.0 4.51e-04 0.0 2.66e-04 0.0 0.0 0.0
47 63.234 0.016 0.091 1.59e-03 1.84e-06 0.01 1.53e-05 2.72e-03 3.15e-06 0.0 0.0
48 66.092 0.015 0.091 9.22e-04 1.07e-06 1.07e-03 1.23e-06 3.78e-03 4.37e-06 0.0 0.0
49 66.794 0.015 0.091 9.11e-05 0.0 6.51e-03 7.52e-06 0.0 0.0 0.0 0.0
50 68.381 0.015 0.091 2.96e-03 3.42e-06 6.98e-03 8.07e-06 8.82e-04 1.02e-06 0.0 0.0
Risulta 8.653e+04 8.653e+04 8.653e+04
MANDANTE:
42
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Modo Frequenza Periodo Acc. Spettrale M efficace X % M efficace Y % M efficace Z % Energia Energia x v
xg xg xg
In percentuale 100.00 100.00 100.00
MANDANTE:
43
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Travi
La sollecitazione “momento flettente” viene calcolata in base all’effettiva analisi globale della
struttura, dovuta ai carichi presenti e derivante dalle combinazioni di carico relative.
I momenti resistenti per la verifica vengono calcolati in base alle armature effettivamente presenti
nella sezione, secondo le indicazioni presenti al cap. 4.1.2.1.2 del DM2008.
La sollecitazione “taglio” viene invece calcolata sommando al contibuto dovuto ai carichi
effettivamente agenti, secondo le varie combinazioni di carico, il valore corrispondente alla
formazione delle cerniere plastiche prodotte dai relativi momenti resistenti, amplificati per un
valore di sovraresistenza pari a 1 per strutture di classe di duttilità B, secondo quanto definito al
par.7.4.4.1.1.
Il valore resistente del taglio per la verifica viene calcolato in base a quanto definito al par.
4.1.2.1.3, tenendo conto delle indicazioni relative alle “zone critiche”, in accordo ai par. 7.4.4.1.2.2,
7.4.6.1.1 e 7.4.6.2.1.
Pilastri
Per evitare la plasticizzazione dei pilastri viene adottato il criterio della gerarchia delle resistenze
per ciascun nodo trave-pilastro, eccezion fatta per i nodi delle sezioni di sommità dell’ultimo piano.
Secondo tale criterio, per ciascun nodo, la somma dei momenti resistenti dei pilastri deve essere
maggiore della somma dei momenti resistenti delle travi, aumentata di un fattore di sovraresistenza
pari ad 1,10 per le strutture in classe di duttilità B.
Anche le sollecitazioni di taglio da utilizzare nelle verifiche vengono ricavati dai momenti
resistenti, secondo quanto indicato nel par.7.4.4.2.1., tenendo conto delle indicazioni relative alle
“zone critiche”, in accordo ai par. 7.4.6.1.2. e 7.4.6.2.2.
MANDANTE:
44
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
45
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
46
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
47
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
48
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Setti
MANDANTE:
49
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
50
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
51
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Pressione platea
Verifica N/M
MANDANTE:
52
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Verifica 25
Acciaio
MANDANTE:
53
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
54
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
55
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
56
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
57
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
In tabella vengono riportati i valori di interesse per il controllo degli stati limite d'esercizio.
In particolare vengono riportati, in relazione al tipo di elemento strutturale, i risultati relativi alle tre
categorie di combinazione considerate:
Combinazioni rare
Combinazioni frequenti
Combinazioni quasi permanenti.
I valori di interesse sono i seguenti:
rRfck rapporto tra la massima compressione nel calcestruzzo e la tensione fck in
combinazioni rare [normalizzato a 1]
rRfyk rapporto tra la massima tensione nell’acciaio e la tensione fyk in
combinazioni rare [normalizzato a 1]
rPfck rapporto tra la massima compressione nel calcestruzzo e la tensione fck in
combinazioni quasi permanenti [normalizzato a 1]
wR apertura caratteristica delle fessure in combinazioni rare [mm]
wF apertura caratteristica delle fessure in combinazioni frequenti [mm]
wP apertura caratteristica delle fessure in combinazioni quasi permanenti
[mm]
dR massima deformazione in combinazioni rare
dF massima deformazione in combinazioni frequenti
dP massima deformazione in combinazioni quasi permanenti
Per ognuno dei nove valori soprariportati viene indicata (Rif.cmb) la combinazione in cui si è
verificato.
In relazione al tipo di elemento strutturale i valori sono selezionati nel modo seguente:
pilastri rRfck rRfyk rPfck per sezioni significative
travi rRfck rRfyk rPfck per sezioni significative
wR wF wP per sezioni significative
dR dF dP massimi in campata
setti e gusci rRfck rRfyk rPfck massimi nei nodi dell’elemento
wR wF wP massimi nei nodi dell’elemento
Si precisa che i valori di massima deformazione per travi sono riferiti al piano verticale (piano
locale 1-2 con momenti flettenti 3-3).
MANDANTE:
58
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
59
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
60
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
61
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
62
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
63
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Cmb numero della combinazione di carico (nel caso che essa sia di S.L.U. è riportata la
tipologia);
Strato Rot. strato nel quale si attinge il minor valore di portanza rispetto al numero di strati
interessati dal cuneo di rottura;
Ver.TB valore limite della resistenza a scorrimento nella direzione parallela alla sezione
trasversale dell'elemento;
S.T.B / TB rapporto tra lo sforzo di taglio agente e il valore limite della resistenza a
scorrimento nella direzione parallela alla sezione trasversale dell'elemento
(verifica positiva se il rapporto è < 1.0);
Ver.TL valore limite della resistenza a scorrimento nella direzione parallela allo sviluppo
longitudinale dell'elemento;
S.T.L / TL rapporto tra lo sforzo di taglio agente e il valore limite della resistenza a
MANDANTE:
64
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Nel caso in cui si è scelto di determinare la portanza anche per gli elementi platea viene riportata un
ulteriore elemento nel quale sono riportate le verifiche di portanza del plinto equivalente alla Macro
in esame
Ai fini dei calcoli di portanza le sollecitazioni SLU sismiche saranno considerate moltiplicate per un
coef. GammaRD = 1.10
MANDANTE:
65
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
TABULATI DI CALCOLO
PARAMETRI DI CALCOLO
Coefficienti parziali di sicurezza per Tensioni Ammissibili, SLE e SLD nel calcolo della portanza per fondazioni superficiali :
Coeff. parziale di sicurezza Fc (statico) : 2.50
Coeff. parziale di sicurezza Fq (statico) : 2.50
Coeff. parziale di sicurezza Fg (statico) : 2.50
Coeff. parziale di sicurezza Fc (sismico) : 3.00
Coeff. parziale di sicurezza Fq (sismico) : 3.00
Coeff. parziale di sicurezza Fg (sismico) : 3.00
Coefficienti parziali di sicurezza per SLU nel calcolo della portanza per fondazioni superficiali :
Coeff. parz. di sicurezza Prop. Materiali per Tan(fi) (statico) : 1.25
Coeff. parz. di sicurezza Prop. Materiali per c' (statico) : 1.25
Coeff. parz. di sicurezza Prop. Materiali per Cu (statico) : 1.40
Coeff. parz. di sicurezza Prop. Materiali per Tan(fi) (sismico) : 1.25
Coeff. parz. di sicurezza Prop. Materiali per c' (sismico) : 1.25
Coeff. parz. di sicurezza Prop. Materiali per Cu (sismico) : 1.40
Coeff. R1 capacità portante : 1.00
Coeff. R2 capacità portante : 1.80
Coeff. R3 capacità portante : 2.30
Coeff. R1 scorrimento : 1.00
Coeff. R2 scorrimento : 1.10
Coeff. R3 scorrimento : 1.10
ARCHIVIO STRATIGRAFIE
MANDANTE:
66
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Strato n ° Quota di riferimento Spessore Indice / Descrizione terreno Effetto Attr. Neg.
1 da 0.0 a -200.0 cm. 200.0 cm. 001 / Strato 1 Assente
2 da -200.0 a -3000.0 cm. 2800.0 cm. 002 / Strato 2 Assente
ARCHIVIO TERRENI
Indice / Descrizione terreno : 001 / Strato 1
Comportamento del terreno : Condizione drenata
Peso Spec. Peso Spec. Sat. Angolo Res. Coesione Coes. non Dren. Mod. Edo. Mod. Ela. Poisson D.R. RQD C. Ades.
daN/cmc daN/cmc Gradi (°) daN/cmq daN/cmq daN/cmq daN/cmq % %
1.870 E-3 1.870 E-3 39.000 0.000 0.000 492.000 393.735 0.270 50.0 0.0 1.00
Peso Spec. Peso Spec. Sat. Angolo Res. Coesione Coes. non Dren. Mod. Edo. Mod. Ela. Poisson D.R. RQD C. Ades.
daN/cmc daN/cmc Gradi (°) daN/cmq daN/cmq daN/cmq daN/cmq % %
1.690 E-3 1.790 E-3 22.000 0.100 0.565 88.000 419.000 0.500 60.0 0.0 0.50
MANDANTE:
67
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
68
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Elemento Tipologia Indice Strat. Prof. Fon. Base Eq. Spessore Lung. Eq. Lung. Travata Eq.
n° cm cm cm cm cm
MACRO N° 1 Macro-Platea 001 15.00 598.32 30.00 1813.41 1813.41
MACRO N° 2 Macro-Platea 001 35.00 350.00 70.00 700.00 700.00
MACRO N° 3 Macro-Platea 001 35.00 350.00 70.00 700.00 700.00
Cmb Tipologia Sismica Ecc. B Ecc. L S. Taglio B S. Taglio L S. Normale T.T. min T.T. max
n° cm cm daN daN daN daN/cmq daN/cmq
018 SLU STR No -41.6 18.4 0.2 7191.6 -286935.7 -0.206 -0.317
066 SLV A1 Si 2.1 22.1 28598.2 10908.2 -175658.1 -0.135 -0.188
089 SLV A1 Si -59.4 -59.4 8142.3 -36063.9 -179490.8 -0.089 -0.252
Cmb Strato Rot. Ver. TB S.T.B / TB Ver. TL S.T.L / TL Sgm. Lt. Qlim q Qlim g Qlim c Qres T QLIM T.T. / QLIM
n° n° daN daN daN/cmq daN/cmq daN/cmq daN/cmq daN/cmq daN/cmq
018/SLU STR 2 di 3 135000.9 0.000 134755.8 0.053 -0.028 -0.163 0.000 -1.561 -0.027 -1.750 0.181
066/SLV A1 2 di 3 82787.6 0.345 82542.4 0.132 -0.028 -0.153 0.000 -1.493 -0.027 -1.673 0.113
089/SLV A1 2 di 3 84586.0 0.096 84340.8 0.428 -0.028 -0.153 0.000 -1.480 -0.027 -1.660 0.152
Cmb Tipologia Sismica Ecc. B Ecc. L S. Taglio B S. Taglio L S. Normale T.T. min T.T. max
n° cm cm daN daN daN daN/cmq daN/cmq
004 SLU STR No -4.1 3.1 2.5 1337.2 -77978.7 -0.297 -0.338
059 SLV A1 Si -16.0 -4.5 -7435.3 -1861.4 -40238.6 -0.137 -0.191
080 SLV A1 Si -10.9 19.9 -1927.7 5242.2 -42681.5 -0.122 -0.226
Cmb Strato Rot. Ver. TB S.T.B / TB Ver. TL S.T.L / TL Sgm. Lt. Qlim q Qlim g Qlim c Qres T QLIM T.T. / QLIM
n° n° daN daN daN/cmq daN/cmq daN/cmq daN/cmq daN/cmq daN/cmq
004/SLU STR 2 di 2 37357.8 0.000 36973.4 0.036 -0.065 -0.163 0.000 -1.777 -0.051 -1.990 0.170
059/SLV A1 2 di 2 19649.5 0.378 19265.1 0.097 -0.065 -0.153 0.000 -1.685 -0.051 -1.889 0.101
080/SLV A1 2 di 2 20795.8 0.093 20411.3 0.257 -0.065 -0.153 0.000 -1.714 -0.051 -1.918 0.118
Cmb Tipologia Sismica Ecc. B Ecc. L S. Taglio B S. Taglio L S. Normale T.T. min T.T. max
n° cm cm daN daN daN daN/cmq daN/cmq
004 SLU STR No 2.9 2.6 1019.1 2.1 -82574.8 -0.319 -0.355
061 SLV A1 Si -4.1 -1.3 -2840.9 -7412.5 -46848.2 -0.180 -0.207
090 SLV A1 Si 16.8 4.7 10026.0 -2062.2 -49221.4 -0.157 -0.249
Cmb Strato Rot. Ver. TB S.T.B / TB Ver. TL S.T.L / TL Sgm. Lt. Qlim q Qlim g Qlim c Qres T QLIM T.T. / QLIM
n° n° daN daN daN/cmq daN/cmq daN/cmq daN/cmq daN/cmq daN/cmq
004/SLU STR 2 di 2 39514.4 0.026 39129.9 0.000 -0.065 -0.163 0.000 -1.778 -0.051 -1.991 0.178
061/SLV A1 2 di 2 22750.9 0.125 22366.4 0.331 -0.065 -0.153 0.000 -1.704 -0.051 -1.908 0.108
090/SLV A1 2 di 2 23864.4 0.420 23479.9 0.088 -0.065 -0.153 0.000 -1.661 -0.051 -1.864 0.134
La determinazione dei cedimenti delle fondazioni, assume, in special modo nella fase di
MANDANTE:
69
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
esercizio, una rilevanza notevole per il manufatto da realizzarsi. Nell'evolversi della fase di
cedimento, il terreno passa da uno stato di sforzo corrente (dovuto al peso proprio) a uno nuovo, per
effetto del carico addizionale applicato. La variazione dello stato tensionale di cui sopra, produce
una serie di movimenti di rotolamento e scorrimento relativo tra i granuli del terreno nonché
deformazioni elastiche è rotture delle particelle costituenti il mezzo, localizzate in una limitata zona
d'influenza a ridosso dell'area di carico. L'insieme di questi fenomeni costituisce il cedimento, che
nel caso in esame è quello verticale. Nonostante che la frazione elastica sia modesta, l'esperienza ha
dimostrato che modellare il terreno (ai fini del calcolo dei cedimenti) come materiale pseudoelastico
permette di ottenere risultati soddisfacenti. Diversi sono i metodi esistenti in letteratura per il
calcolo dei cedimenti (si ricorda che qualunque sia il metodo di calcolo, la determinazione del
valore del cedimento deve intendersi come la miglior stima delle deformazioni subite dal terreno da
attendersi all'applicazione dei carichi) quelli implementati vengono di seguito descritti.
Si ricorda che tale metodo si basa sull'ipotesi edometrica, quindi l'approssimazione del risultato è
tanto migliore quanto più ridotto è il rapporto tra lo spessore dello strato deformabile e la
dimensione in pianta delle fondazioni. Tuttavia lo stesso è dotato di ottima approssimazione anche
nel caso di strati deformabili di spessore notevole.
La doppia formulazione adottata consente di ottenere un intervallo di valori (valore minimo per
wImp. e valore massimo per wLib.) del cedimento elastico per la fondazione in esame.
MANDANTE:
70
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
71
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
I materiali utilizzati nella modellazione sono individuati da una sigla identificativa ed un codice
numerico (gli elementi strutturali richiamano quest’ultimo nella propria descrizione). Per ogni
materiale vengono riportati in tabella i seguenti dati:
I dati soprariportati vengono utilizzati per la modellazione dello schema statico e per la
determinazione dei carichi inerziali e termici. In relazione al tipo di materiale vengono riportati
inoltre:
1 cemento armato
Rck resistenza caratteristica cubica
Fctm resistenza media a trazione semplice
2 acciaio
Ft tensione di rottura a trazione
Fy tensione di snervamento
Fd resistenza di calcolo
Fdt resistenza di calcolo per spess. t>40 mm
Sadm tensione ammissibile
Sadmt tensione ammissibile per spess. t>40 mm
3 muratura
Resist. Fk resistenza caratteristica a compressione
Resist. Fvko resistenza caratteristica a taglio
4 legno
Resist. fc0k Resistenza caratteristica (tensione amm. per
REGLES) per compressione
Resist. ft0k Resistenza caratteristica (tensione amm. per
MANDANTE:
72
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Le sezioni utilizzate nella modellazione sono individuate da una sigla identificativa ed un codice
numerico (gli elementi strutturali richiamano quest’ultimo nella propria descrizione). Per ogni
sezione vengono riportati in tabella i seguenti dati:
MANDANTE:
73
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
I dati soprariportati vengono utilizzati per la determinazione dei carichi inerziali e per la definizione
delle rigidezze degli elementi strutturali; qualora il valore di Area V2 (e/o Area V3) sia nullo la
deformabilità per taglio V2 (e/o V3) è trascurata. La valutazione delle caratteristiche inerziali delle
sezioni è condotta nel riferimento 2-3 dell’elemento.
Per quanto concerne i profilati semplici ed accoppiati l’asse 2 del riferimento coincide con l’asse x
riportato nei più diffusi profilatari.
MANDANTE:
74
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Ogni nodo è individuato dalle coordinate cartesiane nel sistema di riferimento globale (X Y Z).
Ad ogni nodo è eventualmente associato un codice di vincolamento rigido, un codice di fondazione
speciale, ed un set di sei molle (tre per le traslazioni, tre per le rotazioni). Le tabelle sottoriportate
riflettono le succitate possibilità. In particolare per ogni nodo viene indicato in tabella:
Nodo numero del nodo.
X valore della coordinata X
Y valore della coordinata Y
Z valore della coordinata Z
Per i nodi ai quali sia associato un codice di vincolamento rigido, un codice di fondazione speciale o
un set di molle viene indicato in tabella:
Nodo numero del nodo.
X valore della coordinata X
Y valore della coordinata Y
Z valore della coordinata Z
Note eventuale codice di vincolo (es. v=110010 sei valori relativi ai sei gradi di libertà
previsti per il nodo TxTyTzRxRyRz, il valore 1 indica che lo spostamento o rotazione
relativo è impedito, il valore 0 indica che lo spostamento o rotazione relativo è
libero).
Note (FS = 1, 2,…) eventuale codice del tipo di fondazione speciale (1, 2,… fanno
riferimento alle tipologie: plinto, palo, plinto su pali,…) che è collegato al nodo.
(ISO = “id SIGLA”) indice e sigla identificativa dell’ eventuale isolatore sismico
assegnato al nodo
Rig. TX valore della rigidezza dei vincoli elastici eventualmente applicati al nodo, nello
specifico TX (idem per TY, TZ, RX, RY, RZ).
MANDANTE:
75
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
76
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Il programma utilizza per la modellazione elementi a due nodi denominati in generale travi.
Ogni elemento trave è individuato dal nodo iniziale e dal nodo finale.
Ogni elemento è caratterizzato da un insieme di proprietà riportate in tabella che ne completano la
modellazione.
1
Y 2
orientamento elementi 2
orientamento elementi
3
X
3 1 2D non verticali Z
2D verticali
X
In particolare per ogni elemento viene indicato in tabella:
Elem. numero dell’elemento
Note codice di comportamento: trave, trave di fondazione, pilastro, asta, asta
tesa, asta compressa
Nodo I (J) numero del nodo iniziale (finale)
Mat. codice del materiale assegnato all’elemento
Sez. codice della sezione assegnata all’elemento
Rotaz. valore della rotazione dell’elemento, attorno al proprio asse, nel caso in
cui l’orientamento di default non sia adottabile; l’orientamento di
default prevede per gli elementi non verticali l’asse 2 contenuto nel
piano verticale e l’asse 3 orizzontale, per gli elementi verticali l’asse 2
diretto secondo X negativo e l’asse 3 diretto secondo Y negativo
Svincolo I (J) codici di svincolo per le azioni interne; i primi sei codici si riferiscono
al nodo iniziale, i restanti sei al nodo finale (il valore 1 indica che la
relativa azione interna non è attiva)
Wink V costante di sottofondo (coefficiente di Winkler) per la modellazione
della trave su suolo elastico
Wink O costante di sottofondo (coefficiente di Winkler) per la modellazione del
suolo elastico orizzontale
Elem. Note Nodo I Nodo J Mat. Sez. Rotaz. Svincolo I Svincolo J Wink V Wink O
gradi daN/cm3 daN/cm3
1 Asta 100 231 11 4
2 Asta 230 99 11 4
3 Asta 90 213 11 4
4 Asta 212 89 11 4
5 Pilas. 123 155 11 1
6 Pilas. 125 154 11 1
7 Pilas. 58 157 11 1
8 Pilas. 54 156 11 1
9 Pilas. 59 159 11 1
10 Pilas. 55 158 11 1
11 Pilas. 130 161 11 1
12 Pilas. 128 160 11 1
MANDANTE:
77
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
78
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Z
3 Z
Y 2 3
1 Y 1
X
2
X
MANDANTE:
79
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Elem. Note Nodo I Nodo J Nodo K Nodo L Mat. Spessore Wink V Wink O
cm daN/cm3 daN/cm3
1 Guscio fond. 5 11 10 3 3 30.0 0.04 0.01
2 Guscio fond. 15 6 4 14 3 30.0 0.04 0.01
3 Guscio fond. 37 15 14 45 3 30.0 0.04 0.01
4 Guscio fond. 62 61 11 5 3 30.0 0.04 0.01
5 Guscio fond. 64 63 6 15 3 30.0 0.04 0.01
6 Guscio fond. 57 64 15 37 3 30.0 0.04 0.01
7 Guscio fond. 1 9 12 7 3 30.0 0.04 0.01
8 Guscio fond. 13 2 8 16 3 30.0 0.04 0.01
9 Guscio fond. 46 13 16 38 3 30.0 0.04 0.01
10 Guscio fond. 188 17 19 202 3 30.0 0.04 0.01
11 Guscio fond. 203 65 17 188 3 30.0 0.04 0.01
12 Guscio fond. 204 20 18 173 3 30.0 0.04 0.01
13 Guscio fond. 132 21 29 133 3 30.0 0.04 0.01
14 Guscio fond. 123 66 21 132 3 30.0 0.04 0.01
15 Guscio fond. 134 30 22 135 3 30.0 0.04 0.01
16 Guscio fond. 41 23 31 49 3 30.0 0.04 0.01
17 Guscio fond. 59 67 23 41 3 30.0 0.04 0.01
18 Guscio fond. 50 32 24 42 3 30.0 0.04 0.01
19 Guscio fond. 142 25 33 143 3 30.0 0.04 0.01
20 Guscio fond. 129 68 25 142 3 30.0 0.04 0.01
21 Guscio fond. 144 34 26 145 3 30.0 0.04 0.01
22 Guscio fond. 17 27 35 19 3 30.0 0.04 0.01
23 Guscio fond. 65 69 27 17 3 30.0 0.04 0.01
24 Guscio fond. 20 36 28 18 3 30.0 0.04 0.01
25 Guscio fond. 21 37 45 29 3 30.0 0.04 0.01
26 Guscio fond. 66 57 37 21 3 30.0 0.04 0.01
27 Guscio fond. 30 46 38 22 3 30.0 0.04 0.01
28 Guscio fond. 23 39 47 31 3 30.0 0.04 0.01
29 Guscio fond. 67 58 39 23 3 30.0 0.04 0.01
30 Guscio fond. 32 48 40 24 3 30.0 0.04 0.01
31 Guscio fond. 137 41 49 138 3 30.0 0.04 0.01
32 Guscio fond. 130 59 41 137 3 30.0 0.04 0.01
33 Guscio fond. 139 50 42 140 3 30.0 0.04 0.01
34 Guscio fond. 27 43 51 35 3 30.0 0.04 0.01
35 Guscio fond. 69 60 43 27 3 30.0 0.04 0.01
36 Guscio fond. 36 52 44 28 3 30.0 0.04 0.01
37 Guscio fond. 117 116 61 62 3 30.0 0.04 0.01
38 Guscio fond. 107 118 63 64 3 30.0 0.04 0.01
39 Guscio fond. 119 107 64 57 3 30.0 0.04 0.01
40 Guscio fond. 205 120 65 203 3 30.0 0.04 0.01
41 Guscio fond. 136 121 66 123 3 70.0 0.04 0.02
42 Guscio fond. 110 109 67 59 3 30.0 0.04 0.01
43 Guscio fond. 146 112 68 129 3 70.0 0.04 0.02
44 Guscio fond. 120 115 69 65 3 30.0 0.04 0.01
45 Guscio fond. 121 119 57 66 3 70.0 0.04 0.02
46 Guscio fond. 109 122 58 67 3 30.0 0.04 0.01
47 Guscio fond. 141 110 59 130 3 70.0 0.04 0.02
48 Guscio fond. 115 113 60 69 3 30.0 0.04 0.01
MANDANTE:
80
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
81
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
82
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
83
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Nel caso in cui si sia proceduto alla progettazione con le tensioni ammissibili vengono riportate le
massime tensioni nell'elemento (massima compressione nel calcestruzzo, massima tensione
nell'acciaio, massima tensione tangenziale); nel caso in cui si sia proceduto alla progettazione con il
metodo degli stati limite vengono riportati il rapporto x/d e le verifiche per sollecitazioni
proporzionali nonché le verifiche in esercizio.
MANDANTE:
84
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
ID Arch. Tipo G1k G2k Qk Fatt. A s sis. Psi 0 Psi 1 Psi 2 Psi S 2 Fatt. Fi
daN/cm2 daN/cm2 daN/cm2
1 Variab. 1.00e-03 0.15 1.00 0.70 0.50 0.30 0.30 1.00
6 Neve 3.50e-02 5.00e-03 8.00e-03 1.00 0.50 0.20 0.0 0.0 1.00
7 Neve 3.50e-03 1.50e-03 8.00e-03 1.00 0.50 0.20 0.0 0.0 1.00
Elem. Tipo ID Arch. Mat. Spessore Orditura G1k G2k Qk Nodo 1/6.. Nodo 2/7.. Nodo 3/8.. Nodo.. Nodo..
daN/cm2 daN/cm2 daN/cm2
1 SM 1 m=11 1.0 0.0 1.00e-03 0.15 164 162 163 165
2 SM 1 m=11 1.0 0.0 1.00e-03 0.15 162 160 161 163
3 SM 1 m=11 1.0 0.0 1.00e-03 0.15 160 158 159 161
4 SM 1 m=11 1.0 0.0 1.00e-03 0.15 156 154 155 157
5 SM 1 m=11 1.0 0.0 1.00e-03 0.15 154 152 153 155
6 SM 1 m=11 1.0 0.0 1.00e-03 0.15 152 150 151 153
7 CM 6 m=1 5.0 0.0 3.50e-02 5.00e-03 8.00e-03 178 181 168 189 187
166
8 CM 6 m=1 5.0 0.0 3.50e-02 5.00e-03 8.00e-03 179 182 181 178
9 CM 6 m=1 5.0 0.0 3.50e-02 5.00e-03 8.00e-03 180 183 182 179
10 CM 6 m=1 5.0 0.0 3.50e-02 5.00e-03 8.00e-03 167 172 175 169 183
180
11 CM 7 m=11 0.5 90.0 3.50e-03 1.50e-03 8.00e-03 244 217 223 215
12 CM 7 m=11 0.5 90.0 3.50e-03 1.50e-03 8.00e-03 215 223 229 222
13 CM 7 m=11 0.5 90.0 3.50e-03 1.50e-03 8.00e-03 222 229 241 233
14 CM 7 m=11 0.5 90.0 3.50e-03 1.50e-03 8.00e-03 233 241 235 240
15 CM 7 m=11 0.5 90.0 3.50e-03 1.50e-03 8.00e-03 243 244 215 246
16 CM 7 m=11 0.5 90.0 3.50e-03 1.50e-03 8.00e-03 246 215 222 221
17 CM 7 m=11 0.5 90.0 3.50e-03 1.50e-03 8.00e-03 221 222 233 228
18 CM 7 m=11 0.5 90.0 3.50e-03 1.50e-03 8.00e-03 228 233 240 239
19 CM 7 m=11 0.5 90.0 3.50e-03 1.50e-03 8.00e-03 242 243 246 245
20 CM 7 m=11 0.5 90.0 3.50e-03 1.50e-03 8.00e-03 245 246 221 216
21 CM 7 m=11 0.5 90.0 3.50e-03 1.50e-03 8.00e-03 216 221 228 227
22 CM 7 m=11 0.5 90.0 3.50e-03 1.50e-03 8.00e-03 227 228 239 234
23 CM 7 m=11 0.5 90.0 3.50e-03 1.50e-03 8.00e-03 214 242 245 220
24 CM 7 m=11 0.5 90.0 3.50e-03 1.50e-03 8.00e-03 220 245 216 226
MANDANTE:
85
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
25 CM 7 m=11 0.5 90.0 3.50e-03 1.50e-03 8.00e-03 226 216 227 238
26 CM 7 m=11 0.5 90.0 3.50e-03 1.50e-03 8.00e-03 238 227 234 232
MANDANTE:
86
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Flangia:
Materiale: Acciaio S275 fy = 275 N/mm2 ft = 430 N/mm2 Rd = 1.15
Dimensioni (B x H x Sp): 180.0 x 392.3 x 10.0 mm
Bullonature:
Viti cl. 8.8 Dadi 8 ( fyb = 649 N/mm2, ftb = 800 N/mm2 )
Diametro Ø = 16 mm Ares = 156.8 mm2 (ridotta per filettatura)
Diametro foro Ø0 = 17 mm
Calcolo resistenze
Resistenza a trazione dei bulloni Ftb,Rd = 0,9 • ftb • Ares / M2 = 90333.1 N
Resistenza a punzonamento flangia Bpf,Rd = 0,6 • • dm • tf • ftk / M2 = 155621.9 N
Resistenza a punzonamento ala passante Bpa,Rd = 0,6 • • dm • ta • ftk / M2 = 147840.8 N
MANDANTE:
87
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Legenda
Ff,Rd = Mres,m / ( Bm • Rm ) resistenza a flessione flangia
Ft,Rd = min [ Ftb,Rd , Bpf,Rd , Bpa,Rd , Ff,Rd ] resistenza a trazione di progetto
Resistenza a taglio dei bulloni Fvb,Rd = 0,6 • ftb • Ares / M2 = 60222.1 N
Bull. Fbf,x,Rd [N] Fba,x,Rd [N] Fv,x,Rd [N] Fbf,y,Rd [N] Fba,y,Rd [N] Fv,y,Rd [N]
1 64493.8 92273.0 60222.1 55040.0 130720.0 55040.0
2 97129.4 92273.0 60222.1 137600.0 130720.0 60222.1
3 97129.4 92273.0 60222.1 112604.5 106974.3 60222.1
4 64493.9 92273.0 60222.1 55040.0 130720.0 55040.0
5 64493.8 92273.0 60222.1 55040.0 130720.0 55040.0
6 97129.4 92273.0 60222.1 137600.0 130720.0 60222.1
7 97129.4 92273.0 60222.1 112604.5 106974.3 60222.1
8 64493.9 92273.0 60222.1 55040.0 130720.0 55040.0
Legenda
Fbf,x,Rd = k • • ftk • Ø • tf / M2 resistenza a rifollamento flangia in direzione x
Fba,x,Rd = k • • ftk • Ø • ta / M2 resistenza a rifollamento ala passante in direzione x
Fv,x,Rd = min [ Fvb,Rd , Fbf,x,Rd , Fba,x,Rd ] resistenza a taglio di progetto in direzione x
Fbf,y,Rd = k • • ftk • Ø • tf / M2 resistenza a rifollamento flangia in direzione y
Fba,y,Rd = k • • ftk • Ø • ta / M2 resistenza a rifollamento ala passante in direzione y
Fv,y,Rd = min [ Fvb,Rd , Fbf,y,Rd , Fba,y,Rd ] resistenza a taglio di progetto in direzione y
MANDANTE:
88
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
89
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Verifica del momento di progetto del giunto (Nodo n. 230, CMB n. 11)
Momento resistente del giunto Mj,Rd = 32766650.0 N mm
Momento di progetto Mj,Ed = 17720000.0 N mm
Mj,Ed / Mj,Rd = 0.540794 Ok
Bullonature:
Viti cl. 8.8 Dadi 8 ( fyb = 649 N/mm2, ftb = 800 N/mm2 )
Diametro Ø = 12 mm Ares = 84.8 mm2 (ridotta per filettatura)
Diametro foro Ø0 = 13 mm
Calcolo resistenze
Resistenza a taglio dei bulloni Fvb,Rd = 0,6 • ftb • Ares / M2 = 32572.0 N
Bull. Fbp,x,Rd [N] Fba,x,Rd [N] Fv,x,Rd [N] Fbp,y,Rd [N] Fba,y,Rd [N] Fv,y,Rd [N]
1 61920.0 52922.9 32572.0 61920.0 82295.4 32572.0
2 61920.0 103200.0 32572.0 35048.5 82295.4 32572.0
Legenda
Fbp,x,Rd = k • • ftk • Ø • tc / M2 resistenza a rifollamento piastra in direzione x
Fba,x,Rd = k • • ftk • Ø • ta / M2 resistenza a rifollamento asta elemento in direzione x
Fv,x,Rd = min [ Fvb,Rd , Fbc,x,Rd , Fba,x,Rd ] resistenza a taglio di progetto in direzione x
Fbp,y,Rd = k • • ftk • Ø • tc / M2 resistenza a rifollamento piastra in direzione y
Fba,y,Rd = k • • ftk • Ø • ta / M2 resistenza a rifollamento asta elemento in direzione y
Fv,y,Rd = min [ Fvb,Rd , Fbc,y,Rd , Fba,y,Rd ] resistenza a taglio di progetto in direzione y
MANDANTE:
90
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Legenda
Fv,Ed forza di taglio agente sul bullone
Fv,Rd resistenza a taglio di progetto del bullone
FV = Fv,Ed / Fv,Rd
VER FV ≤ 1
Flangia:
Materiale: Acciaio S275 fy = 275 N/mm2 ft = 430 N/mm2 Rd = 1.15
Dimensioni (B x H x Sp): 180.0 x 575.3 x 10.0 mm
Bullonature:
Viti cl. 8.8 Dadi 8 ( fyb = 649 N/mm2, ftb = 800 N/mm2 )
MANDANTE:
91
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Calcolo resistenze
Resistenza a trazione dei bulloni Ftb,Rd = 0,9 • ftb • Ares / M2 = 90333.1 N
Resistenza a punzonamento flangia Bpf,Rd = 0,6 • • dm • tf • ftk / M2 = 155621.9 N
Resistenza a punzonamento ala passante Bpa,Rd = 0,6 • • dm • ta • ftk / M2 = 147840.8 N
Bull. Ff,Rd [N] Ft,Rd [N]
1 9370.9 9370.9
2 21236.5 21236.5
3 21236.5 21236.5
4 9206.2 9206.2
5 9370.9 9370.9
6 21236.5 21236.5
7 21236.5 21236.5
8 9206.2 9206.2
Legenda
Ff,Rd = Mres,m / ( Bm • Rm ) resistenza a flessione flangia
Ft,Rd = min [ Ftb,Rd , Bpf,Rd , Bpa,Rd , Ff,Rd ] resistenza a trazione di progetto
Resistenza a taglio dei bulloni Fvb,Rd = 0,6 • ftb • Ares / M2 = 60222.1 N
Bull. Fbf,x,Rd [N] Fba,x,Rd [N] Fv,x,Rd [N] Fbf,y,Rd [N] Fba,y,Rd [N] Fv,y,Rd [N]
1 64493.9 92273.0 60222.1 55040.0 130720.0 55040.0
2 97129.4 92273.0 60222.1 137600.0 130720.0 60222.1
3 97129.4 92273.0 60222.1 137600.0 130720.0 60222.1
4 64493.9 92273.0 60222.1 55040.0 130720.0 55040.0
5 64493.9 92273.0 60222.1 55040.0 130720.0 55040.0
6 97129.4 92273.0 60222.1 137600.0 130720.0 60222.1
7 97129.4 92273.0 60222.1 137600.0 130720.0 60222.1
8 64493.9 92273.0 60222.1 55040.0 130720.0 55040.0
Legenda
Fbf,x,Rd = k • • ftk • Ø • tf / M2 resistenza a rifollamento flangia in direzione x
Fba,x,Rd = k • • ftk • Ø • ta / M2 resistenza a rifollamento ala passante in direzione x
Fv,x,Rd = min [ Fvb,Rd , Fbf,x,Rd , Fba,x,Rd ] resistenza a taglio di progetto in direzione x
Fbf,y,Rd = k • • ftk • Ø • tf / M2 resistenza a rifollamento flangia in direzione y
Fba,y,Rd = k • • ftk • Ø • ta / M2 resistenza a rifollamento ala passante in direzione y
Fv,y,Rd = min [ Fvb,Rd , Fbf,y,Rd , Fba,y,Rd ] resistenza a taglio di progetto in direzione y
MANDANTE:
92
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
93
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Verifica del momento di progetto del giunto (Nodo n. 213, CMB n. 18)
Momento resistente del giunto Mj,Rd = 32323510.0 N mm
Momento di progetto Mj,Ed = 21840000.0 N mm
Mj,Ed / Mj,Rd = 0.675669 Ok
Bullonature:
Viti cl. 8.8 Dadi 8 ( fyb = 649 N/mm2, ftb = 800 N/mm2 )
Diametro Ø = 12 mm Ares = 84.8 mm2 (ridotta per filettatura)
Diametro foro Ø0 = 13 mm
Calcolo resistenze
Resistenza a taglio dei bulloni Fvb,Rd = 0,6 • ftb • Ares / M2 = 32572.0 N
Bull. Fbp,x,Rd [N] Fba,x,Rd [N] Fv,x,Rd [N] Fbp,y,Rd [N] Fba,y,Rd [N] Fv,y,Rd [N]
1 61920.0 52923.1 32572.0 61920.0 82295.4 32572.0
2 61920.0 103200.0 32572.0 35048.5 82295.4 32572.0
Legenda
Fbp,x,Rd = k • • ftk • Ø • tc / M2 resistenza a rifollamento piastra in direzione x
Fba,x,Rd = k • • ftk • Ø • ta / M2 resistenza a rifollamento asta elemento in direzione x
Fv,x,Rd = min [ Fvb,Rd , Fbc,x,Rd , Fba,x,Rd ] resistenza a taglio di progetto in direzione x
Fbp,y,Rd = k • • ftk • Ø • tc / M2 resistenza a rifollamento piastra in direzione y
Fba,y,Rd = k • • ftk • Ø • ta / M2 resistenza a rifollamento asta elemento in direzione y
Fv,y,Rd = min [ Fvb,Rd , Fbc,y,Rd , Fba,y,Rd ] resistenza a taglio di progetto in direzione y
MANDANTE:
94
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Verifica secondo il D.M. 14/01/2008 dei nodi: 218, 219, 224, 225, 236, 237
Flangia:
Materiale: Acciaio S275 fy = 275 N/mm2 ft = 430 N/mm2 Rd = 1.15
Dimensioni (B x H x Sp): 180.0 x 282.3 x 15.0 mm
Bullonature:
Viti cl. 8.8 Dadi 8 ( fyb = 649 N/mm2, ftb = 800 N/mm2 )
Diametro Ø = 16 mm Ares = 156.8 mm2 (ridotta per filettatura)
MANDANTE:
95
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Diametro foro Ø0 = 17 mm
Calcolo resistenze
Resistenza a trazione dei bulloni Ftb,Rd = 0,9 • ftb • Ares / M2 = 90333.1 N
Resistenza a punzonamento flangia Bpf,Rd = 0,6 • • dm • tf • ftk / M2 = 233432.9 N
Resistenza a punzonamento ala passante Bpa,Rd = 0,6 • • dm • ta • ftk / M2 = 147840.8 N
Bull. Ff,Rd [N] Ft,Rd [N]
1 41078.7 41078.7
2 47782.0 47782.0
3 47782.0 47782.0
4 41078.7 41078.7
5 41078.7 41078.7
6 47782.0 47782.0
7 47782.0 47782.0
8 41078.7 41078.7
Legenda
Ff,Rd = Mres,m / ( Bm • Rm ) resistenza a flessione flangia
Ft,Rd = min [ Ftb,Rd , Bpf,Rd , Bpa,Rd , Ff,Rd ] resistenza a trazione di progetto
Resistenza a taglio dei bulloni Fvb,Rd = 0,6 • ftb • Ares / M2 = 60222.1 N
Bull. Fbf,x,Rd [N] Fba,x,Rd [N] Fv,x,Rd [N] Fbf,y,Rd [N] Fba,y,Rd [N] Fv,y,Rd [N]
1 96740.8 92273.0 60222.1 82560.0 130720.0 60222.1
2 145694.1 92273.0 60222.1 206400.0 130720.0 60222.1
3 145694.1 92273.0 60222.1 206400.0 130720.0 60222.1
4 96740.8 92273.0 60222.1 82560.0 130720.0 60222.1
5 96740.8 92273.0 60222.1 82560.0 130720.0 60222.1
6 145694.1 92273.0 60222.1 206400.0 130720.0 60222.1
7 145694.1 92273.0 60222.1 206400.0 130720.0 60222.1
8 96740.8 92273.0 60222.1 82560.0 130720.0 60222.1
Legenda
Fbf,x,Rd = k • • ftk • Ø • tf / M2 resistenza a rifollamento flangia in direzione x
Fba,x,Rd = k • • ftk • Ø • ta / M2 resistenza a rifollamento ala passante in direzione x
Fv,x,Rd = min [ Fvb,Rd , Fbf,x,Rd , Fba,x,Rd ] resistenza a taglio di progetto in direzione x
Fbf,y,Rd = k • • ftk • Ø • tf / M2 resistenza a rifollamento flangia in direzione y
Fba,y,Rd = k • • ftk • Ø • ta / M2 resistenza a rifollamento ala passante in direzione y
Fv,y,Rd = min [ Fvb,Rd , Fbf,y,Rd , Fba,y,Rd ] resistenza a taglio di progetto in direzione y
MANDANTE:
96
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
MANDANTE:
97
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Verifica del momento di progetto del giunto (Nodo n. 236, CMB n. 16)
Momento resistente del giunto Mj,Rd = 42906140.0 N mm
Momento di progetto Mj,Ed = 39420000.0 N mm
Mj,Ed / Mj,Rd = 0.918750 Ok
Verifica secondo il D.M. 14/01/2008 dei nodi: 93, 94, 95, 96, 97, 98
Colonna
Tipo di profilo: HEA 200
Materiale: Acciaio S275 fy = 275 N/mm2 ft = 430 N/mm2 Rd = 1.15
Classe sezione: 1
Flangia:
Materiale: Acciaio S275 fy = 275 N/mm2 ft = 430 N/mm2 Rd = 1.15
Dimensioni (B x H x Sp): 305.0 x 300.0 x 20.0 mm
Spessore nervature verticali: 10.0 mm
Spessore nervature orizzontali: 10.0 mm
Bullonature:
MANDANTE:
98
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Viti cl. 8.8 Dadi 8 ( fyb = 649 N/mm2, ftb = 800 N/mm2 )
Diametro Ø = 16 mm Ares = 156.8 mm2 (ridotta per filettatura)
Diametro foro Ø0 = 17 mm
Sollecitazioni:
Nodo.CMB V2 [N] V3 [N] N [N] M2 [N mm] M3 [N mm] T [N mm]
93.18 13073.7 8.7 -61810.2 -42995.0 -24530000.0 -174.0
94.64 -3420.7 14166.7 -18544.6 -31350000.0 -1104000.0 -48251.0
98.63 -7571.1 14194.3 -15615.5 -31410000.0 5512000.0 -47558.0
98.64 -5040.9 14338.9 -21593.0 -31730000.0 2194000.0 -48143.0
Calcolo resistenze
Resistenza a trazione dei bulloni Ftb,Rd = 0,9 • ftb • Ares / M2 = 90333.1 N
Resistenza a punzonamento flangia Bpf,Rd = 0,6 • • dm • tf • ftk / M2 = 311243.9 N
Bull. Ff,Rd [N] Ft,Rd [N]
1 104280.3 90333.1
2 72971.7 72971.7
3 104280.3 90333.1
4 72971.7 72971.7
Legenda
Ff,Rd = Mres,m / ( Bm • Rm ) resistenza a flessione flangia
Ft,Rd = min [ Ftb,Rd , Bpf,Rd , Ff,Rd ] resistenza a trazione di progetto
Resistenza a taglio dei bulloni Fvb,Rd = 0,6 • ftb • Ares / M2 = 60222.1 N
Bull. Fbf,x,Rd [N] Fv,x,Rd [N] Fbf,y,Rd [N] Fv,y,Rd [N]
1 110080.0 60222.1 125404.8 60222.1
2 73093.1 60222.1 73093.1 60222.1
3 110080.0 60222.1 125404.8 60222.1
4 73093.1 60222.1 73093.1 60222.1
Legenda
Fbf,x,Rd = k • • ftk • Ø • tf / M2 resistenza a rifollamento flangia in direzione x
Fv,x,Rd = min [ Fvb,Rd , Fbf,x,Rd ] resistenza a taglio di progetto in direzione x
Fbf,y,Rd = k • • ftk • Ø • tf / M2 resistenza a rifollamento flangia in direzione y
Fv,y,Rd = min [ Fvb,Rd , Fbf,y,Rd ] resistenza a taglio di progetto in direzione y
MANDANTE:
99
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
100
ASSOCIAZIONE TEMPORANEA DI IMPRESE
MANDATARIA: Messa in sicurezza Quadrante Est: primo intervento per la
realizzazione di un sistema di rimozione del percolato
Progetto Esecutivo
RELAZIONE DI CALCOLO STRUTTURALE E SULLE FONDAZIONI
Committente: Comune di Ferrara
Novembre 2013
Sezione parallela a Y a filo della nervatura verticale (Nodo n. 98, CMB n. 64)
Pressione media a bordo piastra pmed = 10.57 N/mm2
Carico lineare sbalzo qlin = 3172.01 N/mm
Lunghezza sbalzo Ls = 42.5 mm
Modulo di resistenza minimo Wmin = 14570.9 mm3
Momento resistente Mp,Rd = 3816180.0 N mm
Momento massimo Mp,Ed = 2864721.0 N mm
Mp,Ed / Mp,Rd = 0.750678 Ok
Verifica del momento di progetto del giunto (Nodo n. 98, CMB n. 64)
Momento resistente del giunto Mj,Rd = 39366840.0 N mm
Momento di progetto Mj,Ed = 31730000.0 N mm
Mj,Ed / Mj,Rd = 0.806008 Ok
Ancoraggio
Tirafondi con uncini e bolzoni
Lunghezza tirafondi Lt = 600 mm (rettilineo 280 mm, Ø semicerchio 80 mm, terminale 64
mm)
Diametro bolzoni Øb = 16 mm
Calcestruzzo
Resistenza cubica caratteristica a compressione Rck = 40.00 N/mm2
Resistenza cilindrica caratteristica a compressione fck = 0,83 • Rck = 33.20
2
N/mm
Resistenza di calcolo a compressione fcd = cc • fck / C = 18.81 N/mm2
Resistenza caratteristica a trazione fctk = 0,7 • 0,30 • fck2/3 = 2.17 N/mm2
Resistenza tangenziale di aderenza di calcolo fbd = 2.25 • • fctk / C = 3.25 N/mm2
Verifica ancoraggio
Si considera la massima resistenza a trazione di progetto dei tirafondi
Trazione di progetto dell'ancoraggio Ft,an,Ed = max [ Ft,Rd ] = 90333.1 N
Resistenza a trazione per aderenza Ft,ad,Rd = Lt • • Ø • fbd = 98135.0 N
Ft,ad,Rd > Ft,an,Ed Ok
MANDANTE:
101