CALCULATION SHEET

PPKom : Bidang Pelaksana Jalan Wilayah Timur


Nama Proyek : Peningkatan Jalan Surakarta - Gemolong - Gayer / Bts. Kab. Grobogan (DAK) STA 6+000 - 10+005)
Ruas jalan : Jalan Surakarta-Gemolong-Gayer
Lokasi : Kab. Grobogan
Tahun Anggaran : 2022
Nama Penawar : PT. HEFA SARANA KONTRAKTOR

No Gambar/Sketsa Perhitungan Satuan Kuantitas


a b c d e
2.3.(26) Saluran berbentuk U Tipe DS 3 Volume = Panjang M1 720

STA 6+920 - STA 7+040 = 120


STA 7+150 - STA 7+235 = 85
STA 7+235 - STA 7+750 = 515

TOTAL = 720 M1

2.3.(27) Saluran Berbentuk U Tipe DS 3a (dengan tutup) Volume = Panjang M1 475

STA 9+530 - STA 10+005 = 475

TOTAL = 475 M1

3.1.(1) Galian Biasa STA 6+000 - STA 10+005 M3 2415.015

Volume = l x p x t
= 10.05 x 4005 x 0.06
= 2415.015

TOTAL = 2415.015

3.1.(7) Galian Perkerasan Beraspal dengan Cold Milling Machine Volume = l x t x p M3 59.16
STA 6+000 -STA 6+100 = 1.5 x 0.017 x 100 = 2.55
STA 6+100 - STA 6+225 = 1.5 x 0.017 x 125 = 3.1875
STA 6+460 - STA 6+530 = 1.5 x 0.017 x 70 = 1.785
STA 6+530 - STA 6+680 = 1.5 x 0.017 x 150 = 3.825
STA 6+680 - STA 6+770 = 1.5 x 0.017 x 90 = 2.295
STA 6+770 - STA 6+920 = 1.5 x 0.017 x 150 = 3.825
STA 6+920 - STA 7+040 = 1.5 x 0.017 x 120 = 3.06
STA 7+235 - STA 7+750 = 1.5 x 0.017 x 515 = 13.1325
STA 7+750 - STA 8+750 = 1.5 x 0.017 x 1000 = 25.5

TOTAL = 59.16

3.2.(2a) Timbunan Pilihan dari Sumber Galian Volume = l x t x p M3 1430.7


STA 8+750 - 9+530 = 3 x 0.38 x 780 = 889.2
STA 9+530 - 10+005 = 3 x 0.38 x 475 = 541.5

TOTAL = 1430.7

3.3.(1) Penyiapan Badan Jalan STA 6+000 - STA 10+005 M2 5927.4

Volume = l x p x t
= 7.4 x 4005 x 0.2
= 5927.4

TOTAL = 5927.4

5.1.(1) Lapis Pondasi Agregat Kelas A Volume = l x t x p M3 1616.52


STA 8+750 - STA 9+530 = 2.8 x 0.18 x 780 = 393.12
= 5 x 0.15 x 780 = 585
STA 9+530 - STA 10+005 = 2.8 x 0.18 x 475 = 239.4
= 5.6 x 0.15 x 475 = 399

TOTAL = 1616.52

5.1.(3) Lapis Pondasi Agregat Kelas S Volume = l x t x p M3 490


STA 6+00 - STA 6+100 = 2 x 0.1 x 100 = 20
STA 6+100 - STA 8+000 = 2 x 0.1 x 1900 = 380
STA 8+00 - STA 8+450 = 2 x 0.1 x 450 = 90

TOTAL = 490

5.3.(1.a) Perkerasan Beton Semen Volume = l x t x p M3 2881.48


STA 8+750 - STA 9+530 = 8.2 x 0.28 x 780 = 1790.88
STA 9+530 - STA 10+005 = 8.2 x 0.28 x 475 = 1090.6

TOTAL = 2881.48
5.3.(3) Lapis Pondasi Bawah Beton Kurus (Concrete Vibrator) Volume = l x t x p M3 1029.1
STA 8+750 - STA 9+530 = 8.2 x 0.1 x 780 = 639.6
STA 9+530 - STA 10+005 = 8.2 x 0.1 x 475 = 389.5

TOTAL = 1029.1

5.3.(8) Beton Struktur, fc 20 Mpa (pada Perkerasan Jalan) Volume = l x t x p M3 1602


STA 6+00 - STA 10+005 = 2 X 0.2 x 4005 = 1602

TOTAL = 1602

5.5.(1) Lapis Fondasi Agregat Semen Kelas A (Cemen Treated Base = CTB) Volume = l x t x p M3 351
STA 7+040 - STA 7+150 = 6 x 0.3 x 110 = 198
STA 7+150 - STA 7+235 = 6 x 0.3 x 85 = 153

TOTAL = 351

6.1.(2a) Lapis Perekat Aspal Cair/Emulsi STA 6+000 - STA 10+005 Liter 7409.25

Volume = l x p x koef l/M2


= 7.4 x 4005 x 0.25 l/M2
= 7409.25

TOTAL = 7409.25

6.5.(1) Laston Lapis Aus Asbuton (AC-WC Asb) Volume = l x t x p x BJ t/m3 Ton 2595.136
STA 6+00 - STA 6+100 = 10.5 x 0.04 x 100 x 2.3 = 96.6
STA 6+100 - STA 6+225 = 7.4 x 0.04 x 125 x 2.3 = 85.1
STA 6+460 - STA 6+530 = 7.4 x 0.04 x 70 x 2.3 = 47.656
STA 6+530 - STA 10+005 = 7.4 x 0.04 x 3475 x 2.3 = 2365.78

TOTAL = 2595.136

6.5.(2) Laston Lapis Aus Asbuton (AC-BC Asb) Volume = l x t x p x BJ t/m3 Ton 2611.098
STA 6+00 - STA 6+100 = 10.5 x 0.06 x 100 x 2.3 = 144.9
STA 6+100 - STA 6+225 = 7.4 x 0.06 x 125 x 2.3 = 127.65
STA 6+460 - STA 6+530 = 7.4 x 0.06 x 70 x 2.3 = 71.484
STA 6+530 - STA 8+750 = 7.4 x 0.06 x 2220 x 2.3 = 2267.064

TOTAL = 2611.098

7.9.(1) Pasangan Batu volume = l x t x p M3 432


= 3 x 0.2 x 720
= 432

TOTAL = 432