No. Document : ………………………………….

Date : ………………………………….
Check List Alat dan Bahan Pengujian Penetrant Location : ………………………………….
Sub Contractor : ………………………………….
Page : 1 of 2

Status
No. Item Spec / Range Brand/Manufacture Detail Gambar
Ready Not Ready

1 Liquid Penetrant ( Visible ) SKL - SP2 MAGNAFLUX

2 Developer ( Dry Developer ) SKD-S2 MAGNAFLUX

3 Cleaner/Remover ( Solvent ) SKC - S MAGNAFLUX

4 Infrared Temperature Gun -50⁰C to 550⁰C N/A

5 Digital Capiler 0 - 150 mm N/A

6 Stainless Steel Rulers 0 - 15 mm N/A

7 Wire Brush / Wire Cup N/A N/A

8 Chemical Resistant Glove N/A N/A


No. Document : ………………………………….
Date : ………………………………….
Check List Alat dan Bahan Pengujian Penetrant Location : ………………………………….
Sub Contractor : ………………………………….
Page : 2 of 2

Status
No. Item Spec / Range Brand/Manufacture Detail Gambar
Ready Not Ready

9 Clean Clothes N/A N/A

10 Brush N/A N/A

Note : 1. Lakukan Pengechekan kelayakan di setiap item Alat dan Bahan yang akan di gunakan.
2. Semua Alat dan Bahan harus ber-status ada di lokasi pekerjaan ( Ready )
3. Jika terdapat salah satu Item yang tidak ada ( Not Ready ) maka harus konfimasi ke Pengawas
atau Inspektor untuk bisa memulai Pekerjaan.

Confrimed by Prepared
Consultant Supervision Contractor
OCG + JOPRISS ASSOCIATION PT. Adhi Karya ( Persero ) Tbk.

(.................................) (.................................)