Dammam -1

Roof First Floor GF Floor


POD-1, 3MW FWU 14nos Landlord corridor POD-1, 2MW FWU 10 nos Electrical Module
Chiller-1 FCU-2nos 10 CRAH units
TES-1
PO1-FWU-1 PO1-FWU-8 FCU-1 PO1-FWU-1 Electrical CRAH -Duty
TES-2
PO1-FWU-2 PO1-FWU-9 FCU-2 PO1-FWU-2 Module 1A CRAH -Standby
Chiller-2
PO1-FWU-3 PO1-FWU-10 PO1-FWU-3 Electrical CRAH -Duty
PO1-FWU-4 PO1-FWU-11 PO1-FWU-4 Module 1B CRAH -Standby
Chiller-3
PO1-FWU-5 PO1-FWU-12 PO1-FWU-5 Electrical CRAH -Duty
TES-3 PO1-FWU-6 PO1-FWU-13 PO1-FWU-6 Module 1C CRAH -Standby
Chiller-4 TES-4 PO1-FWU-7 PO1-FWU-14 PO1-FWU-7 Electrical CRAH -Duty
TES-5 PO1-FWU-8 Module 1D CRAH -Standby
PO1-FWU-9 Electrical CRAH -Duty
Chiller-5
PO1-FWU-10 Module 1E CRAH -Standby
Landlord corridor
Chiller-1 POD-2 , 3MW FWU 14 nos POD-2, 2MW FWU 10 nos Electrical Module 10 CRAH units
TES-1 FCU-2nos
TES-2 PO2-FWU-1 PO2-FWU-8 FCU-1 PO2-FWU-1 Electrical CRAH -Duty
Chiller-2
PO2-FWU-2 PO2-FWU-9 FCU-2 PO2-FWU-2 Module 2A CRAH -Standby
PO2-FWU-3 PO2-FWU-10 PO2-FWU-3 Electrical CRAH -Duty
Chiller-3
PO2-FWU-4 PO2-FWU-11 PO2-FWU-4 Module 2B CRAH -Standby
PO2-FWU-5 PO2-FWU-12 PO2-FWU-5 Electrical CRAH -Duty
TES-3
Chiller-4 PO2-FWU-6 PO2-FWU-13 PO2-FWU-6 Module 2C CRAH -Standby
TES-4
PO2-FWU-7 PO2-FWU-14 PO2-FWU-7 Electrical CRAH -Duty
TES-5
PO2-FWU-8 Module 2D CRAH -Standby
Chiller-5 PO2-FWU-9 Electrical CRAH -Duty
PO2-FWU-10 Module 2E CRAH -Standby
Landlord corridor
POD-3 , 3MW FWU 14 nos POD-3, 2MW FWU 10 nos Electrical Module 10 CRAH units
Chiller-1 TES-1 FCU-2nos
TES-2 PO3-FWU-1 PO3-FWU-8 FCU-1 PO3-FWU-1 Electrical CRAH -Duty
Chiller-2
PO3-FWU-2 PO3-FWU-9 FCU-2 PO3-FWU-2 Module 3A CRAH -Standby
PO3-FWU-3 PO3-FWU-10 PO3-FWU-3 Electrical CRAH -Duty
Chiller-3
PO3-FWU-4 PO3-FWU-11 PO3-FWU-4 Module 3B CRAH -Standby
PO3-FWU-5 PO3-FWU-12 PO3-FWU-5 Electrical CRAH -Duty
TES-3
Chiller-4 PO3-FWU-6 PO3-FWU-13 PO3-FWU-6 Module 3C CRAH -Standby
TES-4
PO3-FWU-7 PO3-FWU-14 PO3-FWU-7 Electrical CRAH -Duty
TES-5
PO3-FWU-8 Module 3D CRAH -Standby
Chiller-5 ` PO3-FWU-9 Electrical CRAH -Duty
PO3-FWU-10 Module 3E CRAH -Standby
Landlord corridor
POD-4 , 3MW FWU 14 nos POD-4, 2MW FWU 10 nos Electrical Module 10 CRAH units
Chiller-1 TES-1 FCU-2nos
TES-2 PO4-FWU-1 PO4-FWU-8 FCU-1 PO4-FWU-1 Electrical CRAH -Duty
Chiller-2
PO4-FWU-2 PO4-FWU-9 FCU-2 PO4-FWU-2 Module 4A CRAH -Standby
PO4-FWU-3 PO4-FWU-10 PO4-FWU-3 Electrical CRAH -Duty
Chiller-3
PO4-FWU-4 PO4-FWU-11 PO4-FWU-4 Module 4B CRAH -Standby
PO4-FWU-5 PO4-FWU-12 PO4-FWU-5 Electrical CRAH -Duty
TES-3
Chiller-4 PO4-FWU-6 PO4-FWU-13 PO4-FWU-6 Module 4C CRAH -Standby
TES-4
PO4-FWU-7 PO4-FWU-14 PO4-FWU-7 Electrical CRAH -Duty
TES-5
PO4-FWU-8 Module 4D CRAH -Standby
Chiller-5 PO4-FWU-9 Electrical CRAH -Duty
PO4-FWU-10 Module 4E CRAH -Standby
Redundancy 4+1 12+2 8+2 1+1
Assumption
Roof First Floor GF Floor
POD-1A, 1.2 MW Fanwall 8 units IDF ROOM ,200kW 8 CRAH units Electrical Module 6 CRAH units
Electrical
Chiller-1 CRAH -1 CRAH -Duty
PO1A-FWU-1 PO1A-FWU-5 IDF-1 Module
CRAH -2 AUX-A CRAH -Standby
Electrical
TES-1 CRAH -1 CRAH -Duty
PO1A-FWU-2 PO1A-FWU-6 IDF-2 Module
Chiller-2 TES-2 CRAH -2 CRAH -Standby
AUX-B
TES-3 Electrical
CRAH -1 CRAH -Duty
PO1A-FWU-3 PO1A-FWU-7 IDF-3 Module
CRAH -2 AUX-C CRAH -Standby
Chiller-3 CRAH -1
PO1A-FWU-4 PO1A-FWU-8 IDF-4
CRAH -2

Critical Chilled water


5-chillers (4 Duty + 1 Standby) and 5-TES tanks supporting one 3MW POD in First floor , One 2MW POD Ground floor & 5
facility for 3MW & 2MW
Electrical modules
POD's
Critical Chilled water
3- chillers (2 Duty + 1 Standby) and 3-TES tanks supporting one 1.2 MW POD in First floor,200kW IDF 4 -Rooms in Ground
facility for 1.2 MW POD &
floor & 3 Electrical modules AUX
200kW IDF's