Sei sulla pagina 1di 2

RINCIAN RENCANA ANGGARAN BIAYA

HARGA SURVEY
REHABILITASI BANGUNAN POSYANDU RW. 02
TAHUN ANGGARAN 2021

HARGA HARGA TOTAL


NO. URAIAN PEKERJAAN KODE SAT. VOLUME SUB TOTAL Rp.
SATUAN Rp. Rp.
1 2 3 4 5 6 7 8

I. PERSIAPAN
1 Pengadaan/Sewa Direksikeet Ls 1,00 450.000,00 450.000,00
2 Plang Nama Kegiatan Menggunakan Bahan Bender Ls 1,00 150.000,00 150.000,00
3 Pekerjaan Bongkaran dan Buangan Bekas Bongkaran Ls 1,00 500.000,00 500.000,00
SUB JUMLAH 1.100.000,00 1.100.000,00

II. PEKERJAAN BETON


1 Beton Ringbalk 15/20 cm
- Cor Beton Mutu F'c = 19,3 Mpa A.4.1.1.7. M3 0,66 927.100,00 611.886,00
- Pembesian A.4.1.1.17.a Kg 108,85 13.800,00 1.502.182,44
- Bekisting multiplek 9mm, Rangka Kayu Gunung Klas III A.4.1.1.23. M2 4,40 130.900,00 576.247,98
SUB JUMLAH 2.690.316,42 2.690.316,42

III. PEKERJAAN DINDING


1 Dinding Bata ad 1PC : 5Ps A.4.4.1.10 M2 9,68 108.700,00 1.052.216,00
2 Plesteran Dinding Bata ad 1PC : 5PS + Acian A.4.4.2.16. M2 19,36 62.300,00 1.206.128,00
SUB JUMLAH 2.258.344,00 2.258.344,00

IV. PEKERJAAN ATAP


1 Rangka Atap Baja Ringan Terpasang M2 47,67 150.000,00 7.150.115,47
2 Bubung Genteng Palentong A.4.5.2.4 M1 12,00 80.900,00 970.800,00
3 Pasang Kembali Genteng Palentong Lama Ls 1,00 500.000,00 500.000,00
4 Talang Seng BJLS G-18 M1 9,00 63.500,00 571.500,00
SUB JUMLAH 9.192.415,47 9.192.415,47

V. PEKERJAAN PENUTUP LANGIT-LANGIT


1 Plafond GRC 5 mm, + Rangka Hollow 2/4 A.4.5.1.5 M2 35,00 105.600,00 3.696.000,00
2 Lispang Wood Plank A.4.5.1.8 M1 17,00 44.200,00 751.400,00
SUB JUMLAH 4.447.400,00 4.447.400,00

VI. PEKERJAAN PENUTUP LANTAI DAN DINDING


1 Lantai Keramik 40x40 Putih Polos A.4.4.3.4 M2 28,00 160.500,00 4.494.000,00
SUB JUMLAH 4.494.000,00 4.494.000,00

VII. PEKERJAAN KAYU


1 Pasangan Kusen Pintu dan Jendela Kayu Kls. II A.4.6.1.2. M2 0,18 6.395.400,00 1.179.951,30
2 Pasangan Pintu Panel Kayu Kls. II A.4.6.1.5. M2 1,60 581.900,00 931.040,00
SUB JUMLAH 2.110.991,30 2.110.991,30
VIII. PEKERJAAN KUNCI DAN KACA
1 Kunci Tanam Doble Slag Biasa A.4.6.2.1. M2 1,00 210.900,00 210.900,00
2 Engsel Pintu A.4.6.2.5. M2 2,00 27.900,00 55.800,00
3 Pas. Kaca 5 mm A.4.6.2.17. M2 4,48 127.400,00 570.752,00
SUB JUMLAH 837.452,00 837.452,00

IX. PEKERJAAN PENGECATAN


1 Pengecatan Dinding Tembok A.4.7.1.11 M2 93,66 14.200,00 1.329.997,17
SUB JUMLAH 1.329.997,17 1.329.997,17