Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Material Prices
Paint etc.
Sanitary Fittings
Introductory Notes.
1 Excavation 07 - 09
2 Anti-termite treatment 10
3 Earthwork 11 - 12
4 Earthwork support 13 - 14
5 Concrete 15 - 25
6 Timber formwork 26 - 28
7 Steel reinforcement 29
8 Brickwork 30 - 36
9 Hollow block masonry 37
10 Random rubble masonry 38
11 Pressed tiling 39
12 Wall tiling & Terrazzo tiles 40
13 Roofing 41 - 45
14 Roof plumbing 46 - 47
15 Ceiling 48 - 49
16 Doors & windows 50 - 52
17 Ironmongery 53 - 56
18 Plastering 57 - 63
19 Painting & Decorating 64 - 68
20 Plumbing (PVC) 69 - 78
21 External drainage (EW pipes) 79
22 Plumbimg (C.I. pipes) 80
23 Manholes & Gulleys 81
24 Sanitary fittings 82 - 84
25 Gutters & Downpipes. 85 - 87
MATERIAL AND LABOUR ANALYSIS FOR BUILDING WORKS.
The material and labour component required for the various items of work including the minimal
plant required for same is detailed in the analysis of the Basic Rates which have been included
in the following pages.
Basic Rate.
(a) Materials.
The quantities of material required for the items are computed from known
data and experience. Their total value is calculated on the basis of current
costs of purchase at sources of supply. Unless otherwise stated wastage
is allowed in the norms.
(b) Transport.
This component provides for the cost of transport of material from sources
of supply to basis the sites of work. This component is usually added to
the material cost.
(c) Labour.
The labour wages are as approved by the Government from time to time
and on the basis of an 8 hour working day.
(d) Plant.
This component provides for the minimum plant required for the items of work.
The cost of tools and implements is provided for in the overheads allowances.
The Basic Cost is the sum of the costs of items (a), (b), (c) and (d) above.
Overhead costs include such costs that cannot be considered as direct productive work
on the job. These may be generally grouped as follows.
(a) Job Overheads. - that vary with and are caused directly by the individual jobs.
3 Temporary Works.
13 Head office rent, lights, telephone, stationary supplies, furniture etc. for same 0.60
Profit
Ten percent (10%) of the Basic costs is allowed as profit of the Contractor.
Combining the factors for overheads and the profit factors we get 35% of the Basic
Rate as the Overhead and Profit factor which is also called the 'Mark-up' on the Basic
Rate. i.e. the Basic Rate is multiplied by the factor 1.35 to obtain the working rate.
This Basic Rate Anaylsis does not include for the use of heavy plant and equipment.
This analysis provides for a labour intensive method of work with a minimal use of
machinary. The machinery allowed In this analysis is the concrete mixer, the vibrator
and a hoist in the case of a multi-storeyed building for the lift of materials to the
various floors.
If a building has more than four floors or when the Contrat period is compressed to a
few months then it will be necessary to allow of the use of heavy machinery such as
tower cranes, dumpers, loaders, batching plant for the mixing of concrete, bins for
storage of materials etc. and also for the employment of contract managers and
additional staff.
The cost of such items of work will not be accommodated within the 35% 'Mark-up'
and will have to be provided for in separate items such as preliminaries to the Contract.
Conversion - Imperial to Metric
------------------------------------------------------------------------------------------------------------------------------
To Convert To Rate Multiply
Rate per per by
------------------------------------------------------------------------------------------------------------------------------
Cube M3 0.353
Square M2 0.1075
Sq.ft M2 10.7584
L.ft M 3.28
Allowances to be made in the rates for lift in respect of work on upper floors-
In the analysis of the various items of work in the fllowing pages the rates refer to work
on the ground floor.
To these rates the percentages ( of the ground floor rates) indicate in the table below
should be added to obtain the rates applicable to the 1st, 2nd, 3rd floors. This B.S.R.
is limited to work on the ground and 3 upper floors only.
------------------------------------------------------------------------------------------------------------------------------
Ground to Ground to Ground to
1st floor 2nd floor 3rd floor
------------------------------------------------------------------------------------------------------------------------------
1) Soft/Loose soil
2) Ordinary soil
3) Hard/Dense soil
4) Mud/Wet clay
5) Soft disintegrated rock
( i.e. rock not requiring blasting)
6) Hard rock - a) Where blasting is approved.
b) Where blasting is prohibited.
2 The analysis has been prepared for each of the above categories as shown in
items nos 3 - 9.
3 However, in the preparation of estimates for purposes of calling for Tenders, only two
B.O.Q. items would be included in the B.O.Q. as against the B.S.R. item Nos. 3, 4,
5, 6, 7, 8 & 9. The description of these two B.O.Q. itmes would be as follows:
(a) Ecavation in any material met with except rock requiring blasting.
4 This classification has been adopted (where tenders are called) to avoid any dispute
that may arise as to the exact nature of the soil that will be met with when the actual
excavation is carried out. The tenderer is expected to examine the site and to form his
own opinion of the nature of the soil that is met with and rate his tender accordingly.
5 The classification of the soils in Note 1 above and the analysis provided for the different
type of soil will help the estimator in arriving at the actual cost of excavation, for which
he will have to allow in his estimate.
6 Under Note 1 (6) b Hard Rock, an analysis is provided for removing Hard Rock met
within foundation excavations where blasting is prohibited or cannot be done, like in
built ut areas where blasting can cause damage to adjoining buildings.
7 In the excavation itmes Nos 3 to 9, the labour norm allowed in the items is for an
excavation up to a maximum depth of 5'-0" an additional unskilled labourer should
be added for every additional 5'-0" or part thereof for each cube of excavation beyond
the original 5'-0" depth.
EXCAVATION
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Item Description Rate Amount
---------------------------------------------------------------------------------------------------------------------------------------------------------------
1 Removing top soil to a depth not exceeding 6" & depositing as directed within site.
Per Square
---------------------------------------------------------------------------------------------------------------------------------------------------------------
2 Excavation over site to reduce level, in any material except rock requiring blasting
including depositing and levelling as directed up to a distance not exceeding 30'-0"
Per cube
---------------------------------------------------------------------------------------------------------------------------------------------------------------
3 Excavation in trenches for walls / column pits in soft / loose soil up to 5'-0" deep and
depositing excavated material to a distance not exceeding 30'-0" (Earth work support
to be paid separately where necessary).
Per cube
4 Excavation in trenches for walls / column pits in ordinary soil up to 5'-0" deep
and depositing excavated material to a distance not exceeding 30'-0".
Per cube
---------------------------------------------------------------------------------------------------------------------------------------------------------------
5 Excavation in trenches for walls / column pits in Hard / dense soil up to a depth
of 5'-0" and depositing excavated material up to a distance not exceeding 30'-0"
Per cube
---------------------------------------------------------------------------------------------------------------------------------------------------------------
6 Excavation in trenches for walls / column pits in Mud / wet soil up to a depth
of 5'-0" and depositing excavated material to a distance not exceeding 30'-0".
Per cube
7 Excavation in trenches for walls / column pits in soft disintegrated rock ( not requiring blasting)
to a depth of 5'-0" and depositing excavated material to a distance not exceeding 30'-0".
Per cube
---------------------------------------------------------------------------------------------------------------------------------------------------------------
8 Excavation in trenches for wall / column pits in Hard rock requiring blasting up to a
depth of 5'-0' and depositing excavated material to a distance not exceeding 30'-0".
Per cube
Materials
0.75 lbs blasting powder - -
10 L.ft fuse - -
1 lb jumper steel - -
Labour
1 day Sk labourer 2,000.00 2,000.00
2 days U / Sk labourer 1,500.00 3,000.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
10 Anti - termite treatment on excavated foundation and compacted soil under floors.
Per square
Materials
16 lbs D.D.T. powder - -
( 8% in 20 glas of water)
20 gallons water 25.00 500.00
Labour
1/2 day U / Sk labourer 1,500.00 750.00
Per cube
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per cube
---------------------------------------------------------------------------------------------------------------------------------------------------------------
13 Filling under floors including levelling, watering & compacting in 3" layers
with available and selected earth at site.
Per cube
14 Filling under floors including levelling, watering & compacting in 3" layers
with imported selected earth.
Per cube
---------------------------------------------------------------------------------------------------------------------------------------------------------------
15 Cutting turf sods, loading to hand carts and transporting upto 30 yards,
laying and watering for 30 days. (Royalty for turf, pegging and transport
beyond 30 yards paid separately).
Per cube
NOTE:
EARTHWORK SUPPORT
Consider trench 15'-0" long 3'-0" wide and 5'-0" deep open planking to both faces.
Materials
17.5 cu. ft class II timber (4 uses) - -
Add 5% on above for wedges. -
Labour
1 day carpenter - -
3 days U / Sk labourer 1,500.00 4,500.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Consyder trenches 15' 0" ie long 3' 0' wide and 5' 0" height of planking to both faces.
Materials
30 cu.ft class II timber (4 uses) - -
Add 5% on above for wedges. -
Labour
2 days carpenter - -
6 days U / Sk labourer 1,500.00 9,000.00
Consider trench of lenth of 15'-0" width 5'-6" at top & 3'-6" at bottom.
Materials
100 cu.ft class II timber (4 uses) - -
Add 5% on above for wedges. -
Labour
8 days carpenter - -
20 days U / Sk labourer 1,500.00 30,000.00
Preamble
Assumptions;
1 Mixing concerte using a concerte mixer 14/10 cu.ft capacity and manual loading are
the basis on which the norms are worked.
2 A gang of one skilled and six unskilled labourers produce 3.00 cubes of concrete per
day using a 14/10 cu.ft capacity concrete mixer. This is as per accepted practice.
3 The production of concrete is at the mixer site; transporting mixed concrete and
placing same in position is paid for separately.
5 NOTE:
a) Water available at site
b) If water is not available at site allowance must be made for transport of Water .
c) Sand - includes 15% for bulking.
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Item Description Rate Amount
---------------------------------------------------------------------------------------------------------------------------------------------------------------
19 Mixing concrete 1:3:6 (1 1/2")
Per cube
Materials
13 cwt (50 Kg bags) cement 0 1,095.00 14,235.00
0.53 cubes sand 15,000.00 7,950.00
0.92 cubes 1 1/2" metal 7,000.00 6,440.00
1/3 day hire of mixer 3,000.00 1,000.00
110 gallons water 25.00 2,750.00
Labour
1 day skilled labourer 2,000.00 2,000.00
3 days U / Sk labourer 1,500.00 4,500.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per cube
Materials
14 cwt cement (50 Kg. Bags) 1,095.00 15,330.00
0.6 cubes sand 15,000.00 9,000.00
0.9 cubes 1" metal 7,000.00 6,300.00
1/3 day hire of mixer 3,000.00 1,000.00
100 gallons Water 25.00 2,500.00
Labour
1 day skilled labourer 2,000.00 2,000.00
3 days U / Sk labourer 1,500.00 4,500.00
Per cube
Materials
18 cwt cement ( 50 Kg. Bags ) 1,095.00 19,710.00
0.5 cubes sand 15,000.00 7,500.00
0.88 cubes 3/4" metal 8,500.00 7,480.00
1/3 day hire of mixer 3,000.00 1,000.00
120 gallons Water 25.00 3,000.00
Labour
1 day skilled labourer 2,000.00 2,000.00
3 days U / Sk labourer 1,500.00 4,500.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per cube
Materials
23 cwt cement ( 50 bags ) 970.00 22,310.00
0.42 cubes sand 15,000.00 6,300.00
0.82 cubes 3/4" metal 8,500.00 6,970.00
1/3 day hire of mixer 3,000.00 1,000.00
150 gallons water 25.00 3,750.00
Labour
1 day skilled labourer 2,000.00 2,000.00
3 days U / Sk labourer 1,500.00 4,500.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per cube
Materials
31 cwt cement ( 50 Kg. Bags ) 970.00 30,070.00
0.44 cubes sand 15,000.00 6,600.00
0.96 cubes 3/4" metal 8,500.00 8,160.00
1/3 day hire of mixer 3,000.00 1,000.00
200 gallons Water 25.00 5,000.00
Labour
1 day skilled labourer 2,000.00 2,000.00
3 days U / Sk labourer 1,500.00 4,500.00
24 2" thick cement concrete 1:3:6(1 1/2") screed in foundation at depths not exceeding 5'-0".
Per square
Materials
1/6 cube concrete 38,875.00 6,479.17
Add 10% for wastage 647.92
Labour
1/8 day Sk labourer 2,000.00 250.00
1/2 day U / Sk labourer 1,500.00 750.00
NOTE: For laying concrete more than 5'-0", add 1/6 day unskilled labourer for each
additional 5'-0" or part thereof per square.
---------------------------------------------------------------------------------------------------------------------------------------------------------------
25 3" thick cement concrete 1:3:6(1 1/2") screed in foundation at depths not exceeding 5'-0".
Per square
Materials
1/4 cube concrete 38,875.00 9,718.75
Add 10% for wastage 971.88
Labour
1/8 day Sk labourer 2,000.00 250.00
3/4 day U / Sk labourer 1,500.00 1,125.00
NOTE:
For laying concrete at depths more than 5'-0", add 1/4 day unskilled labourer for each
additional 5'-0" or part there-of per square.
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Item Description Rate Amount
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per square
Materials
0.5 cubes concrete 38,875.00 19,437.50
Add 5% for wastage 971.88
200 gallons Water 25.00 5,000.00
Labour
1/2 day Sk labourer 2,000.00 1,000.00
1 1/4 day U / Sk labourer 1,500.00 1,875.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Consider 24 No. columns each 4 1/2" x 6" x 10'-0" i.e. 0.45 cubes.
Materials
0.45 cubes concrete 45,190.00 20,335.50
Add 10% for wastage 2,033.55
Plant
1 day hire of vibrator 3,000.00 3,000.00
Labour
1 day mason 2,000.00 2,000.00
1 day carpenter - -
3 days U / Sk labourer 1,500.00 4,500.00
1 day Sk labourer ( Vibrator ) 2,000.00 2,000.00
Curing
100 sq.ft Jute Hessian - -
170 gallons Water 25.00 4,250.00
1 day U / Sk labourer 1,500.00 1,500.00
Consider 18 No. columns 6" x 6" each 10'-0" high i.e. 0.45 cubes.
Materials
0.45 cubes concrete 45,190.00 20,335.50
Add 10% for wastage 2,033.55
Plant
1 day hire of vibrator 800.00 800.00
Labour
1 day mason 400.00 400.00
1 day carpenter 400.00 400.00
1 day Sk labourer ( vibrator ) 300.00 300.00
3 days U / Sk labourer 240.00 720.00
Curing
80 Sf.ft Jute Hessian 10.00 800.00
140 gallons Water 5.00 700.00
1 1/2 days U / Sk labourer 240.00 360.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Consider 8 No. 9" x 9" columns each 10'-0" high I.e. 0.45 cubes.
Materials
0.45 cubes concrete 45,190.00 20,335.50
Add 10% for wastage 2,033.55
Plant
1 day hire of vibrator 3,000.00 3,000.00
Labour
1 day mason 2,000.00 2,000.00
1 day carpenter - -
1 day Sk labourer ( Vibrator ) 2,000.00 2,000.00
3 days U / Sk labourer 1,500.00 4,500.00
Curing
60 sq.ft Jute Hessian - -
100 gallons water 25.00 2,500.00
1/2 day U / Sk labourer 1,500.00 750.00
Materials
0.5 cubes concrete 45,190.00 22,595.00
Add 5% for wastage 1,129.75
Plant
1 day hire of vibrator 3,000.00 3,000.00
Labour
1 day mason 2,000.00 2,000.00
1 day carpenter - -
1 day Sk labourer ( Vibrator ) 2,000.00 2,000.00
3 days U / Sk labourer 1,500.00 4,500.00
Curing
40 sq.ft Jute Hessian - -
100 gallons water 25.00 2,500.00
1 1/2 days U / Sk labourer curing 1,500.00 2,250.00
Consider 4 No. columns 13 1/2" x 13 1/2" each 10'-0" high i.e. 0.51 cubes.
Materials
0.51 cubes concrete 45,190.00 23,046.90
Add 5% for wastage 1,152.35
Plant
1 day hire of vibrator 3,000.00 3,000.00
Labour
1 day mason 2,000.00 2,000.00
1 day carpenter - -
3 days U / Sk labourer 1,500.00 4,500.00
1 day Sk labourer ( vibrator.) 2,000.00 2,000.00
Curing
45 sq.ft Jute Hessian - -
100 gallons water 25.00 2,500.00
1 1/2 days U / Sk labourer 1,500.00 2,250.00
Materials
0.45 cubes concrete 45,190.00 20,335.50
Add 5% for wastage 1,016.78
Plant
1 day hire of vibrator 3,000.00 3,000.00
Labour
1 day mason 2,000.00 2,000.00
1 day carpenter - -
4 days U / Sk labourer 1,500.00 6,000.00
1 day Sk labourer ( vibrator ) 2,000.00 2,000.00
Curing
90 sq.ft Jute Hessian - -
180 gallons water 25.00 4,500.00
1 1/2 days U / Sk labourer 1,500.00 2,250.00
Materials
0.45 cubes concrete 45,190.00 20,335.50
Add 10% for wastage 2,033.55
Plant
1 day hire of vibrator 3,000.00 3,000.00
Labour
1 day mason 2,000.00 2,000.00
1 day carpenter - -
4 days U / Sk labourer 1,500.00 6,000.00
1 day Sk labourer ( vibrator ) 2,000.00 2,000.00
Curing
75 sq.ft Jute Hessian - -
150 gallons water 25.00 3,750.00
1 1/2 days U / Sk labourer 1,500.00 2,250.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Materials
0.45 cubes concrete 45,190.00 20,335.50
Add 10% for wastage 2,033.55
Plant
1 day hire of vibrator 3,000.00 3,000.00
Labour
1 day mason 2,000.00 2,000.00
1 day carpenter - -
4 days U / Sk labourer 1,500.00 6,000.00
1 day Sk labourer ( vibrator ) 2,000.00 2,000.00
Curing
60 sq.ft Jute Hessian - -
120 gallons water 25.00 3,000.00
1 1/2 days U / Sk labourer 1,500.00 2,250.00
Consider 5" thick slab 10'-0" x 12' -0" -Volume of concrete 0.50 cube
Materials
0.50 cube concrete 45,190.00 22,595.00
Add 10% for wastage 2,259.50
Plant
1 day hire of vibrator 3,000.00 3,000.00
Labour
1 day mason 2,000.00 2,000.00
1 day carpenter - -
1 day SK labourer ( vibrator ) 2,000.00 2,000.00
4 days U / Sk labourer 1,500.00 6,000.00
Curing
30 sq.ft Jute Hessian - -
90 gallons Water 25.00 2,250.00
1 1/2 days U / Sk labourer 1,500.00 2,250.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Materials
0.50 cube concrete 45,190.00 22,595.00
Add 10% for wastage 2,259.50
Plant
1 day hire of vibrator 3,000.00 3,000.00
Labour
1 day mason 2,000.00 2,000.00
1 day carpenter - -
1 day SK labourer ( vibrator ) 2,000.00 2,000.00
4 days U / Sk labourer 1,500.00 6,000.00
Curing
25 sq.ft Jute Hessian - -
90 gallons Water 25.00 2,250.00
1 1/2 days U / Sk labourer 1,500.00 2,250.00
Materials
0.45 cube concrete 45,190.00 20,335.50
Add 10% for wastage 2,033.55
Plant
1 day hire of vibrator 3,000.00 3,000.00
Labour
1 day mason 2,000.00 2,000.00
1 day carpenter - -
1 day Sk labourer ( vibrator ) 2,000.00 2,000.00
4 days U / Sk labourer 1,500.00 6,000.00
Curing
10 sq.ft Jute Hessian - -
90 gallons Water 25.00 2,250.00
1 1/2 days U / Sk labourer 1,500.00 2,250.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Materials
0.45 cu.ft concrete 45,190.00 20,335.50
Add 10% for wastage 2,033.55
Plant
1 day hire of vibrator 3,000.00 3,000.00
Labour
1 day mason 2,000.00 2,000.00
1 day carpenter - -
1 day Sk labourer ( vibrator ) 2,000.00 2,000.00
4 days U / Sk labourer 1,500.00 6,000.00
Curing
60 sq.ft Jute Hessian - -
90 gallons Water 25.00 2,250.00
1 1/2 days U / Sk labourer 1,500.00 2,250.00
Materials
0.45 cu.ft concrete 45,190.00 20,335.50
Add 10% for wastage 2,033.55
Plant
1 day hire of vibrator 3,000.00 3,000.00
Labour
1 day mason 2,000.00 2,000.00
1 day carpenter - -
1 day Sk labourer ( vibrator ) 2,000.00 2,000.00
4 days U / Sk labourer 1,500.00 6,000.00
Curing
55 sq.ft Jute Hessian - -
90 gallons Water 25.00 2,250.00
1 1/2 days U / Sk labourer 1,500.00 2,250.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Materials
0.45 cu.ft concrete 45,190.00 20,335.50
Add 10% for wastage 2,033.55
Plant
1 day hire of vibrator 3,000.00 3,000.00
Labour
1 day mason 2,000.00 2,000.00
1 day carpenter - -
1 day Sk labourer ( vibrator ) 2,000.00 2,000.00
4 days U / Sk labourer 1,500.00 6,000.00
Curing
40 sq.ft Jute Hessian - -
90 gallons Water 25.00 2,250.00
1 1/2 days U / Sk labourer 1,500.00 2,250.00
TIMBER FORMWORK
41 Sawn timber formwork to 9" x 9" cement concrete column in ground floor.
Per Sqr.
( A ) MAKING MOULD
1 ) Materials
18.15 sq.ft 1" thick class II timber planks - -
17.1 L.ft 2" x 2" class II timber in yokes. - -
16.12 L.ft 2" x 1" class II timber battens. - -
1 1/2 lbs wire nails. 100.00 150.00
2 ) Fabricanting
1/2 day carpenter - -
1/2 day U / Sk labourer 1,500.00 750.00
2 ) Labour
1 1/2 days carpenter - -
2 days U / Sk labourer 1,500.00 3,000.00
( B ) Assembling
( A ) Making panels
1 ) Materials
220 sq.ft 1" thick tongue and grooved timber planks. - -
121 L.ft 4" x 2" runners at 2'-0" centres. - -
4 lbs. wire nails. 100.00 400.00
2 ) labour
3 days carpenter - -
3 days U / Sk labourer 1,500.00 4,500.00
( B ) Assembling
Materials
690 L.ft 4" x 2" vertical timber props. ( 10 uses. ) - -
66 L.ft 2" x 2" bracing for props. - -
122 No. wedges - -
33 sq.ft 1" base plates for props. - -
Total cost for assembling per use for 200 sq.ft 10,670.00
(A+B+C+D)
STEEL REINFORCEMENTS
44 Mild steel / Tor steel reinforcement to lintels, slabs, beams or columns bent to shape
laid in position and tied with G . I . wire as directed.
Materials
1 cwt M. S./ Tor steel rods including 2,760.00 2,760.00
transport to site.
Allow 15% for wastage 414.00
Labour
1 day blacksimth - -
1 day U / Sk labourer 1,500.00 1,500.00
BRICKWORK
Per cube
Materials
1450 bricks 12.00 17,400.00
Add 5% wastage 870.00
4 cwt cement ( 50 Kg bags ) 970.00 3,880.00
0.25 cubes sand 15,000.00 3,750.00
150 gallons water 25.00 3,750.00
Labour
3 days mason 2,000.00 6,000.00
4 days U / Sk labourer 1,500.00 6,000.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per cube
Materials
1450 Nos. bricks 12.00 17,400.00
Add 5% wastage 870.00
2 1/3 cwt cement ( 50 Kg bags ) 970.00 2,263.33
3/8 cubes sand 15,000.00 5,625.00
150 gallons water 25.00 3,750.00
Labour
3 days mason 2,000.00 6,000.00
4 days U / Sk labourer 1,500.00 6,000.00
47 Brick work in cement and sand 1:5 in 4 1/2" thick walls in ground floor
Per square
Materials
550 Nos. bricks 12.00 6,600.00
Add 5% wastage 330.00
1.3 cwt cement ( 50 Kg bags ) 970.00 1,261.00
1/10 cubes sand 15,000.00 1,500.00
50 gallons water 25.00 1,250.00
Labour
1 1/2 days mason 2,000.00 3,000.00
2 days U / Sk labourer 1,500.00 3,000.00
Scaffolding - Add 5% of labour cost 300.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
48 9" thick brick wall in cement & sand 1:5 in ground floor
Per square
Materials
1090 Nos. bricks 12.00 13,080.00
Add 5% for wastage 654.00
3 cwt cement ( 50 Kg bags ) 970.00 2,910.00
0.2 cubes sand 15,000.00 3,000.00
115 gallons water 25.00 2,875.00
Labour
2 1/4 days mason 2,000.00 4,500.00
3 3/4 days U / Sk labourer 1,500.00 5,625.00
Scaffolding - Add 3% of labour cost 303.75
49 Brickwork 13 1/2" thick in cement & sand 1:5 in superstructure in ground floor
Per square
Materials
1630 Nos. bricks 12.00 19,560.00
Add 5% for wastage 978.00
4.5 cwt cement ( 50 Kg bags ) 970.00 4,365.00
0.3 cubes sand 15,000.00 4,500.00
170 gallons water 25.00 4,250.00
Labour
3 1/2 days mason 2,000.00 7,000.00
5 1/2 days U / Sk labourer 1,500.00 8,250.00
Scaffolding - Add 2% of labour cost 305.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
50 9" thick brick wall in cement & sand 1:5 in superstructure in ground floor
Materials
1090 Nos. bricks 12.00 13,080.00
Add 5% for wastage 654.00
1.75 cwt cement ( 50 Kg bags ) 970.00 1,697.50
0.3 cubes sand 15,000.00 4,500.00
115 gallons water 25.00 2,875.00
Labour
2 1/4 days mason 2,000.00 4,500.00
3 days U / Sk labourer 1,500.00 4,500.00
Scaffolding - Add 3% of labour cost 270.00
51 4 1/2" thick brick wall ( wire cut ) in cement & sand 1:5 in ground floor
Per square
Materials
550 Nos. wire cut bricks 12.00 6,600.00
Add 2% for wastage 132.00
1.2 cwt cement ( 50 Kg bags ) 970.00 1,164.00
0.08 cubes sand 15,000.00 1,200.00
30 gallons water 25.00 750.00
Labour
1 1/2 days mason 2,000.00 3,000.00
2 days U / Sk labourer 1,500.00 3,000.00
Scaffolding - Add 5% of labour cost 300.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
52 9" thick brick in cement & sand 1:5 with wire cut bricks
Per square
Materials
1080 Nos. wire cut bricks 12.00 12,960.00
Add 4% for wastage 518.40
2.5 cwt cement ( 50 Kg bags ) 970.00 2,425.00
0.18 cubes sand 15,000.00 2,700.00
100 gallons water 25.00 2,500.00
Labour
2 1/4 days mason 2,000.00 4,500.00
3 3/4 days U / Sk labourer 1,500.00 5,625.00
Scaffolding - Add 3% of labour cost 303.75
53 13 1/2" thick brick wall ( wire cut ) in cement & sand 1:5 in ground floor
Per square
Materials
1630 Nos. wire cut bricks 12.00 19,560.00
Add 2% for wastage 391.20
4.5 cwt cement ( 50 Kg bags ) 970.00 4,365.00
0.3 cubes sand 15,000.00 4,500.00
150 gallons water 25.00 3,750.00
Labour
3 3/4 days mason 2,000.00 7,500.00
5 1/2 days U / Sk labourer 1,500.00 8,250.00
Scaffolding - Add 2% of labour cost 315.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
54 Extra over for facing including raised pointing 1 / 8" thick in cement and sand
1:1 mixture in ground floor
Per square
Materials
0.5 cwt cement ( 50 Kg bags ) 970.00 485.00
1 cu.ft sand 150.00 150.00
1/10 gallons acid - -
10 gallons water 25.00 250.00
Labour
5 days mason 2,000.00 10,000.00
3 1/2 days U / Sk labourer 1,500.00 5,250.00
55 3" thick brick paved floor in lime sand mortar 2 : 5 in ground floor
Per square
Materials
350 Nos. bricks 12.00 4,200.00
1.2 cwt slaked lime 970.00 1,164.00
0.11 cubes sand 15,000.00 1,650.00
45 gallons water 25.00 1,125.00
Labourer
1 1/4 days mason 2,000.00 2,500.00
2 1/2 days U / Sk labourer 1,500.00 3,750.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
56 Steps 1'-11/2" x 0'-6" in brick in cement and sand 1:5 with 1/2" thick cement
and sand 1:2 rendering including necessary excavation.
Per 10 L.ft
Materials
120 Nos. bricks 12.00 1,440.00
0.5 cwt cement ( 50 Kg bags ) 970.00 485.00
0.05 cubes sand 15,000.00 750.00
15 gallons water 25.00 375.00
Labour
1/2 day mason 2,000.00 1,000.00
1/2 day U / Sk labourer 1,500.00 750.00
57 Brick drains in cement and sand 1 : 5, 9" wide and 6" - 9" average depth
including cement rendering 1/2" thick 1:2 to exposed faces with 1'-6" ramp
including necessary excavation.
Per 10 L.ft
Materials
140 Nos bricks 12.00 1,680.00
0.8 cwt cement ( 50 Kg bags ) 970.00 776.00
0.05 cubes sand 15,000.00 750.00
20 gallons water 25.00 500.00
Labour
1 1/4 days mason 2,000.00 2,500.00
1 1/4 days U / Sk labourer 1,500.00 1,875.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
58 Brick drains in cement and sand 1 : 5, 9" wide and 6" - 9" average depth
including cementrendering 1/2" thick 1:2 to exposed faces without ramp
including necessary excavation.
Per 10 L.ft
Materials
110 bricks 12.00 1,320.00
0.7 cwt cement ( 50 Kg bags ) 970.00 679.00
0.04 cubes sand 15,000.00 600.00
15 gallons water 25.00 375.00
Labour
1 days mason 2,000.00 2,000.00
1 1/4 days U / Sk labourer 1,500.00 1,875.00
HOLLOW BLOCKWORK
59 8" thick Hollow blockwork in cement and sand mortar 1 : 5 in ground floor
( Cavities unfilled )
Per square
10'-0" x 10'-0" area ( size of each block 16" x 8" x 8" )
Materials
112 Nos Hollow cement block - -
Allow 5% for wastage -
0.75 cwt cement ( 50 Kg bags ) 970.00 727.50
0.06 cubes sand 15,000.00 900.00
Labour
1 1/2 days mason 2,000.00 3,000.00
2 1/2 days U / Sk labourer 1,500.00 3,750.00
Add 3% for Scaffolding 202.50
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per square
10'-0" x 10'-0" area ( size of each block 16" x 8" x 4" )
Materials
112 Nos. Hollow cement block 35.00 3,920.00
Allow 5% for wastage 196.00
0.4 cwt cement ( 50 Kg bags ) 970.00 388.00
0.03 cubes sand 15,000.00 450.00
Labour
1 days mason 2,000.00 2,000.00
2 days U / Sk labourer 1,500.00 3,000.00
Add 5% for Scaffolding 250.00
RUBBLE MASONRY
Materials
1.3 cubes 6" - 9" rubble 5,000.00 6,500.00
7.25 cwt cement ( 50 Kg bags ) 970.00 7,032.50
0.3 cube sand 15,000.00 4,500.00
100 gallons water 25.00 2,500.00
Labour
4 days mason 2,000.00 8,000.00
6 days U / Sk labourer 1,500.00 9,000.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Materials
1.3 cubes 6" - 9" rubble 5,000.00 6,500.00
7.25 cwt cement ( 50 Kg bags ) 970.00 7,032.50
0.3 cube sand 15,000.00 4,500.00
100 gallons water 25.00 2,500.00
Labour
4 1/2 days mason 2,000.00 9,000.00
7 days U / Sk labourer 1,500.00 10,500.00
Add 3% for Scaffolding 585.00
TILE WORKS
Per square
Materials
225 Nos. pressed tiles 8" x 8" - -
Add 5% for wastage -
1 1/4 cwt cement ( 50 Kg bags ) 970.00 1,212.50
0.07 cube sand 15,000.00 1,050.00
1/4 lb wax polish - -
1/4 lb coloured pigment - -
2 lbs cotton waste - -
Labour
4 days Special mason 2,500.00 10,000.00
4 days U / Sk labourer 1,500.00 6,000.00
1/2 day U / Sk labourer for polishing 1,500.00 750.00
Per square
Materials
400 Nos galzed tiles 6" x 6" - -
Add 10% for wastage on cutting -
2 1/2 cwt cement ( 50 Kg bags ) 970.00 2,425.00
0.11 cube sand 15,000.00 1,650.00
1 lb white cement - -
Labour
4 days Special mason 2,500.00 10,000.00
4 days U / Sk laboruer 1,500.00 6,000.00
1/4 day U / Sk laboruer for cleaning 1,500.00 375.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
65 Terrazzo floor tiles on 1/2" thick cement and sand 1 : 2 in ground floor
Per square
Materials
100 Nos 12" x 12" terrazzo tiles - -
Add 5% for wastage -
1 1/4 cwt cement ( 50 kg bags ) 970.00 1,212.50
0.07 cubes sand 15,000.00 1,050.00
2 lbs Coloured pigment - -
1/2 lb wax polish - -
2 lb cotton waste - -
Labour
4 days Special mson 2,500.00 10,000.00
3 days U / Sk labourer 1,500.00 4,500.00
1/2 day U / Sk labourer ( polishing ) 1,500.00 750.00
ROOF WORK
66 Timber framework for calicut pattern tile hip roof in single storey building
consisting of wall plate, beam, ridge plate, rafters etc. (Preservative
treatment to be measured separately.)
Materials
34 cu.ft class 1 timber - -
Add 10% for wastage -
660 l.ft 2" x 1" reepers - -
Add 5% for wastage -
8 lbs wire nails 6" long 100.00 800.00
2 lbs wire nails 2" long 100.00 200.00
Labour
7 days carpenter - -
8 days U / Sk labourer 1,500.00 12,000.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
67 Roof covering with calicut pattern clay tiles in single storeyed building
(Timber frame work & ridge covering measured separately)
Materials
750 nos. tiles - -
Labour
3 days carpenter - -
3 days U / Sk labourer 1,500.00 4,500.00
68 Timber framework for corrugated asbestos sheet roof in single storeyed building.
Materials
13 1/4 cu.ft timber purlins - -
Add 10% for wastage -
Labour
2 1/2 days carpenter - -
3 days U / Sk labourer 1,500.00 4,500.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
69 Roof covering with corrugated asbestos sheets ( Timber frame work & ridge
covering measured separately )
Materials
420 sq.ft asbestos corrugated sheets. - -
72 Nos. roofing screws and washers. - -
Labour
1 days carpenter - -
2 days U / Sk labourer 1,500.00 3,000.00
70 One layer half round clay tiles over corrugated asbestos roof covering
Per square
Materials
650 Nos half round clay tiles - -
Labour
2 days U / Sk labourer 1,500.00 3,000.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
71 Asbestos close fittings ridging fixed complete with roofing screws or bols ( hook )
Materials
4 pairs ridges 3' - 8" long - -
16 nos. roofing screws or bolts - -
Labour
1/4 day carpenter - -
1/4 day U / Sk labourer 1,500.00 375.00
72 Ridging covering with calicut pattren ridge tiles bedded in cement lime mortar 1 : 1 : 4
Materials
9 nos. ridge tiles - -
1/3 cwt cement ( 50 Kg bags ) 970.00 323.33
0.02 cube sand 15,000.00 300.00
15 lbs slaked lime - -
1/2 lb colouring powder - -
Labour
1/4 day mason 2,000.00 500.00
1/4 day U / Sk labourer 1,500.00 375.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
73 3/4" x 9" high valance board fixed with brass screws to ends of rafters ( for tile roofing )
Materials
75 sq.ft 1" thick planks 90.00 6,750.00
Add 5% for wastage 337.50
70 Nos. 1 1/2" brass screws - -
Labour
3 days carpenter - -
3 days U / Sk labourer 1,500.00 4,500.00
Add 5% for scaffolding 225.00
74 3/4" x 9" high valance board fixed with brass screws at 2'-0" centres to sides of rafters.
Materials
75 sq.ft 1" thick planks 90.00 6,750.00
Add 5% for wastage 337.50
50 Nos. 1 1/2" brass screws - -
Labour
3 days carpenter - -
3 days U / Sk labourer 1,500.00 4,500.00
Add 5% for scaffolding 225.00
ROOF PLUMBING
75 18 B.W.G.( 1.2 mm ) galvanised iron sheet valley gutter 3'-0" girth overall once bent with
end laps not less than 9" width including 3/4" tongued and grooved planks laid to slope
and profile on timber and profile on members.
Materials
2 no. G.I. sheet ( 8' x 4' ) - -
1/4 gal wood preservative - -
0.1 cwt cememnt ( 50 Kg bags ) 970.00 97.00
0.05 cwt slaked lime - -
1 cu.ft sand 15,000.00 150.00
50 sq.ft planks - -
2 lbs 1 1/2" wire nails 100.00 200.00
Labour
Building sides
1/4 day mason 2,000.00 500.00
1/2 day U / Sk labourer 1,500.00 750.00
76 18 B.W.G. ( 1.2 mm ) galvanised iron flashing 1'-6" girth overall 3 times bent with
end laps notless than 6", lead soldered, turned and tucked up to not less than 6"
in to chase cut in wall and pointed in cement morter 1:2 lower end dressed over
roof covering not less than 1'-0" wide.
Materials
1 no. G.I. sheet ( 8' x 4' ) - -
0.05 cwt cememnt ( 50 Kg bags ) 970.00 48.50
1 cu.ft sand 150.00 150.00
1 lbs soldering lead - -
Labour
Building sides
1/4 day mason 2,000.00 500.00
1/2 day U / Sk labourer 1,500.00 750.00
CEILING WORK
77 Timber framework for 4'-0" x 4'-0" flat asbestos ceiling ( sheet measured separately ),
comprising of 4" x 2" joists and 2" x 2" bearers in class I timber.
Materials
8 cu.ft timber class I - -
1 lb 2" nails 100.00 100.00
26 Nos. fiber / plastic plugs - -
25 lbs cement 970.00 220.45
2 cu.ft sand 15,000.00 300.00
1/4 use 2" brush - -
1/3 gal tarnap - -
Labour
2 1/2 days carpenter - -
1/2 day mason 2,000.00 1,000.00
1 1/2 days U / Sk labourer 1,500.00 2,250.00
Add 5% for scaffolding 162.50
---------------------------------------------------------------------------------------------------------------------------------------------------------------
78 Horizontal ceiling lining using 4' 0" x 4' 0" flat asbestos cement sheet fixed with
and including beading and cove mouldings on timber framework.(Timber framework
& painting measured separately)
Materials
210 sq.ft flat asbestos sheets - -
60 l.ft 2" x 2" Halmilla cove mouldings - -
125 l.ft 1/2" x 1 1/2" Halmilla beadings - -
1/4 lb 1/4" clout headed nails - -
96 nos 1 1/2" brass screws - -
Labour
1 1/2 days carpenter - -
2 days U / Sk labourer 1,500.00 3,000.00
Add 5% for scaffolding 150.00
79 3/4" thick tongued and grooved Lunumidella ceiling boards fixed horizontal
on 4" x 2" class I timber Joists at 2'-0" centres with 1 1/2" brass nails.
Materials
115 l.ft 4" x 2" timber joists 65.00 7,475.00
215 sq.ft 6" x 3/4" Lunumidella ceiling planks. - -
3 lbs cement 970.00 26.45
4 cu.ft sand 15,000.00 600.00
4 Kg 1 1/2" brass nails - -
Labour
Making holes, fixing joints & making good -
1 day mason 2,000.00 2,000.00
1 day carpenter - -
3 days U / Sk labourer 1,500.00 4,500.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
80 3/4" x 6" wide tongued and grooved Lunumidella ceiling boards fixed to
underside of roof rafters, (existing) with 1 1/2" brass nails including levelling
with timber strips where necessary.
Materials
220 sq.ft ceiling planks - -
40 l.ft 2" x 1/4" timber strips - -
2 Kg 3/4" nails 100.00 200.00
4 Kg 1 1/2" brass nails - -
Labour
3 days carpenter - -
6 days U / Sk labourer 1,500.00 9,000.00
Add 3% for scaffolding 270.00
81 Door single hung 3'-3" x 7'-0" high overall with frame having 1 1/4" thick sash and
3 3/4"x 2 3/4" timber frame (glazing, ironmongery & painting measured separately)
Materials
a) Frame -
1 1/2 cu.ft 4" x 3" timber - -
2 No. spur stones - -
6 No. fiber/plastic plugs with 4" long brass screws - -
2 No. 5/8" mild steel dowels 4" long - -
b) Sash -
14 sq.ft 1 1/2" planks - -
5 sq.ft 1" planks 90.00 450.00
Labour
5 days carpenter - -
1 1/2 days U / Sk labourer 1,500.00 2,250.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
82 Door glazed and panelled double hung 4'-0" x 7'-0" high overall with frame
including 1 1/4" thick sash and 3 3/4" x 2 3/4" frame (Glazing, ironmongery
& painting measured separately)
Materials
a) Frame -
1 2/3 cu.ft 4" x 3" timber - -
2 No. spur stones - -
6 No. fiber / plastic plugs with 4" long screws - -
2 No. 5/8" dia mild steel dowels 4" long - -
b) Sashes -
16 sq.ft 1 1/2" planks - -
7 sq.ft 1" planks 90.00 630.00
Labour
6 days carpenter - -
2 days U / Sk labourer 1,500.00 3,000.00
83 Plywoood door single hung 3'-1 1/2" x 6'-11 1/2" overall with frame having 1 1/4" thick
sash and 3 1/4" x 2 1/4" frame . ( Iron-mongery and painting measrued separately ).
Materials
a) Frame -
1.8 cu.ft 4" x 3" timber - -
2 No. spur stones - -
6 No. fiber/plastic plugs with 4" long brass screws - -
b) Sash -
1 No. 6'-9" x 2'-9" plywood sash - -
Labour
3/4 day carpenter - -
3/8 day U / Sk labourer 1,500.00 562.50
1/4 day mason ( fixing frame ) 2,000.00 500.00
1/4 day U / Sk labourer ( - do - ) 1,500.00 375.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
84 Door ledged, braced and battened single hung 2'-6" x 6'-6" overall, with frame
having 7/8" thick tongued & grooved planks and 3 3/4" x 2 3/4" frame.
(Ironmongery & painting measured separately)
Materials
a) Frame -
1.7 cu.ft 4" x 3" timber - -
2 No. spur stones - -
6 No. fiber/plastic plugs with 4" long brass screws - -
2 No. 5/8" mild steel dowels 4" long. - -
b) Sash -
21 sq.ft 1" thick planks 90.00 1,890.00
3 doz 1 1/4" long brass screws. - -
Labour
2 1/4 day carpenter - -
1 day U / Sk labourer 1,500.00 1,500.00
1/4 day mason ( fixing frame ) 2,000.00 500.00
1/4 day U / Sk labourer ( - do - ) 1,500.00 375.00
85 Window, glazed 7'-0" x 4'-0" high overall with frame comprising 3 No.
openable sashes and 3 3/4" x 2 3/4" frame and mullions.
Materials
a) Frame -
3.2 cu.ft 4" x 3" timber - -
4 No fiber/plastic plugs with 4" long brass screws - -
b) Sashes -
9.25 sq.ft 3" x 1 1/2" timber - -
Labour
6 days carpenter - -
2 1/2 days U / Sk labourer 1,500.00 3,750.00
1/2 day mason ( fixing frame ) 2,000.00 1,000.00
1/2 day U / Sk labourer ( - do - ) 1,500.00 750.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
86 1/6" clear sheet glass panes exceeding 1 but not exceeding 4 square feet
cut and fixed with timber beadings to doors and windows.
Consider sash 3'-0"x4'-0" high with 3" x 1 1/4" stile and 4 Nos. glass panes.
Materials
9 sq.ft glass panes - -
30 L.ft 1/2" x 1/2" beading - -
4 doz brass panel pins - -
Labour
1/2 day glazier - -
1/2 day U / Sk labourer 1,500.00 750.00
IRONMONGARY
Per Pair.
Materials
1 1/2 pairs butt hinges - -
24 nos 3/4" brass screws - -
Labour
1/4 day carpenter - -
1/4 day U / Sk labourer 1,500.00 375.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per Pair.
Materials
1 pair Tee hinges - -
24 nos 3/4" iron screws - -
Labour
1/4 day carpenter - -
1/4 day U / Sklabourer 1,500.00 375.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
89 Rim lock
Per No.
Materials
1 No rim lock with screws - -
Labour
1/4 day carpenter - -
1/4 day U / Sklabourer 1,500.00 375.00
90 Mortice lock
Per No.
Materials
1 No mortice lock with screws - -
Labour
1/2 day carpenter - -
1/2 day U / Sklabourer 1,500.00 750.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
91 Casement stays.
Per No.
Materials
4 Nos csaement stays - -
16 Nos 1/2" brass screws - -
Labour
1/4 day carpenter - -
1/4 day U / Sk labourer 1,500.00 375.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per No.
Materials
1 No door closer - -
8 Nos 3/4' brass screws - -
Labour
1/4 day carpenter - -
1/4 day U / Sk labourer 1,500.00 375.00
Per No.
Materials
1 No Tower / Skeleton bolt - -
10 Nos 1/2" brass screws - -
Labour
1/2 hr carpenter - -
1/2 hr U / Sk labourer 1,500.00 750.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
94 Barrel bolt 4"
Per No.
Materials
1 No barrel bolt - -
8 Nos 1/2' brass screws - -
Labour
1/2 hr carpenter - -
1/2 hr U / Sk labourer 1,500.00 93.75
---------------------------------------------------------------------------------------------------------------------------------------------------------------
95 Casement fasteners.
Per No.
Materials
6 Nos casement fasteners - -
24 Nos 1/2" brass screws - -
Labour
1/2 day carpenter - -
1/2 day U / Sk labourer 1,500.00 750.00
Per No.
Materials
6 Nos brass fanlight catches - -
24 nos 1/2" brass screws - -
Labour
1/2 day carpenter - -
1/2 day U / Sk labourer 1,500.00 750.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
97 Draw rings
Per No.
Materials
6 Nos draw rings - -
12 nos 1/2" brass screws - -
Labour
1/4 day carpenter - -
1/4 day U / Sk labourer 1,500.00 375.00
PLASTERWORKS.
98 3/4" thick DPC, in cement sand 1:2 finished with 2 coats hot tar and blinded with sand.
Per square
Materials
2.25 cwt cement ( 50 Kg bags ) 970.00 2,182.50
0.11 cube sand 15,000.00 1,650.00
1 1/2 gals bitumen - -
10 lbs Firewood - -
10 gallons water 25.00 250.00
Labour
1 1/4 days mason 2,000.00 2,500.00
2 1/2 days U / Sk labourer 1,500.00 3,750.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
99 3/4" thick plastering to wall in lime and sand 2 : 5 including floating with lime putty.
Per square
Materials
1.3 cwt slaked lime - -
0.07 cube sand 15,000.00 1,050.00
10 gallons water 25.00 250.00
Labour
1 day mason 2,000.00 2,000.00
1 3/4 days U / Sk labourer 1,500.00 2,625.00
Add 3% for scaffolding 138.75
100 5/8" thick plastering to wall in lime and sand 2 : 5 including floating with lime putty.
Per square
Materials
1.4 cwt cement ( 50 Kg bags ) 970.00 1,358.00
0.06 cube sand 15,000.00 900.00
10 gallons water 25.00 250.00
Labour
1 days mason 2,000.00 2,000.00
1 1/2 days U / Sk labourer 1,500.00 2,250.00
Add 3% for scaffolding 127.50
---------------------------------------------------------------------------------------------------------------------------------------------------------------
101 3/8" thick plastering to soffit of slab in cement and sand 1 : 3 including
floating with lime putty.
Per square
Materials
0.8 cwt cement ( 50 Kg bags ) 970.00 776.00
0.16 cwt salked lime - -
0.03 cube sand 15,000.00 450.00
5 gallons water 25.00 125.00
Labour
2 1/2 days mason 2,000.00 5,000.00
2 1/2 days U / Sk labourer 1,500.00 3,750.00
Add 3% for scaffolding 262.50
102 3/8" thick plastering to sides and soffit of beams in cement and sand 1 : 3
including floating with lime putty.
Per Sqr.
Materials
Labour
2 days mason 2,000.00 4,000.00
2 days U / Sk labourer 1,500.00 3,000.00
Add 3% for scaffolding 210.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
103 5/8" thick plastering to wall in lime, cement and sand 1 : 1 : 5 finished semi
rough with wooden floating.
Per square
Materials
0.8 cwt cement ( 50 Kg bags ) 970.00 776.00
0.4 cwt salked lime - -
0.07 cube sand 15,000.00 1,050.00
10 gallons water 25.00 250.00
Labour
1 day mason 2,000.00 2,000.00
1 1/4 days U / Sk labourer 1,500.00 1,875.00
Add 3% for saffolding 116.25
104 5/8" thick plastering to wall in lime, cement and sand 1 : 1 : 5 finished
smooth with lime putty floating.
Per square
Materials
0.8 cwt cement ( 50 Kg bags ) 970.00 776.00
0.6 cwt salked lime - -
0.07 cube sand 15,000.00 1,050.00
10 gallons water 25.00 250.00
Labour
1 day mason 2,000.00 2,000.00
1 1/4 days U / Sk labourer 1,500.00 1,875.00
Add 3% for scaffolding 116.25
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per square
Materials
1.07 cwt cement ( 50 Kg bags ) 970.00 1,037.90
0.05 cube sand 15,000.00 750.00
10 gallons water 25.00 250.00
Labour
1 day mason 2,000.00 2,000.00
1 1/2 days U / Sk labourer 1,500.00 2,250.00
1/4 day U / Sk labourer ( curing ) 1,500.00 375.00
106 1/2" thick rendering in cement and sand 1 : 2 in floors, finished smooth.
Per square
Materials
1.5 cwt cement ( 50 Kg bags ) 970.00 1,455.00
0.05 cube sand 15,000.00 750.00
10 gallons water 25.00 250.00
Labour
1 day mason 2,000.00 2,000.00
1 1/2 days U / Sk labourer 1,500.00 2,250.00
1/4 day U / Sk labourer ( curing ) 1,500.00 375.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per square
Materials
1.75 cwt cement ( 50 Kg bags ) 970.00 1,697.50
0.08 cube sand 15,000.00 1,200.00
10 gallons water 25.00 250.00
Labour
1 1/4 days mason 2,000.00 2,500.00
2 days U / Sk labourer 1,500.00 3,000.00
1/4 day U / Sk labourer ( curing ) 1,500.00 375.00
108 3/4" thick rendering in cement and sand 1 : 2 in floors finished smooth.
Per square
Materials
2.25 cwt cement ( 50 Kg bags ) 970.00 2,182.50
0.08 cube sand 15,000.00 1,200.00
10 gallons water 25.00 250.00
Labour
1 1/4 days mason 2,000.00 2,500.00
2 days U / Sk labourer 1,500.00 3,000.00
1/4 day U / Sk labourer ( curing ) 1,500.00 375.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
109 3/4" thick rendering in cement and sand 1 : 2 in coloured cement floors finished smooth.
Per square
Materials
2.25 cwt cement ( 50 Kg bags ) 970.00 2,182.50
0.05 cube sand 15,000.00 750.00
5 lbs powder pigment 25.00 125.00
10 gallons water
Labour
1 1/4 days mason 2,000.00 2,500.00
2 days U / Sk labourer 1,500.00 3,000.00
1/4 day U / Sk labourer ( curing ) 1,500.00 375.00
110 1/2" x 6" skirting in cement and sand 1:3 projected or flush to walls finished
with floating including forming groove.
Per 10 L.ft
Materials
0.1 cwt cement ( 50 Kg bags ) 970.00 97.00
0.003 cube sand 15,000.00 45.00
0.25 lbs powdered pigment 25.00 6.25
Labour
3/8 days mason 2,000.00 750.00
5/16 days U / Sk labourer 1,500.00 468.75
NOTE:
Where coloured skirting is not required , delete provision for powdered pigment.
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Item Description Rate Amount
---------------------------------------------------------------------------------------------------------------------------------------------------------------
111 Prepare and apply one coat of preservative (oil type) to structural timber
including touching up cut ends etc. after fixing.
Per square
Materials
2.75 ltr. Wood preservative (oil type) -
1/10 use 3" brush - -
Labour
3/4 day painter - -
1/2 day U / Sk labourer 1,500.00 750.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
112 Prepare surface of steel truss and apply two coats of anticorrosive primer.
Materials
2 1/4 ltr anti - corrosive primer - -
0.15 ltr mineral turpentine or thinner - -
1 No. wire brush - -
1/8 use 2" brush - -
Labour
1 1/2 days painter - -
1 1/2 days U / Sk labourer 1,500.00 2,250.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
113 Apply one coat of anti-corrosive primer and two coats enamel paint on
already shop primed and erected steel roof truss.
Materials
0.2 ltr. anti - corrosive primer - -
1 1/3 ltr. enamel paint - -
0.2 ltr. mineral turpentine or thinnner - -
1/5 use 2" brush - -
Labour
2 1/2 days painter - -
1 day U / Sk labourer 1,500.00 1,500.00
Add 3% for scaffolding 45.00
Cost per square 1,545.00
20% Overheads & Profit 309.00
114 Perpare and apply two coats primer and finishing coat of enamel
paint to mild steel ( angle/flat ) gate
Consider 50 sq.ft
Materials
1 1/2 ltr. anti - corrosive primer - -
2/3 ltr. enamel paint - -
0.2 ltr. mineral turpentine or thinnner - -
1/2 use wire brush - -
1/5 use 2" brush - -
Labour
1/2 day painter - -
3/4 day U / Sk labourer 1,500.00 1,125.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
115 Painting steel on new work with 2 coats of anti - corrosive paint
Per square
Materials
2/3 ltr anti - corrosive paint - -
1/5 use 2" brush - -
Labour
1 1/2 days painter - -
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per square
Materials
1/2 gallon Wood preservative 338.00 169.00
1/5 use 2" brush - -
Labour
1/2 day painter - -
117 Preparing and painting wood work with primer and 2 coats enamel paint
Per square
Materials
3/4 ltr. Wood primer - -
2.5 ltr. enamel paint ( 2 coats ) - -
1/10 use 2" brush - -
2 nos sand papers - -
Labour
1 1/2 days painter - -
1/2 day U / Sk labourer 1,500.00 750.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per 10 squares
Materials
0.5 cwt boiled lime - -
2 lbs salt - -
1/2 lb yellow ochre - -
2 ozs blue - -
1/3 use 6" brush - -
10 gallons water 25.00 250.00
Labour
2 1/2 days painter - -
2 1/2 days U / Sk labourer 1,500.00 3,750.00
Add 3% for scaffolding 112.50
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per 10 squares
120 Prepare and apply one coat of Alkali resistant primer and two
coats of emulsion paint to walls.
Per square
Materials
0.9 ltr primer - -
1.4 ltr emulsion paint - -
1 gallon water 25.00 25.00
1/10 use 6" brush - -
2 nos sand papers - -
Labour
1 1/4 days painter - -
Add 3% for scaffolding -
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per 10 squares
Materials
5/8 cwt cement ( 50 Kg bags ) 970.00 606.25
1 no. 6" coir brush - -
5 gallons water 25.00 125.00
Labour
2 days painter - -
2 days U / Sk labourer 1,500.00 3,000.00
Add 3% for scaffolding 90.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per square
123 Prepare and apply one coat alkali resistant primer and two coats of emulsion
paint to soffit of slabs.
Materials
0.9 ltr wall primer - -
1.5 ltr emulsion paint - -
1/10 use 6" brush - -
Labour
1 3/4 days painter - -
Add 3% for scaffolding -
---------------------------------------------------------------------------------------------------------------------------------------------------------------
124 Varnishing two coats with copal varnish after sand papering
Per square
Materials
1.8 ltr. varnish - -
1/3 use 3" brush - -
2 No. sand papers - -
Labour
1/2 day painter - -
1/2 day U / Sk labourer 1,500.00 750.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per square
Materials
3/4 lb wax polish - -
6 nos. sheets sand papers - -
1/10 use floor brush - -
1/2 yards flannel cloth - -
Labour
3 hrs. U / Sk labourer 1,500.00 562.50
126 1/2" diameter PVC pipes fixed to walls ( specials paid separately )
Per 10 L.ft
Materials
13 L.ft pipes - -
3 Nos clips and nails - -
2 grms solvent cement - -
Labour
1 hr plumber - -
1 hr U / Sk labourer 1,500.00 187.50
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per 10 L.ft
Materials
13 L.ft pipes - -
3 Nos clips and nails - -
3 grms solvent cement - -
Labour
1 hr plumber - -
1 hr U / Sk labourer 1,500.00 187.50
128 1" diameter PVC pipes fixed to walls ( specials paid separately )
Materials
100 L.ft pipes - -
Add 5% for wastage -
8 Nos 1" dia sockets - -
32 grns. Solvent cement - -
35 Nos clips and nails - -
Labour
1/2 day plumber - -
1/2 day U / Sk labourer 1,500.00 750.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
129 1 1/4" diameter PVC pipes fixed to walls ( specials paid separately )
Materials
100 L.ft pipes - -
Add 5% for wastage -
8 Nos 1 1 / 4" dia sockets - -
48 grns. Solvent cement - -
35 Nos clips and nails - -
Labour
3/4 day plumber - -
3/4 day U / Sk labourer 1,500.00 1,125.00
130 1 1/2" diameter PVC pipes laid to walls ( specials paid separately )
Materials
100 L.ft pipes - -
Add 5% for wastage -
8 Nos 1 1 / 2" dia sockets - -
64 grns. Solvent cement - -
35 Nos clips and nails - -
Labour
3/4 day plumber - -
3/4 day U / Sk labourer 1,500.00 1,125.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
131 2" diameter PVC pipes laid to walls ( specials paid separately )
Materials
100 L.ft pipes - -
Add 5% for wastage -
8 Nos 2" dia sockets - -
112 grns. Solvent cement - -
35 Nos clips and nails - -
Labour
3/4 day plumber - -
3/4 day U / Sk labourer 1,500.00 1,125.00
132 3" diameter PVC pipes laid to walls ( specials paid separately )
Materials
100 L.ft pipes - -
Add 5% for wastage -
8 Nos 3" dia sockets - -
200 grns. Solvent cement - -
35 Nos clips and nails - -
Labour
1 day plumber - -
1 day U / Sk labourer 1,500.00 1,500.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
133 Excavation for laying 1/2" to 3" diameter PVC pipes in ground not less than
1'-6" deep, back filling & compacting.
Labour
2 1/4 days U / Sk labourer 1,500.00 3,375.00
134 Chasing brickwork for laying 1/2" to 1 1/2" dia PVC pipes and making good
average depth 2". ( Pipes and specials paid separately )
Materials
0.1 cwt cement ( 50 Kg bags ) 970.00 97.00
0.01 cubes sand 15,000.00 150.00
Labour
3 days mason 2,000.00 6,000.00
3 days U / Sk labourer 1,500.00 4,500.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
135 Chasing brickwork for laying 1 1/2" to 3" dia PVC pipes and making good
average depth 3". ( Pipes and specials paid separately )
Materials
0.2 cwt cement ( 50 Kg bags ) 970.00 194.00
0.03 cubes sand 15,000.00 450.00
Labour
3 1/2 days mason 2,000.00 7,000.00
3 1/2 days U / Sk labourer 1,500.00 5,250.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per 10 specials
Materials
10 No. 1/2" elbows / bends / sockets - -
20 grms. solvent cement - -
Labour
2 hrs. plumber - -
Per 10 specials
Materials
10 No. 3/4" elbows / bends / sockets - -
30 grms. solvent cement - -
Labour
2 hrs. plumber - -
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per 10 specials
Materials
10 No. 1" elbows / bends / sockets - -
40 grms. solvent cement - -
Labour
2 hrs. plumber - -
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per 10 specials
Materials
10 No. 1 1/4" elbows / bends / sockets - -
60 grms. solvent cement - -
Labour
2 hrs. plumber - -
Per 10 specials
Materials
10 No. 1 1/2" elbows / bends / sockets - -
80 grms. solvent cement - -
Labour
1/2 days plumber - -
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per 10 specials
Materials
10 Nos. 2" elbows / bends / sockets - -
100 grms. solvent cement - -
Labour
1/2 day plumber - -
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per 10 specials
Materials
10 Nos. 2 1/2" elbows / bends / sockets - -
200 grms. solvent cement - -
Labour
1/2 day plumber - -
Per 10 specials
Materials
10 Nos. 3" elbows / bends / sockets - -
240 grms. solvent cement - -
Labour
1/2 day plumber - -
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per 10 Tees
Materials
10 Nos. 1/2" dia Tees - -
30 grms. solvent cement - -
Labour
1/2 day plumber - -
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per 10 Tees
Materials
10 Nos. 3/4" dia Tees - -
45 grms. solvent cement - -
Labour
1/2 day plumber - -
Per 10 Tees
Materials
10 Nos. 1" dia Tees - -
60 grms. solvent cement - -
Labour
1/2 day plumber - -
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per 10 Tees
Materials
10 Nos. 1 3/4" dia Tees - -
90 grms. solvent cement - -
Labour
1/2 day plumber - -
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per 10 Tees
Materials
10 Nos. 1 1/2" dia Tees - -
120 grms. solvent cement - -
Labour
1 day plumber - -
Per 10 Tees
Materials
10 Nos. 2" dia Tees - -
210 grms. solvent cement - -
Labour
1 day plumber - -
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per 10 Tees
Materials
10 Nos. 2 1/2" dia Tees - -
300 grms. solvent cement - -
Labour
1 day plumber - -
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Per 10 Tees
Materials
10 Nos. 3" dia Tees - -
360 grms. solvent cement - -
Labour
1 1/2 days plumber - -
152 4" dia glazed earthenware pipes laid on 6" thick bedding in cement concrete
1:3:6(1 1/2") including excavation average 2'-0" depth, backfilling with
selected excavated materials and concrete haunching to joints.
Materials
50 Nos 4" dia EW pipes - -
0.75 cubes cement concrete 1:3:6 (1 1/2" ) 38,875.00 29,156.25
2 lbs yarn - -
0.5 cwt cement ( jointing ) 970.00 485.00
4 cubes excavation 3,375.00 13,500.00
Labour
Laying concrete bedding -
1 1/2 days U / Sk labourer 1,500.00 2,250.00
Backfilling -
2 1/2 days U / Sk labourer 1,500.00 3,750.00
PLUMBING (C I PIPES)
153 4' dia C.I. Soil/vent pipe fixed vertically to walls jointed with cement caulking.
(Specials measured separately )
Materials
6 L.ft 4' dia C.I. Pipe - -
Add 10% for wastage -
5/16 lbs yarn - -
1 No timber plug 6" x 6" x 2" - -
2 Nos 3" iron screws - -
2 lbs cement 970.00 17.64
Labour
1/4 days plumber - -
1/4 days U / Sk labourer 1,500.00 375.00
Add 5% Scaffolding 18.75
---------------------------------------------------------------------------------------------------------------------------------------------------------------
154 4' dia C.I. pipes fixed to walls jointed with lead caulking. (Specials measured separately)
Materials
6 L.ft 4" dia C.I. Pipe - -
Add 10% for wastage -
5/16 lbs yarn - -
1 No wood plug 6" x 6" x 2" - -
2 Nos 3" iron screws - -
6 lbs lead - -
1/16 cwt firewood - -
Labour
1/4 day plumber - -
1/4 day U / Sk labourer 1,500.00 375.00
Add 10% for sundries in cement and sand 37.50
Add 5% for Scaffolding 18.75
155 4" dia stoneware gulley with 6" x 6" x 6" gulley box including excavation, 4" thick
cement concrete 1:2:4(3/4") base, surrounded by 4 1/2" thick brickwork in cement
and sand 1:5 extended 6" above top of gulley box including making connection,
1/2" cement and sand 1:2 rendering internally and exposed faces finished smooth
with neat cement floating and providing G.I. grating on top of gulley.
Per No.
Materials
1 No 4" S.W. gulley - -
4 cu.ft excavation 3,375.00 135.00
5.5 sq.ft 4 1/2" brickwork 17,241.00 948.26
0.8 cu.ft cement concrete 1:2:4(3/4") 45,190.00 361.52
1 sq.ft 1/2" cement rendering 1:2 7,080.00 70.80
1 No 4" G.I. grating - -
Labour
1/2 day mason 2,000.00 1,000.00
1/2 day U / Sk labourer 1,500.00 750.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
156 Manhole 2'-0"x2'-0" internally with invert depth not exceeding 2'-0" including excavation,
backfilling 6" cement concrete 1:2:4 ( 3/4" ) base with 3/8" dia. mild steel rods at
4" centres bothways, forming channels and benching in similar concrete, 4 1/2" walls
in brick in cement 1:5, 1/2" thick cement and sand 1:2 rendering internally and exposed
surfaces including channels, benching and 2" thick RCC removable cover slab
2'-3"x2'-3" inlet and outlet connection al complete to working order
Per No.
Materials
35 cu.ft excavation 3,375.00 1,181.25
7 cu.ft cement concrete 1:2:4( 3/4' ) in
base & channels 45,190.00 3,163.30
33 sq.ft 4 1/2" brickwork in cement 1 : 5 17,241.00 5,689.53
28 sq.ft 1/2" cement rendering 1 : 2 7,080.00 1,982.40
1 No RCC cover slab - -
Labour
1 1/2 days mason 2,000.00 3,000.00
2 1/2 days U / Sk labourer 1,500.00 3,750.00
SANITARY FITTINGS.
157 22"x16" glazed fireclay wash basin with 1/2" dia Chromium plated pillar tap,
waste plug, Chromium plated waste chain and stay, including fixing wash basin
on brackets. ( water supply and waste water connection measured separately ).
Per No.
Materials
1 No wash basin complete with brackets. - -
1 No 1/2" tap with waste plug and chain - -
4 Nos wooden plugs - -
6 Nos 1 1/2" brass screws - -
2 lbs cement 970.00 17.64
Labour
1/2 day mason 2,000.00 1,000.00
1 day U / Sk labourer 1,500.00 1,500.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
158 Sink 24"x15"x7" overall vitreous China with rubber plug and Chromium plated chain
waste carried on iron brackets painted and fixed to walls. ( Water supply and waste
water connection measured separately ).
Per No.
Materials
1 No sink 24" x 15" x 7" - -
2 Nos L iron bracktes - -
2 lbs cement 970.00 17.64
2 Nos tapered wooden blocks 2" thick - -
8 Nos 1 1/2" brass screws - -
Labour
1/2 day mason 2,000.00 1,000.00
1/2 day U / Sk labourer 1,500.00 750.00
159 Closet pedestal type with L / L flushing cistern, flush pipe double plastic seat cover,
1/2" dia stop cock , trap supplied & fixed complete to working order.
Per No.
Materials
1 No. low level suite complete - -
1 No. 1/2" dia stop cock - -
2 lbs cement 970.00 17.64
1/4 cu.ft sand 15,000.00 37.50
2 Nos. 1 1/2" brass screws - -
Labour
1/4 day mason 2,000.00 500.00
1 day plumber - -
1 day U / Sk albourer 1,500.00 1,500.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
160 Closet squatting type with trap including high level cistern fixed complete with flush pipe
and 1/2" dia stop cock, all complete to working order.
Per No.
Materials
1 No. squatting pan with trap - -
1 No. 2 gallons C.I. Cistern with 1 1/4" flush
pipe chain and overflow pipe - -
1 No. clip - -
5 No. wooden plugs - -
1 doz. 1 1/2" brass screws - -
1 No. 1/2" stop cock - -
1/4 cwt cement 970.00 2.20
1/2 cu.ft 1" metal - -
1/4 cu.ft sand 15,000.00 37.50
Labour
1/2 day mason 2,000.00 1,000.00
1 day plumber - -
1 day U / Sk labourer 1,500.00 1,500.00
Per No.
Materials
1 No. bidet - -
Labour
1 day plumber - -
1 day U / Sk labourer 1,500.00 1,500.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
162 4 No. Bowl type urinal with trap and 2 glas capacity automatic flushing cistern and
spreaders complete to working prders.
Per No.
Materials
4 Nos. Urinals Bowls - -
1 No. 2 gallons cistern - -
8 Nos. rowl plugs - -
1 No. spreader - -
1 No. wooden plugs ( for cistern ) - -
4 Nos. 1 1/2" brass screws - -
4 lbs cement 970.00 35.27
1/8 cu.ft sand 15,000.00 18.75
Labour
1/4 day mason 2,000.00 500.00
1 day plumber - -
1 day U / Sk labourer 1,500.00 1,500.00
163 6" dia half round PVC eaves gutter fixed to timber valance board including gutter joiner
and brackets fixed at 18" centres. ( Other specials paid separately ).
Consider 24 L.ft
Materials
2 Nos. 6" dia eaves gutter lengths 809.00 1,618.00
1 No. joiner 101.00 101.00
17 Nos. gutter brackets 44.00 748.00
34 Nos. 3/4" brass screws 3.00 102.00
20 grms solvent cement - -
Labour
1/2 days plumber - -
1/2 days U / Sk labourer 1,500.00 750.00
Add 5% Scaffolding 37.50
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Materials
1 No PVC gutter head - -
2 Nos gutter joiners - -
2 Nos gutter brackets - -
12 grms solvent cement - -
4 Nos 3/4" brass screws - -
Labour
1/8 day plumber - -
1/8 day U / Sk labourer 1,500.00 187.50
Add 5% Scaffolding 9.38
Materials
1 No PVC mitre - -
2 Nos gutter joiners - -
2 Nos brackets - -
12 grms solvent cement - -
4 Nos 3/4" brass screws - -
Labour
1/8 day plumber - -
1/8 day U / Sk labourer 1,500.00 187.50
Add 5% Scaffolding 9.38
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Materials
1 No. end cap - -
12 grms solvent cement - -
Labour
1/16 day plumber - -
1/16 day U / Sk labourer 1,500.00 93.75
Add 5% Scaffolding 4.69
167 3 1/2" dia PVC rain water down pipes fixed to brick wall with wooden plugs buried
in wall. ( Specials measured separately )
Materials
2 Nos. 3 1/2' dia pipe lengths - -
1 No. 3 1/2" joiner - -
4 Nos. PVC straps - -
8 Nos. brass screws 1" long - -
30 grms solvent cement - -
Labour
1/3 days plumber - -
1/3 day U / Sk labourer 1,500.00 500.00
Add 5% Scaffolding 25.00
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Materials
1 No 60 deg. - 80 deg. Elbow - -
32 grms solvent cement - -
Labour
1/16 day plumber - -
1/16 day U / Sk labourer 1,500.00 93.75
Add 5% Scaffolding 4.69
Cost per No. 98.44
---------------------------------------------------------------------------------------------------------------------------------------------------------------
Materials
1 No 60 deg. - 80 deg. Shoe - -
15 grms solvent cement - -
Labour
1/16 day plumber - -
1/16 day U / Sk labourer 1,500.00 93.75
Add 5% Scaffolding 4.69
Cost per No. 98.44
EXCAVATION
1 Removing top soil to a depth not exceeding 6" & depositing as directed within site. 1,800.00 square
2 Excavation over site to reduce level, in any material except rock requiring blasting
includingdepositing and levelling as directed up to a distance not exceeding 30'- 0" 2,925.00 cube
3 Excavation in trenches for walls / column pits in soft / loose soil up to 5'-0" deep and
depositing excavated material to a distance not exceeding 30'-0" (Earth work support
to be paid separately where necessary). 1,800.00 cube
4 Excavation in trenches for walls / column pits in ordinary soil up to 5'-0" deep
and depositing excavated material to a distance not exceeding 30'-0". 4,050.00 cube
5 Excavation in trenches for walls / column pits in Hard / dense soil up to a depth
of 5'-0" and depositing excavated material up to a distance not exceeding 30'-0" 6,300.00 cube
6 Excavation in trenches for walls / column pits in Mud / wet soil up to a depth
of 5'-0" and depositing excavated material to a distance not exceeding 30'-0". 5,400.00 cube
8 Excavation in trenches for wall / column pits in Hard rock requiring blasting up to a
depth of 5'-0' and depositing excavated material to a distance not exceeding 30'-0". 6,000.00 cube
10 Anti - termite treatment on excavated foundation and compacted soil under floors. 1,500.00 square
13 Filling under floors including levelling, watering & compacting in 3" layers with
available and selected earth at site. 3,600.00 cube
14 Filling under floors including levelling, watering & compacting in 3" layers
with imported selected earth. 8,568.00 cube
15 Cutting turf sods, loading to hand carts and transporting upto 30 yards, laying
and watering for 30 days. (Royalty for turf, pegging and transport 9,900.00 cube
beyond 30 yards paid separately )
18 Earthwork support (close planking) in deep excavation in trenches up to 15'-0" depth. 8,000.00 square
24 2" thick cement concrete 1:3:6(1 1/2") screed in foundation at depths 9,752.50 square
not exceeding 5'-0".
25 3" thick cement concrete 1:3:6(1 1/2") screed in foundation at depths 14,478.75 square
not exceeding 5'-0".
26 6" thick cement concrete floor in ( mass concrete )1:3:6(1 1/2") 33,941.25 square
27 Cement concrete 1:2:4(3/4") in 4 1/2" x 6" columns in ground floor. 105,650.80 cube
28 Cement concrete 1:2:4(3/4") in 6" x 6" columns in ground floor. 71,597.47 cube
29 Cement concrete 1:2:4(3/4") in 9" x 9" columns in ground floor. 98,984.13 cube
30 Cement concrete 1:2:4(3/4") in 12" x 12" columns in ground floor. 95,939.40 cube
31 Cement concrete 1:2:4(3/4") in 13 1/2" x 13 1/2" columns in ground floor. 95,174.69 cube
32 Cement concrete 1:2:4(3/4") in 6" x 6" beam up to 1st floor level. 109,606.07 cube
33 Cement concrete 1:2:4(3/4") in 9" x 6" beam up to 1st floor level. 110,317.47 cube
34 Cement concrete 1:2:4(3/4") in 9" x 9" beam up to 1st floor level. 108,317.47 cube
37 Cement concrete 1:2:4(3/4") in 4 1/2" x 6" lintels in ground floor 106,317.47 cube
38 Cement concrete 1:2:4(3/4") in 9" x 9" lintels in ground floor 106,317.47 cube
39 Cement concrete 1:2:4(3/4") in 9" x 12" lintels in ground floor 106,317.47 cube
40 Cement concrete 1:2:4(3/4") in 12" x 15" lintels in ground floor 106,317.47 cube
TIMBER FORMWORK
41 Sawn timber formwork to 9" x 9" cement concrete column in ground floor. 7,800.00 square
42 Sawn timber formwork for concrete beams in ground floor. 15,120.00 square
43 Sawn timber formwork for underside of first floor slab. 6,402.00 square
REINFORCEMENTS
44 Mild steel / Tor steel reinforcement to lintels, slabs, beams or columns bent
to shape laid in position and tied with G . I . wire as directed. 5,838.48 cwt
BRICKWORK
45 Brick work in cement & sand 1:5 in foundation up to D. P. C. level. 49,980.00 cube
46 Brick work in cement & sand 1:8 in foundation up to D. P. C. level. 50,290.00 cube
47 Brick work in cement and sand 1:5 in 4 1/2" thick walls in ground floor 20,689.20 square
48 9" thick brick wall in cement & sand 1:5 in ground floor 39,537.30 square
49 Brickwork 13 1/2" thick in cement & sand 1:5 in superstructure in ground floor 59,049.60 square
50 9" thick brick wall in cement & sand 1:5 in superstructure in ground floor 38,491.80 square
51 4 1/2" thick brick wall ( wire cut ) in cement & sand 1:5 in ground floor 19,375.20 square
52 9" thick brick in cement & sand 1:5 with wire cut bricks
( Facing to brickwork measured separately ) 37,838.58 square
53 13 1/2" thick brick wall ( wire cut ) in cement & sand 1:5 in ground floor
( Facing to brickwork measured separately ) 58,357.44 square
54 Extra over for facing including raised pointing 1 / 8" thick in cement and sand 1:1
mixture in ground floor ( Facing to brickwork measured separately ) 19,362.00 square
55 3" thick brick paved floor in lime sand mortar 2 : 5 in ground floor 17,266.80 square
56 Steps 1'-11/2" x 0'-6" in brick in cement and sand 1:5 with 1/2" thick cement
and sand 1:2 rendering including necessary excavation. 576.00 L.ft
57 Brick drains in cement and sand 1 : 5, 9" wide and 6" - 9" average depth including
cement rendering1/2" thick 1:2 to exposed faces with 1'-6" ramp including 969.72 L.ft
necessary excavation
58 Brick drains in cement and sand 1 : 5, 9" wide and 6" - 9" average depth including
cement rendering 1/2" thick 1:2 to exposed faces without ramp including 821.88 L.ft
necessary excavation.
BLOCK WORK
59 8" thick Hollow blockwork in cement and sand mortar 1 : 5 in ground floor 10,296.00 square
(cavities unfilled)
60 4" thick Hollow block masonry in cement and sand mortar 1:5 with cavity unfilled. 12,244.80 square
TILE WORKS
63 Pressed floor tiles bedded in 1/2" cement mortar 1 : 2 and pointing in neat cement in
ground floor. 22,815.00 square
65 Terrazzo floor tiles on 1/2" thick cement and sand 1 : 2 in ground floor 21,015.00 square
ROOF WORK
66 Timber framework for calicut pattern tile hip roof in single storey building consisting
of wall plate,beam,ridge plate,rafters etc.( Preservative treatment to be 2,600.00 square
measured separately )
67 Roof covering with calicut pattern clay tiles in single storeyed building
(Timber frame work & ridge covering measured separately) 900.00 square
68 Timber framework for corrugated asbestos sheet roof in single storeyed building. 1,500.00 square
69 Roof covering with corrugated asbestos sheets ( Timber frame work & ridge covering
measured separately ) 1,000.00 square
70 One layer half round clay tiles over corrugated asbestos roof covering 3,600.00 square
71 Asbestos close fittings ridging fixed complete with roofing screws or bols ( hook ) 33.76 L.ft
72 Ridging covering with calicut pattren ridge tiles bedded in cement lime mortar 1 : 1 : 4 149.83 L.ft
73 3/4" x 9" high valance board fixed with brass screws to ends of rafters (for tile roofing) 141.75 L.ft
74 3/4"x 9" high valance board fixed with brass screws at 2'-0" centres to sides of rafters. 141.75 L.ft
ROOF PLUMBING
75 18 B.W.G.( 1.2 mm ) galvanised iron sheet valley gutter 3'-0" girth overall
once bent with end laps not less than 9" width including 3/4" tongued and grooved
planks laid to slope and profile on timber and profile on members. 315.76 L.ft
76 18 B.W.G. ( 1.2 mm ) galvanised iron flashing 1'-6" girth overall 3 times bent with
end laps notless than 6", lead soldered, turned and tucked up to not less than 6"
in to chase cut in wall and pointed in cement morter 1:2 lower end dressed over
roof covering not less than 1'-0" wide. 225.88 L.ft
CEILING WORK
77 Timber framework for 4'-0" x 4'-0" flat asbestos ceiling ( sheet measured separately ),
comprising of 4" x 2" joists and 2" x 2" bearers in class I timber. 2,481.82 square
78 Horizontal ceiling lining using 4' 0" x 4' 0" flat asbestos cement sheet fixed withand
including beading and cove mouldings on timber framework.(Timber framework and
painting measured separately) 1,938.46 square
79 3/4" thick tongued and grooved Lunumidella ceiling boards fixed horizontal on 4" x 2"
class I timber Joists at 2'-0" centres with 1 1/2" brass nails. 12,788.59 square
80 3/4" x 6" wide tongued and grooved Lunumidella ceiling boards fixed to underside of
roof rafters, (existing) with 1 1/2" brass nails including levelling with timber sterips
where necessary. 6,313.33 square
82 Door glazed and panelled double hung 4'-0" x 7'-0" high overall with frame including
1 1/4" thick sash and 3 3/4" x 2 3/4" frame (Glazing, ironmongery and painting
measured separately) 155.57 sq.ft
83 Plywoood door single hung 3'-1 1/2" x 6'-11 1/2" overall with frame having 1 1/4" thick
sash and 3 1/4" x 2 1/4" frame . ( Iron-mongery and painting measrued separately ). 79.31 sq.ft
84 Door ledged, braced and battened single hung 2'-6" x 6'-6" overall, with frame having
7/8" thick tongued & grooved planks and 3 3/4" x 2 3/4" frame.
(Ironmongery & painting measured separately) 314.95 sq.ft
85 Window, glazed 7'-0" x 4'-0" high overall with frame comprising 3 No.
openable sashes and 3 3/4" x 2 3/4" frame and mullions. 235.71 sq.ft
86 1/6" clear sheet glass panes exceeding 1 but not exceeding 4 square feet
cut and fixed with timber beadings to doors and windows. 100.00 sq.ft
IRONMONGARY
PLASTERWORKS.
98 3/4" thick DPC, in cement sand 1:2 finished with 2 coats hot tar and blinded with sand. 12,399.00 square
99 3/4" thick plastering to wall in lime and sand 2 : 5 including floating with lime putty. 7,276.50 square
100 5/8" thick plastering to wall in lime and sand 2 : 5 including floating with lime putty. 8,262.60 square
101 3/8" thick plastering to soffit of slab in cement and sand 1 : 3 including floating with
lime putty. 12,436.20 square
102 3/8" thick plastering to sides and soffit of beams in cement and sand 1 : 3 including
floating with lime putty. 10,273.20 square
103 5/8" thick plastering to wall in lime, cement and sand 1 : 1 : 5 finished semi rough
with wooden floating. 7,280.70 square
104 5/8" thick plastering to wall in lime, cement and sand 1 : 1 : 5 finished
smooth with lime putty floating. 7,280.70 square
105 1/2" thick rendering in cement and sand 1 : 3 finished smooth. 7,995.48 square
106 1/2" thick rendering in cement and sand 1 : 2 in floors, finished smooth. 8,496.00 square
107 3/4" thick rendering in cement and sand 1 : 3 finished smooth. 10,827.00 square
108 3/4" thick rendering in cement and sand 1 : 2 in floors finished smooth. 11,409.00 square
109 3/4" thick rendering in cement sand 1 : 2 in coloured cement floors finished smooth. 10,719.00 square
110 1/2" x 6" skirting in cement and sand 1:3 projected or flush to walls finished with
floating including forming groove. 164.04 L.ft
111 Prepare and apply one coat of preservative (oil type) to structural timber including
touching up cut ends etc. after fixing. 900.00 square
112 Prepare surface of steel truss and apply two coats of anticorrosive primer. 2,700.00 square
113 Apply one coat of anti-corrosive primer and two coats enamel paint on
already shop primed and erected steel roof truss. 1,854.00 square
114 Perpare and apply two coats primer and finishing coat of enamel
paint to mild steel ( angle/flat ) gate 2,700.00 square
115 Painting steel on new work with 2 coats of anti - corrosive paint - square
116 Painting new timber work with 2 coats wood preservative 202.80 square
117 Preparing and painting wood work with primer and 2 coats enamel paint 900.00 square
118 White or colour washing two coats in single storeyed building. 493.50 square
120 Prepare and apply one coat of Alkali resistant primer and two
coats of emulsion paint to walls. 30.00 square
121 Cement washing to walls of single storeyed building 2 coats. 458.55 square
123 Prepare and apply one coat alkali resistant primer and two coats of emulsion
paint to soffit of slabs. - square
124 Varnishing two coats with copal varnish after sand papering 900.00 square
126 1/2" diameter PVC pipes fixed to walls ( specials paid separately ) 22.50 L.ft
127 3/4" diameter PVC pipes to walls ( specials paid separately ) 22.50 L.ft
128 1" diameter PVC pipes fixed to walls ( specials paid separately ) 9.00 L.ft
129 1 1/4" diameter PVC pipes fixed to walls ( specials paid separately ) 13.50 L.ft
130 1 1/2" diameter PVC pipes laid to walls ( specials paid separately ) 13.50 L.ft
131 2" diameter PVC pipes laid to walls ( specials paid separately ) 13.50 L.ft
132 3" diameter PVC pipes laid to walls ( specials paid separately ) 18.00 L.ft
133 Excavation for laying 1/2" to 3" diameter PVC pipes in ground not less than
1'-6" deep back filling & compacting. 40.50 L.ft
134 Chasing brickwork for laying 1/2" to 1 1/2" dia PVC pipes and making good
average depth 2". ( Pipes and specials paid separately ) 128.96 L.ft
135 Chasing brickwork for laying 1 1/2" to 3" dia PVC pipes and making good
a verage depth 3". ( Pipes and specials paid separately ) 154.73 L.ft
PLUMBING (C I PIPES)
153 4" dia C.I. Soil/vent pipe fixed vertically to walls jointed with cement caulking.
(Specials measured separately ) 82.28 L.ft
154 4" dia C.I. pipes fixed to walls jointed with lead caulking. 86.25 L.ft
(Specials measured separately)
155 4" dia stoneware gulley with 6" x 6" x 6" gulley box including excavation, 4" thick
cement concrete 1:2:4(3/4") base, surrounded by 4 1/2" thick brickwork in cement
and sand 1:5 extended 6" above top of gulley box including making connection,
1/2" cement and sand 1:2 rendering internally and exposed faces finished smooth
with neat cement floating and providing G.I. grating on top of gulley. 3,918.69 No
156 Manhole 2'-0"x2'-0" internally with invert depth not exceeding 2'-0" including
excavation, backfilling, 6" cement concrete 1:2:4 ( 3/4" ) base with 3/8" dia. mild
steel removable cover slab rods at 4" centres bothways, forming channels and
benching in similar concrete, 4 1/2" walls in brick in cement 1:5, 1/2" thick cement
and sand 1:2 rendering internally and exposed surfaces including channels,
benching and 2" thick RCC removable cover slab 2'-3"x2'-3" inlet and outlet 22,519.78 No
connection all complete to working order
SANITARY FITTINGS.
157 22"x16" glazed fireclay wash basin with 1/2" dia Chromium plated pillar tap,
waste plug, Chromium plated waste chain and stay, including fixing wash basin
on brackets. ( water supply and waste water connection measured separately ). 3,021.16 No
158 Sink 24"x15"x7" overall vitreous China with rubber plug and Chromium plated chain
waste carried on iron brackets painted and fixed to walls. ( Water supply and waste
water connection measured separately ). 2,121.16 No
159 Closet pedestal type with L / L flushing cistern, flush pipe double plastic seat cover,
1/2" dia stop cock , trap supplied & fixed complete to working order. 2,466.16 No
160 Closet squatting type with trap including high level cistern fixed complete with flush
pipe and 1/2" dia stop cock, all complete to working order. 3,047.65 No
161 Vitreous China bidet suite fixed complete to working order 1,800.00 No
162 4 No. Bowl type urinal with trap and 2 glas capacity automatic flushing cistern and
spreaders complete to working prders. 616.21 No
163 6" dia half round PVC eaves gutter fixed to timber valance board including gutter
joiner and brackets fixed at 18" centres. ( Other specials paid separately ). 44.48 L.ft