Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
HUESKER SRL
Piazza della Libert 3 - Trieste Libert www.huesker.com tel. 040/363605
Alberto Simini Trieste 9 Aprile 2008 fax. 040/3481343 1
SOMMARIO:
1) Classificazione e propriet 2) Funzioni 3) Campi dapplicazione 4) Applicazioni
Alberto Simini
Alberto Simini
SOMMARIO:
1) Classificazione e propriet 2) Funzioni 3) Campi dapplicazione 4) Applicazioni
Alberto Simini
Alberto Simini
CLASSIFICAZIONE E TIPOLOGIE
PRINCIPALI FAMIGLIE DI PRODOTTI (SIGLA)
GEOSINTETICI
GEOTESSILI GEOGRIGLIE GEORETI GEOSPAZIATORI GEOCELLE GEOMEMBRANE GEOSTUOIE GEOCOMPOSITI
Alberto Simini
BIOPRODOTTI
(GTX) (GGR) (GNE) (GSP) (GCE) (GMB) (GMA) (GCO)
Trieste 9 Aprile 2008
Alberto Simini
+/-
++
++
+/-
+/-
++
++
- - bassa temperatura < -5 Resistenza UV Creep Resistenza per unit di peso Resilienza Infiammabilit Temperatura di fusione C Temperatura trans. Vetrosa C Densit kg/m3
Alberto Simini
Assorbimento umidit
10
Alberto Simini
11
Creep
Allungamento sotto carico costante (60% Frott) nel tempo di alcuni polimeri
Alberto Simini Trieste 9 Aprile 2008 12
SOMMARIO:
1) Classificazione e propriet 2) Funzioni 3) Campi dapplicazione 4) Applicazioni
Alberto Simini
13
rinforzo
protezione
contenimento
Alberto Simini Trieste 9 Aprile 2008 Main Functions of geosynthetics 14
Funzioni meccaniche
filtrazione
drenaggio
impermeabilizzazione
In molti casi abbiamo funzioni combinate: Una o due decisive, altre secondarie (meno importanti)
Alberto Simini
Rinforzo & separazione, separazione & filtrazione, Trieste 9 Aprile contenimento & rinforzo etc.2008
SOMMARIO:
1) Classificazione e propriet 2) Funzioni 3) Campi dapplicazione 4) Applicazioni
Alberto Simini
17
APPLICAZIONI
TERRE RINFORZATE TRATTENIMENTO TERRENO SU SUPERFICI LISCIE
RILEVATI SU PALI IMPERMEABILIZZAZIONE (discariche, bacini) ATTRAVERSAMENTO DI CAVIT BONIFICA AREE INQUINATE
PROTEZIONE
Discariche
Argini, stabilizzazione pendii
Idraulica
Argini
Edilizia
Muri di sostegno
Geotecnica
stabilizzazione pendii, rilevati, muri di sostegno,
Rinforzo di base di rilevati Rinforzo antipunzonamento su pali Attraversamento di cavit Rinforzo dei sottofondi stradali e ferroviari Rinforzo dei conglomerati bituminosi Pali portanti con geotessili tubolari
Impermeabilizzazione
Rilevati
Rilevati
Rilevati, dighe
Rilevati Strade pavimentate e non pavimentate Strade fessurate, allargamenti, scavi in trincea Rilevati Gallerie Fondo e copertura Strade pavimentate e non pavimentate Strade fessurate, allargamenti, scavi in trincea Strade pavimentate e non pavimentate Strade fessurate, allargamenti, scavi in trincea Dighe Dighe, bacini, argini Strati drenanti, sottofondi, scogliere Dighe, stabilizzazione argini Sponde, argini, coste, fondali, pile Membrane dighe, bacini Muri interrati, terrazzi, tetti Sottofondi, vespai drenanti Muri interrati, giardini pensili Strade pavimentate e non pav. Strade fess., allargamenti, scavi in trincea
Rilevati
Sottofondi, vespai drenanti Drenaggi laterali alla strada, dreni verticali a nastro, muri di sostegno, gallerie Scarpate e fossi di guardia Gallerie
Strati drenanti, sottofondi Strati di monitoraggio, drenaggio del percolato e biogas Scarpate della copertura Membrane fondo e copertura
Controllo dellerosione
Scarpate
Alberto Simini
Protezione Membrane
19
Membrane muri e solai
Alberto Simini
20
10
RINFORZO DI BASE
Alberto Simini
21
RINFORZO SU PALI
RINFORZO SU CAVIT
Alberto Simini
22
11
Alberto Simini
23
I GEOSINTETICI DI RINFORZO SONO VERE E PROPRIE ARMATURE E AVENDO, QUINDI, UNA FUNZIONE STRUTTURALE, LA FUNZIONALIT E SICUREZZA DELLE OPERE LEGATA ALLE LORO PRESTAZIONI.
Alberto Simini
24
12
Scatola di Casagrande
Alberto Simini
25
Scatola di Casagrande
compressione
trazione
T = N tan '
Alberto Simini Trieste 9 Aprile 2008 26
13
Scatola di Casagrande
T
rinforzo
T:Incremento della resistenza al taglio del terreno per effetto del rinforzo
T
P Ph Pv
Un geosintetico di rinforzo aumenta la resistenza al taglio del terreno lungo la superficie di rottura grazie a due effetti benefici: 1) Oppone resistenza alla sollecitazione di taglio agente 2) Aumenta la resistenza al taglio poich incrementa la tensione normale sulla superficie di scorrimento Trieste 9 Aprile 2008 27 Alberto Simini
T dj T dj+1 T dn-1 T dn
la tensione a cui il geosintetico di rinforzo dovr resistere alla fine della vita utile di progetto prevista.
Alberto Simini
28
14
FORMULE PER IL CALCOLO DELLA TENSIONE DI PROGETTO A LUNGO TERMINE (LTDS) BS 8006 (UK)
Tdes =
Fd =
Fcreep Tk ult . fm fd fe
EBGEO (DE)
Fk A1 A2 A3 A4 B
Pr NF G 38064 (FR)
Tadm =
Tal =
RFCR
29
PROVA DI TRAZIONE SUI GEOSINTETICI (ISO 10.319) DIAGRAMMA TENSIONE-DEFORMAZIONE A BREVE TERMINE
Tdes =
100 90 80 70 60 50 40 30 20 10
Fcreep Tk ult fm fd fe
GGR "B"
GGR "A"
GGR "C"
GGR "D"
Alberto Simini
9 10 11 12 13
30
allungamento %
15
40 35 30 25 20 15 10 5 0
Alberto Simini
Deformazione (%)
114 anni
P P
creep
HPDE (36%)
Tdes =
PET (63.5%) PVA (62.1%)
Fcreep Tk ult fm f d fe
12
31
Tdes =
Esempio:
Fcreep Tk ult fm fd fe
Durata delle prove di creep: 10.000 ore (ca.1,14 anni) Vita utile dellopera: 1.000.000 ore
Cicli logaritmici di estrapolazione
f m122 = log10 (t d / tt )
td = vita utile di progetto del geosintetico tt = Alberto delle prove di creep durata Simini
fm122 = 2
fm12 = fm121 x fm122 )
( fm = fm11 x fm12
Trieste 9 Aprile 2008
16
Tdes =
Fcreep Tk ult fm fd fe
Variazioni di fd per tipo di geogriglia 1,0 1,20 1,05 1,45 1,05 > 1,50
E consentito adottare il fattore di riduzione di una geogriglia di minore resistenza per una geogriglia di maggiore resistenza appartenente alla stessa famiglia Trieste 9 Aprile 2008 Alberto Simini
33
Tdes =
Materia prima geogriglia HDPE - PVA PET HDPE - PVA PET HDPE - PVA PET HDPE - PVA HDPE - PVA
Fcreep Tk ult fm fd fe
Variazioni di fe per tipo di geogriglia 1,0 1,05 1,15 1,20 1,0 1,0 1,05 1,0 1,10 1,20 1,0 1,0 1,20
34
17
SOMMARIO:
1) Classificazione e propriet 2) Funzioni 3) Campi dapplicazione 4) Applicazioni
Alberto Simini
35
Terre rinforzate
Alberto Simini
36
18
Alberto Simini
37
a mensola
Resistono anche grazie al peso del terreno che insiste sulla base
Alberto Simini Trieste 9 Aprile 2008 38
19
a) In pietrame
b) Con gabbioni
39
Sono delle strutture realizzate con terreno che hanno una pendenza del fronte che supera langolo di naturale declivio del terreno stesso Inserendo dei geosintetici allinterno del rilevato si riescono ad ottenere pendenze fino a 90.
Rilevato classico
Alberto Simini
40
20
Alberto Simini
42
21
Alberto Simini
43
Alberto Simini
44
22
Alberto Simini
45
Alberto Simini
46
23
Alberto Simini
47
Alberto Simini
48
24
Alberto Simini
49
2) OPERE A VERDE:
stuoie antierosione idrosemina
Alberto Simini
50
25
Alberto Simini
51
a) verifica al ribaltamento
Alberto Simini
52
26
ANAS VE VECCHIA S.S. 48 DELLE DOLOMITI TERMINE DI CADORE BL RISANAMENTO DI UN TRATTO DI STRADA FRANATO
Alberto Simini
53
Alberto Simini
54
27
ROCCIA
9,22
0,70
13 3 ,4
3,07
6,63
FIUME PIAVE
0,80 3,00 -7,90 2,30 -8,90 3,00 -9,65 3,00 -9,85 2,80 -10,15
Alberto Simini
55
Alberto Simini
56
28
Alberto Simini
57
Alberto Simini
58
29
Alberto Simini
59
Alberto Simini
60
30
Project name: Casate (Veneto) Material: Execution: Quantity: Application: Fortrac 35, 55, 80, 110 HaTe 23.142 steel framework 2002 8.000 m2 geogrids replacement of failed concrete retaining wall of national road in mounatin area with a soil reinforeced retaining vegetated wall
Project main points: height 7,50 m efficiency of dainage system of sliding slope fast execution of the work environmental condition in surrounding area
Alberto Simini Trieste 9 Aprile 2008 61
Alberto Simini
62
31
30
Casate (BL)
Soil
30.00 32.00
pw 0.00 0.00
25
1.70
20
15.00 3.49
1.80
1.9 0
1.31
S.S. 346 - Casate (BL) Sezione 1 100 centre-points defined. 2505 slip circles were investigated. DIN 4084 min = 1.31 x m = 0.03 m y m = 20.02 m R = 21.31 m Datei: Sezione 1 - verifica.boe 16.00 20.00
15
ps = 20.00
1.9 0
0 1.7 80 1.
10
6.14
0 1.4
1.50
1. 60
5
7.50
y= 7.20 m; L= 6 .75 m y= 6 .60 m; L= 6.75 m y= 6.00 m; L= 6 .75 m y= 5 .40 m; L= 6.75 m y= 4.80 m; L= 6 .75 m y= 4 .20 m; L= 6.75 m y= 3.60 m; L= 6 .75 m y= 3 .00 m; L= 6.75 m y= 2.40 m; L= 6.75 m y= 1.80 m; L= 6.75 m y= 1.20 m; L= 6.75 m y= 0.60 m; L= 6.75 m y= 0.00 m; L= 6.75 m
Geo s 13/ :0.80/T0:14.4/mxT:14.4 Ge os 12/:0.80 /T0:1 4.4/mxT:1 4.4 Geos 11 / :0.80/T0:14.4/mxT:14.4 Ge os 10/:0.80 /T0 :2 4.5/mxT:24 .5 Geos 9/:0.80 /T0:24.5/mxT:24.5 Ge os 8/ :0.80/T0:24.5/mxT:24.5 G eos 7/:0.80 /T0:3 2.6/mxT :3 2.6 Ge os 6/ :0.80/T0:32.6/mxT:32.6 G eos 5/:0.80 /T0:3 2.6/mxT:3 2.6 Geos 4/ :0.80/T0:54.4/mxT:54.4 G eos 3/:0.80 /T0 :5 4.4/mxT:5 4.4 Geos 2/ :0.8 0/T0:54.4/mxT:54.4 G eos 1/:0.80 /T0 :5 4.4/mxT:5 4.4
Fortrac 80/30-20
Fortrac 110/30-20
-5 -10 0 10 20 30
Alberto Simini
63
Alberto Simini
64
32
Alberto Simini
65
Alberto Simini
66
33
Alberto Simini
67
Alberto Simini
68
34
Alberto Simini
69
STEEP ARTIFICIAL REINFORCED HILLS USING RECYCLED SOIL VEGA CENTRE - MARGHERA (VENICE) - 2005 Short history: The new Vega Centre is located in Marghera, the old industrial area of Venice. Due to the former industrial chemical activities, the subsoil is considered contaminated in that areas, therefore to recycling it is very difficult and, at the same time, the discharge in the scarce available landfills is very expensive . During the construction of the Vega Centre a huge quantity of material has been produced as a result of excavations and demolition of the old buildings. To give a destination at this stock of material, the idea was to bury it in the same Vega Centre area, creating steep artificial hills reinforced with geogrids. Trieste 9 Aprile 2008 70
Alberto Simini
35
Hill 1
Footbridge
Hill 2
15 m 50 m 50 m
Alberto Simini
71
15 m
17 m
Alberto Simini Trieste 9 Aprile 2008 72
36
25
Marghera - Area "Vega" Ing. Guaraldo Pio S.p.A. 168 centre-points defined. 253 slip circles were investigated. DIN 4084 min = 1.41 xm = -0.42 m ym = 12.98 m R = 12.98 m Datei: Sezione trasversale - interna.boe
Soil
Designation Terreno di riempimento Terreno vegetale Strato 1 Strato 2 Strato 3 Strato 4 Strato 5
20
1.5
0. 3 0. 7
7.4
1.5 1.5
0. 7 0. 1 0. 3
3.7
15
0.4 0.6 0.4 0.2
1.41
Geos 25/:0.80/T 0:26.7/mxT:26.7 Geos 24/:0.80/T0:26.7/mxT:26.7 Geos 23/:0.80/T 0:26.7/mxT:26.7 23/:0.80/mxt:26.61/T0:26.7/mxT:26.7/T:0.3 Geos 22/:0.80/T0:26.7/mxT:26.7 22/:0.80/mxt:35.14/T0:26.7/mxT:26.7/T:3.3 Geos 21/:0.80/T0:26.7/mxT:26.7 21/:0.80/mxt:43.73/T0:26.7/mxT :26.7/T:10.1 Geos 20/:0.80/T0:26.7/mxT:26.7 20/:0.80/mxt:52.28/T 0:26.7/mxT:26.7/T:21.6 Geos 19/:0.80/T0:26.7/mxT :26.7 19/:0.80/mxt:60.70/T0:26.7/mxT:26.7/T:26.7 Geos 18/:0.80/T0:26.7/mxT:26.7 18/:0.80/mxt:69.12/T0:26.7/mxT:26.7/T:26.7
1.5 1.6
10
8.1
y= 9.90 m; L= 8.02 m
y= 9.301.7 8.64 m m; L=
Geos 17/:0.80/T0:40.0/mxT:40.0 17/:0.80/mxt:77.54/T0:40.0/mxT:40.0/T:40.0 Geos 16/:0.80/T0:40.0/mxT:40.0 16/:0.80/mxt:85.96/T0:40.0/mxT :40.0/T :40.0 Geos 15/:0.80/T0:40.0/mxT:40.0 15/:0.80/mxt:94.49/T0:40.0/mxT:40.0/T:40.0 Geos 14/:0.80/T 0:40.0/mxT:40.0 14/:0.80/mxt:103.03/T0:40.0/mxT:40.0/T:40.0 Geos 13/:0.80/T0:40.0/mxT:40.0 13/:0.80/mxt:111.58/T0:40.0/mxT :40.0/T:40.0 Geos 12/:0.80/T0:40.0/mxT:40.0 12/:0.80/mxt:120.12/T 0:40.0/mxT:40.0/T:40.0 Geos 11/:0.80/T0:40.0/mxT:40.0 11/:0.80/mxt:128.67/T0:40.0/mxT:40.0/T:40.0 Geos 10/:0.80/T0:40.0/mxT:40.0 10/:0.80/mxt:137.22/T0:40.0/mxT:40.0/T:40.0 Geos 9/:0.80/T0:40.0/mxT:40.0 9/:0.80/mxt:144.20/T 0:40.0/mxT:40.0/T :40.0 Geos 8/:0.80/T0:40.0/mxT:40.0 8/:0.80/mxt:151.19/T 0:40.0/mxT:40.0/T :40.0 Geos 7/:0.80/T0:40.0/mxT:40.0 7/:0.80/mxt:158.17/T 0:40.0/mxT:40.0/T :40.0 Geos 6/:0.80/T0:40.0/mxT:40.0 6/:0.80/mxt:165.29/T 0:40.0/mxT:40.0/T :40.0 Geos 5/:0.80/T 0:40.0/mxT:40.0 5/:0.80/mxt:172.50/T0:40.0/mxT:40.0/T:40.0 Geos 4/:0.80/T 0:40.0/mxT:40.0 4/:0.80/mxt:179.56/T0:40.0/mxT:40.0/T:40.0 Geos 3/:0.80/T 0:40.0/mxT:40.0 3/:0.80/mxt:186.62/T0:40.0/mxT:40.0/T:40.0 Geos 2/:0.80/T 0:40.0/mxT:40.0 2/:0.80/mxt:193.67/T0:40.0/mxT:40.0/T:40.0 Geos 1/:0.80/T 0:40.0/mxT:40.0
pv = 20.0
4.5
-5 -20
Alberto Simini
-10 0
73
1st hill
Alberto Simini
74
37
Alberto Simini
75
Alberto Simini
76
38
Alberto Simini
77
Alberto Simini
78
39
Alberto Simini
79
LANDSLIDE STABILIZATION IN LONA-LASES (TRENTO ITALY 2005) Short history: Mount Grossa versant has been interested by a heavy deep landslide movement hanging over the national road SP71 and on the Lases lake, with serious risk for near built up area. The causes of this movement can be found in three main reasons: 1) Quarry activity, 2) increasing of ground water after strong rains 3) presence of a preferential deep sliding layer of soil variable between 15 and 30 m. The design solution prescribed the morphological reconstruction of the slope through the removal of material at the top and its deposition at the toe creating steep reinforced slopes.
Alberto Simini Trieste 9 Aprile 2008 80
40
Access road
Lases lake
Alberto Simini
81
Detrital colluvial blanket High fractured porfid rock Cataclasites of porfid rocks elements with fine sand, clay particles and coarse gravel particle-size Old filling soil Excavation area Filling area Excavation and further filling area Main share plane Fault plane Sliding plane Sub-horizontal microdrains
Alberto Simini
82
41
90
13.5
10.9
3.1 3.0 3.1 3.0 3.1 3.0 3.1 2.6 3.5 3.0 3.1
5.0
2.7 3.0 2.7 3.0 2.7 3.0 2.7 3.0 2.7 3.0 2.7
9.6 Soil
6.0
80
Designation Terreno di riempimento Terreno di riporto Detrito a grossi blocchi Porfido fratturato
70
4.7
60
4.7
y= 53.54 m; L= 32.00 m y= 52.36 m; L= 32.00 m y= 50.60 m; L= 29.00 m y= 50.01 m; L= 32.00 m y= 48.83 m; L= 32.00 m y= 47.66 m; L= 32.00 m y= 45.90 m; L= 29.00 m y= 45.31 m; L= 32.00 m y= 44.13 m; L= 32.00 m y= 42.96 m; L= 32.00 m y= 41.20 m; L= 21.00 m y= 40.61 m; L= 24.00 m y= 39.43 m; L= 24.00 m y= 38.26 m; L= 24.00 m y= 36.50 m; L= 17.00 m y= 35.91 m; L= 20.00 m
4.7
50
SB4
4.7
40
4.7
4.7
5.3
30
5.3
y= 24.73 m; L= 8.00 m y= 22.97 m; L= 8.00 m y= 21.20 m; L= 5.00 m y= 20.61 m; L= 8.00 m y= 19.43 m; L= 8.00 m y= 17.67 m; L= 8.00 m y= 15.90 m L= 5.00 m ; y= 15.31 m; L= 8.00 m
SB3
Geos 18/:0.80/T0:48.5/mxT:48.5
5.3
20
Geos 17/:0.80/T0:48.5/mxT:48.5 Geos 16/:0.80/T0:48.5/mxT:48.5 Geos 15/:0.80/T0:48.5/mxT:48.5 Geos 14/:0.80/T0:48.5/mxT:48.5 Geos 13/:0.80/T0:48.5/mxT:48.5 Geos 12/:0.80/T0:48.5/mxT:48.5
5.3
y= 14.13 m; L= 8.00 m y= 12.37 m; L= 8.00 m y= 10.60 m L= 5.00 m ; y= 10.01 m; L= 8.00 m y= 8.83 m; L= 8.00 m y= 7.07 m; L= 8.00 m y= 5.30 m; L= 5.00 m y= 4.71 m; L= 8.00 m SB1 y= 3.53 m; L= 8.00 m y= 1.77 m; L= 8.00 m y= 0.00 m; L= 8.00 m
Loc. Slavinac - Lona-Lases (TN) DIN 4084 Slip bodies 4: = 1.39 With shear strength in the slice sides Datei: 050408 - Block Slip int.boe
5.3
10
Geos 9/ :0.80/T0:48.5/mxT:48.5
5.3
Geos 5/:0.80/T0:48.5/mxT:48.5 Geos 4/:0.80/T0:48.5/mxT:48.5 Geos 3/ :0.80/T0:48.5/mxT:48.5 Geos 2/:0.80/T0:48.5/mxT:48.5 2/:0.80/mxt:244.17/T0:48.5/mxT:48.5/T:48.5 Geos 1/:0.80/T0:48.5/mxT:48.5
Alberto Simini
-10 0 10 20 30 40
83
110 120
Alberto Simini
84
42
90
13. 5
10. 9
5 .0
3.0 2.7
9. 6
2 9 .4
Soil
80
Lona-Lases (TN)
20.0
70
60
4.7 4. 7 4.7
50
SB 4
5.3
5.3
30
4.7
4. 7
40
4.7
SB3
5.3
20
Fortrac 110-30/20
SB2
5. 3
10
5.3
Loc. Slav inac - Lona-Las DIN 4084 Slip bodies 4: = 1.41 Wit h shear strength in the Datei : 050412 - Block Sl ip
SB1
0 -10 0 10 20 30 40 50 60 70 80 90 100 1 10
Alberto Simini
5.3
85
Alberto Simini
86
43
15 m
35 m
Alberto Simini
87
Alberto Simini
88
44
Alberto Simini
89
Alberto Simini
90
45
Alberto Simini
91
Alberto Simini
92
46
Alberto Simini
93
Alberto Simini
94
47
Alberto Simini
95
Alberto Simini
96
48
Alberto Simini
97
Alberto Simini
98
49
Alberto Simini
99
Alberto Simini
100
50
Alberto Simini
101
Alberto Simini
102
51
Alberto Simini
103
Alberto Simini
104
52
Geotextile Reinforcement
Piles
105
Alberto Simini
106
53
Alberto Simini
107
25
Soil
20
c Designation 0.00 20.50 fembankment fill 12.00 18.50 clay 1 17.00 19.00 clay 2
Jetty of Deilam port Section E-E 1. construction step DIN 4084 m in = 1.39 xm = 7.38 m ym = 1.51 m R = 10.47 m Datei: section E-E step 1.boe
2.30 2.20
1 .8
1 .6
5
1.50
1.39
1.4 0
4.00
2.10
10
1.7 0
y= -1.50 m; L= 35.00 m
-5
-10 6.00
15.00
12.00
19.00
-15
mNN 9.0 8.0 7.0 6.0 5.0 4.0 3.0 2.0 1.0 0.0 -1.0 -2.0 -3.0 -4.0 -5.0 -6.0 -7.0 -8.0 -9.0 -10.0 -11.0 -12.0 -13.0 -14.0 -15.0
2. 00
1.9 0
w
Geos 1/:0.70 /T0 :366.0/mxT:366.0 /mxt:6 6.60/T0:366.0/mx
7.50
15.00
-20
-20
-10
10
20
30
40
50
Alberto Simini
108
54
Alberto Simini
109
Deformations Reinforced with one layer of high-strength woven: no failure Settlement about 2.8 m
Alberto Simini
110
55
Alberto Simini
111
Alberto Simini
112
56
Alberto Simini
113
Alberto Simini
114
57
Autobahn A 26 Hamburg-Stade, 2001+, Germany Stabilenka 600 & 400, 1x or 2x, H = 4 to 12 m First Autobahn on Stabilenka after approval
Alberto Simini
115
Autobahn A 26 Hamburg-Stade, 2001+, Germany Stabilenka 600 & 400, 1x or 2x, H = 4 to 12 m First Autobahn on Stabilenka after approval
Alberto Simini
116
58
Mhlenberger Loch (Airbus), Hamburg, Germany, 2001- 2002 Stabilenka 200 & FORTRAC 200 special combination
Alberto Simini
117
Mhlenberger Loch (Airbus), Hamburg, Germany, 2001- 2002 Stabilenka 200 & FORTRAC 200 special combination
Alberto Simini
118
59
Rinforzo su pali
Alberto Simini
119
Geotextile Reinforcement
Piles
120
60
Alberto Simini
121
Pali Pali
Rinforzo con geosintetici tra pali Alberto Simini Trieste 9 Aprile 2008
61
Alberto Simini
123
1993-1994
Alberto Simini
124
62
Alberto Simini
125
Monitoraggio
Cella di controllo
Alberto Simini
126
63
XX24
Kanal 22
22.09.1998
10:00
MQS II km 44.8 + 0,02% locomotive + 0,01% bottom geogrid in span perpend. to embankment loaded waggon
a) 0
XX24 Kanal 20 22.09.1998
5128
empty waggons
10:00
empty waggons
- 0,01%
b)
AZ.: G 9813080
level: bottom (1 st ) geogrid max about 1%; max "sagging" 45 mm Ebene: unterstes (1.) Geogitter max ca. 1%; max "Durchhang" 4,5 cm
Hhe (mm)
1.0 m ~1.9 m
1.0 m ~1.9 m
1.0 m
Anlage: 25.25
LGA
Landesgewerbeanstalt Bayern
-100 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0 6.5 7.0 7.5 8.0
Lnge (m)
64
Tangenziale di Selby, Regno Unito, 2002 Soluzione mista di geogriglie in rotoli ed in strisce su pali Geogriglie in PVA 1200 e 1600 kN/m
up to 12 m
Alberto Simini
129
65
-30 0.10 0.00 Settlement relative to datum m -0.10 -0.20 -0.30 -0.40 -0.50 -30 0.10 0.00 -0.10 -0.20 -0.30 -0.40 -0.50
-20
-10
10
20
30
Alberto Simini
2.00m
2.40m
131
Source: HS 132
66
Metodo Guido
Fonte: HS
Fonte: HS
Alberto Simini
133
Guido-design
Source: HS
Alberto Simini
134
67
Effetto membrana
Alberto Simini
135
Rinforzo su cavit
Alberto Simini
136
68
Geotextile Reinforcement
Piles
137
~ 3,5 m
69
Alberto Simini
140
70
Ferrovie, Grbers, EscavatoreTrieste 9 Aprile 2008 in un cedimento di una cavit, 2001 141 Alberto Simini
Alberto Simini
Trieste 9 Aprile 2008 Ferrovie, Grbers, arco sopra una cavit, 2001
142
71
Ferrovie tedesche, DB AG, Gotha-Leinenfelde, cedimento della scarpata Simini una cavit al piede Aprile 2008 Trieste 9 del rilevato, 2002 143 Alberto causa
Grbers (Passante ferroviario fra Leipzig e Halle) Rilevati rinforzati su attraversamento cavit sotterranee per treni ALTA VELOCITA
Alberto Simini
144
72
Alberto Simini
145
PROGETTO
PRINCIPALI COMPONENTI DI UN SISTEMA DI SICUREZZA MULTI-FASE: Sistema di allarme, (min. 1 segnale di allarme per ogni 1 m di area protetta); Sistema composito di rilevato rinforzato in terra per superare eventuali cavit che si dovessero formare
REQUISITI: Cedimento massimo ammissibile: cedimento massimo differenziale max s 3.0 mm a una distanza dal binario L = 1500 mm Tempo di servizio del sistema: 60 anni Tempo fra il rilevamento della cavit ed il suo riempimento: 4 settimane (i.e. durata del carico del sistema fino a 4 settimane).
Alberto Simini Trieste 9 Aprile 2008 146
73
-0.000
3.000
6.000
9.000
12.000
15.000
18.000
21.000
24.000
6.000 kN/m A B A B A B A B 80.000 60.000 3.000 40.000 20.000 0.000 -20.000 0.000 -40.000 -60.000 -80.000 -100.000 -3.000 -120.000 -140.000 -160.000 -180.000 -6.000 -200.000 -220.000 -240.000 -260.000 -9.000 -280.000 -300.000
2
Alberto Simini
148
74
7.00
8.00
9.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
7.00
6.00
5.00
level + 4.00
4.00 A A*
3.00
2.00
1.00
delta
0.00
-1.00
Alberto Simini
149
Alberto Simini
150
75
Alberto Simini
151
Alberto Simini
152
76
Alberto Simini
153
Alberto Simini
154
77
Alberto Simini
155
Alberto Simini
78
3. Stabilit/portanza
dellappoggio della colonna
4. Sistema a cedimento:
pi comprimibile di pali in acciaio o cemento armato e meno in assenza diTrieste 9 Aprile 2008 colonne Alberto Simini
157
79
Alberto Simini
159
Alberto Simini
160
80
161
Alberto Simini
162
81
Progetto: costruzione di una diga avente lunghezza di 2.4 km su terreni molto soffici (resistenza al taglio non drenata Cu < 15 kN/m2) con fondazioni su colonne in sabbia incapsulate con geotessile Geotextiles Encased Columns (GEC) per il recupero di una area di 140 ettari sulla foce del fiume Elba, ad Amburgo, utilizzata per la relizzazione di una nuova fabbrica per la produzione dellAirbus A 380 da mille posti.
Alberto Simini Trieste 9 Aprile 2008 163
Soluzione alternativa
Alberto Simini
164
82
Caratteristiche del terreno in situ: Cu Eoed da 0.4 a 10.0 kN/m2 sotto un carico ref = 100 kN/m2
Alberto Simini
165
Dati di progetto: Altezza diga: Altezza piano campagna polder: Pendenza scarpe diga: Numero colonne: Diametro colonne Interasse triangolare Caratteristiche geotessile 9 metri sopra il livello mare 5,5 m sopra l. m. ridotta da 1:20 a 1:6 > 60.000 di lungh. da 4 m a 15 m 80 cm da 1,70 m a 2,40 m J variabile da 1.800 a 2.800 kN/m res. traz. da 100 a 400 kN/m Area di copertura colonne Rinforzo sulle colonne Fattore sicurezza assest. diga
Alberto Simini Tempo di realizzazione:
3 anni a 9 mesi
166
83
Alberto Simini
167
Alberto Simini
168
84
Alberto Simini
169
Alberto Simini
170
85
Alberto Simini
171
Alberto Simini
172
86
Alberto Simini
173
Alberto Simini
174
87
Alberto Simini
175
Alberto Simini
176
88
Alberto Simini
177
Alberto Simini
178
89
Alberto Simini
179
- n 2 inclinometri orizzontali
Trieste 9 Aprile 2008 180
Alberto Simini
90
Conclusioni generali: - sulla base delle misurazioni le reali propriet del terreno sono risultate migliori di quelle di progetto - non si sono manifestati problemi di stabilit nella fase di costruzione della diga - il sistema GEC utilizzabile con valori di Cu < 15 kN/m2
- la soluzione GEC ha permesso di:
- risparmiare 35.000 t di acciaio per la costruzione del diaframma - risparmiare 1.100.000 m3 di sabbia - risparmiare la bonifica di 150.000 m2 di area fluviale - ridurre inquinamento acustico: 12 macchine per la vibroinfissione producono un livello di rumore pari a 50 dB a 1.000 metri - ridurre i tempi di costruzione da 3 anni a 9 mesi
Alberto Simini di assestamento
- ridurre drasticamente lassestamento della diga con una velocit 181 similare Trieste 9 Aprile 2008 a quella dei dreni verticali
GRAZIE
PER LA VOSTRA ATTENZIONE
Ing. Alberto Simini
a.simini@huesker.it
HUESKER SRL
Piazza della Libert 3 - Trieste Libert www.huesker.com tel. 040/363605
Alberto Simini Trieste 9 Aprile 2008 fax. 040/3481343 182
91