Sei sulla pagina 1di 7

FORMULA POLINOMICA N° 03 - OBRAS CIVILES E INSTALACIONES ELECTROMECANICAS

ACTUAL ACUMULADO SALDO


Item Descripción % %
METRADO IMPORTE METRADO IMPORTE METRADO IMPORTE
OBRAS CIVILES E INSTALACIONES
3 107,626.23 1,637,946.44 1,042,241.60
ELECTROMECANICAS
3.2 CAMARAS DE BOMBEO 84,252.07 1,244,744.18 573,677.13
CAMARA DE BOMBEO DE AGUAS RESIDUALES
3.2.2 84,252.07 486,791.54 121,154.83
N°02 MIRAFLORES"
3.2.2.01 CAMARA DE BOMBEO Nº 2 MIRAFLORES 81,882.25 390,089.69 119,185.41
3.2.2.01.02 MOVIMIENTO DE TIERRAS 2,908.30 38,216.78 0.00
3.2.2.01.02.04 Confitillo 1/2"-3/4" al interior de cerco perim. 286.25 2,908.30 286.25 2,908.30 100.00% 0.00 0.00 0.00%
3.2.2.01.05 CARPINTERIA METALICA 15,588.42 23,593.15 661.34
3.2.2.01.05.05 REJILLA PARA CAMARA DE REJAS 1.00 1,802.18 1.00 1,802.18 100.00% 0.00 0.00 0.00%
COMPUERTA ARMCO O SIMILAR CON
3.2.2.01.05.06 1.00 13,786.24 1.00 13,786.24 100.00% 0.00 0.00 0.00%
PEDESTAL de Ø20" L=11.00 m.
3.2.2.01.12 INSTALACIONES ELECTROMECANICAS 63,385.53 174,141.15 112,635.14
3.2.2.01.12.01 EQUIPO DE BOMBEO 4,500.00 95,700.00 25,180.41
3.2.2.01.12.01
SISTEMA DE IZAJE (riel, tecle y cadena) 1.00 4,500.00 1.00 4,500.00 50.00% 1.00 4,500.00 50.00%
.03
3.2.2.01.12.03 ACCESORIOS Y NIPLES 58,885.53 73,372.45 0.00
3.2.2.01.12.03
LINEA DE SUCCION 1,553.82 15,864.52 0.00
.01
3.2.2.01.12.03
UNION DRESER DE 6" BB 2.00 1,553.82 2.00 1,553.82 100.00% 0.00 0.00 0.00%
.01.06
3.2.2.01.12.03
LINEA DE DESCARGA 57,331.71 57,507.93 0.00
.02
SISTEMA MECANICO GUIA DE
3.2.2.01.12.03
CANASTILLA Y REJILLA DE RETENCION VER 1.00 13,103.04 1.00 13,103.04 100.00% 0.00 0.00 0.00%
.02.01
DETALLES
3.2.2.01.12.03 UNION DRESER DE HIERRO DUCTIL DE
3.00 3,068.73 3.00 3,068.73 100.00% 0.00 0.00 0.00%
.02.02 8" BB
3.2.2.01.12.03 NIPLE DE HIERRO DUCTIL DE 8"X4 MTS.
1.00 1,640.58 1.00 1,640.58 100.00% 0.00 0.00 0.00%
.02.03 BB
3.2.2.01.12.03 CODO HIERRO DÚCTIL BRIDADO 90º x
3.00 2,785.74 3.00 2,785.74 100.00% 0.00 0.00 0.00%
.02.04 150 mm.
3.2.2.01.12.03 CODO HIERRO DÚCTIL BRIDADO 45º x
3.00 2,785.74 3.00 2,785.74 100.00% 0.00 0.00 0.00%
.02.05 150 mm.
3.2.2.01.12.03
TAPÓN DE HIERRO DÚCTIL DN 200 mm 3.00 702.09 3.00 702.09 100.00% 0.00 0.00 0.00%
.02.06
3.2.2.01.12.03
TAPÓN DE HIERRO DÚCTIL DN 150 mm 3.00 672.09 3.00 672.09 100.00% 0.00 0.00 0.00%
.02.07
3.2.2.01.12.03 YEE DE HIERRO DUCTIL 03 BRIDAS DE
3.00 4,222.74 3.00 4,222.74 100.00% 0.00 0.00 0.00%
.02.08 200 MMX 160 MM.
3.2.2.01.12.03 NIPLE DE HIERRO DUCTIL 8"X 0.35 MTS.
6.00 1,666.20 6.00 1,666.20 100.00% 0.00 0.00 0.00%
.02.09 BB
3.2.2.01.12.03
VALVULA COMPUERTA FoFo.B.B. 8" 3.00 10,133.10 3.00 10,133.10 100.00% 0.00 0.00 0.00%
.02.10
3.2.2.01.12.03
VALVULA SCHECK FoFo.B.B. 6" 2.00 5,181.40 2.00 5,181.40 100.00% 0.00 0.00 0.00%
.02.11
3.2.2.01.12.03
TRANSICION DE BRIDA-MAZA. 8" 1.00 483.40 1.00 483.40 100.00% 0.00 0.00 0.00%
.02.12
3.2.2.01.12.03
EMPAQUES DE JEBE-LONA DE 8" 8.00 186.16 8.00 186.16 100.00% 0.00 0.00 0.00%
.02.13
3.2.2.01.12.03 PERNOS 7/8 X 4" C/TUERCA Y ANILLO
224.00 1,344.00 224.00 1,344.00 100.00% 0.00 0.00 0.00%
.02.14 PLANO
3.2.2.01.12.03 BRIDA ROMPEAGUA DE HIERRO DÚCTIL
4.00 741.76 4.00 741.76 100.00% 0.00 0.00 0.00%
.02.15 PARA TUBERIA DN 200 mm.
3.2.2.01.12.03
MONTAJE Y DESMONTAJE DE EQUIPOS 1.00 4,677.12 1.00 4,677.12 100.00% 0.00 0.00 0.00%
.02.16
3.2.2.01.12.03 SUMINISTRO E INSTALACION DE
1.00 3,479.63 1.00 3,479.63 100.00% 0.00 0.00 0.00%
.02.17 SISTEMA DE VENTILACION DE CAMARA
3.2.2.01.12.03 DADOS DE CONCRETO PARA APOYO DE
3.00 370.08 3.00 370.08 100.00% 0.00 0.00 0.00%
.02.18 TUBERIA 0.25 x 0.50 x 0.80 m.
3.2.2.01.12.03 DADOS DE CONCRETO PARA APOYO DE
1.00 88.11 3.00 264.33 100.00% 0.00 0.00 0.00%
.02.19 BOMBA 0.50 x 0.50 x 0.35 m.
PISO DE CASETA PARA GRUPO
3.2.2.02.08 2,369.82 3,338.51 0.00
ELECTROGENO Y TABLERO DE MANDO
3.2.2.02.08.01 FALSO PISO AMBIENTE G.E Y DE TABLEROS 35.11 792.43 35.11 792.43 100.00% 0.00 0.00 0.00%
3.2.2.02.08.02 PISO PULIDO Y BRUÑADO 31.51 1,577.39 31.51 1,577.39 100.00% 0.00 0.00 0.00%
3.3 SISTEMAS DE UTILIZACION EN MEDIA TENSION 23,374.16 89,601.65 405,415.75
SISTEMA DE UTILIZACIÓN EN MT 50 KV PARA
3.3.1 1,750.00 50,618.33 117,007.33
CAMARA DE BOMBEO -NOMARA
3.3.1.02 MONTAJE ELECTROMECANICO 1,750.00 12,563.88 19,691.90
3.3.1.02.08 TRANSPORTE DE MATERIALES 1,750.00 6,125.00 2,625.00
TRANSPORTE DE MATERIALES LINEA EN
3.3.1.02.08.01 0.20 1,750.00 0.70 6,125.00 70.00% 0.30 2,625.00 30.00%
MEDIA TENSION
SISTEMA DE UTILIZACIÓN EN MT 50 KV PARA
3.3.3 21,624.16 21,624.16 137,161.00
CAMARA DE BOMBEO -MACACARA.
3.3.3.01 SUMINISTRO DE MATERIALES 13,509.28 13,509.28 115,706.00
3.3.3.01.01 POSTES Y MENSULAS 5,118.33 5,118.33 0.00
POSTE CAC 13/600/180/375 (Incluye Perilla y
3.3.3.01.01.01 1.00 1,578.33 1.00 1,578.33 100.00% 0.00 0.00 0.00%
aditivo inhibidor de corrosión)
POSTE CAC 15/400/225/450 (Incluye Perilla y
3.3.3.01.01.02 1.00 1,720.00 1.00 1,720.00 100.00% 0.00 0.00 0.00%
aditivo inhibidor de corrosión)
MENSULA DE CONCRETO VIBRADO DE
3.3.3.01.01.03 2.00 240.00 2.00 240.00 100.00% 0.00 0.00 0.00%
M/1,0/500
MENSULA DE CONCRETO VIBRADO DE
3.3.3.01.01.04 2.00 280.00 2.00 280.00 100.00% 0.00 0.00 0.00%
M/0,8/500
MENSULA DE CONCRETO VIBRADO DE
3.3.3.01.01.05 2.00 250.00 2.00 250.00 100.00% 0.00 0.00 0.00%
M/0,6/500
MEDIA PALOMILLA SIMPLE DE C.AV.
3.3.3.01.01.06 2.00 300.00 2.00 300.00 100.00% 0.00 0.00 0.00%
MP/1.50/150
3.3.3.01.01.07 MEDIA LOZA DE CAV 1.10M/750 2.00 580.00 2.00 580.00 100.00% 0.00 0.00 0.00%
CRUCETADE MADERA TRATADA 100 X
3.3.3.01.01.08 2.00 170.00 2.00 170.00 100.00% 0.00 0.00 0.00%
100MM X 2.40M DE LONGITUD
3.3.3.01.02 AISLADORES y ACCESORIOS 1,440.00 1,440.00 0.00
AISLADOR POLIMERICO TIPO SUSPENSION
3.3.3.01.02.01 12.00 1,440.00 12.00 1,440.00 100.00% 0.00 0.00 0.00%
28KV
3.3.3.01.03 FERRETERIA 3,549.02 3,549.02 0.00
ADAPTADOR TIPO LIRA DE A° G° 16MM Ø X
3.3.3.01.03.01 12.00 348.00 12.00 348.00 100.00% 0.00 0.00 0.00%
78MM LONG
ARANDELA CUADRADA PLANA DE A° G° A°
3.3.3.01.03.02 20.00 50.00 20.00 50.00 100.00% 0.00 0.00 0.00%
G° 57MM X 57MM X 5MM CON AGUJERO 18MM Ø
ARANDELA CUADRADA PLANA DE A° G° A°
3.3.3.01.03.03 12.00 30.00 12.00 30.00 100.00% 0.00 0.00 0.00%
G° 57MM X 57MM X 5MM CON AGUJERO 20MM Ø
ARANDELA CUADRADA PLANA DE A° G° A°
3.3.3.01.03.04 16.00 64.00 16.00 64.00 100.00% 0.00 0.00 0.00%
G°76MM X 76MM X 5MM CON AGUJERO 21MM Ø
GRAPA TIPO PISTOLA DE AL-AL PARA
3.3.3.01.03.05 12.00 300.00 12.00 300.00 100.00% 0.00 0.00 0.00%
CONDUCTOR DE 35MM2, DE 2 PERNOS
PERNO OJO A°G° DE 16MM Ø X 254MM
3.3.3.01.03.06 6.00 63.00 6.00 63.00 100.00% 0.00 0.00 0.00%
LONG,102MM MAQUINADO CON TUERCA Y CONTRAT.
PERNO DOBLE ARMADO A°G° DE 16MM Ø X
3.3.3.01.03.07 20.00 300.00 20.00 300.00 100.00% 0.00 0.00 0.00%
254MM CON TUERCA Y CONTRAT.
PERNO MAQUINADO A°G°16MM Ø X 457MM
3.3.3.01.03.08 3.00 50.10 3.00 50.10 100.00% 0.00 0.00 0.00%
LONG,152MM CON TCA Y CTTCA.
PERNO MAQUINADO A°G°16MM Ø X 508MM
3.3.3.01.03.09 3.00 50.10 3.00 50.10 100.00% 0.00 0.00 0.00%
LONG,152MM CON TCA Y CTTCA.
3.3.3.01.03.10 PLANCHA DE COBRE TIPO "J" 24.00 156.72 24.00 156.72 100.00% 0.00 0.00 0.00%
CONECTOR TIPO SPLIT BOLT PARA CABLE
3.3.3.01.03.11 6.00 61.20 6.00 61.20 100.00% 0.00 0.00 0.00%
DE 25MM2
CONECTOR TIPO CUÑA TIPO MINEWEDGE
3.3.3.01.03.12 12.00 103.20 12.00 103.20 100.00% 0.00 0.00 0.00%
HASTA 50MM2
TUERCA OJO A°G° FORJADO PARA PERNO
3.3.3.01.03.13 3.00 31.50 3.00 31.50 100.00% 0.00 0.00 0.00%
DE 16MM Ø
TERMINAL UNIPOLAR DE 18/30 KV P/ N2XSY
3.3.3.01.03.14 2.00 1,500.00 2.00 1,500.00 100.00% 0.00 0.00 0.00%
X 50mm2 TIPO EXTERIOR 03 Unidades)
3.3.3.01.03.15 FUSIBLE DE EXPULSION TIPO K 6.00 31.20 6.00 31.20 100.00% 0.00 0.00 0.00%
BRAZO SOPORTE RIOSTRA DE PERFIL
3.3.3.01.03.16 ANGULAR DE A°G° DE 50.8 X 50.8 X 6.35mm. SECCION 4.00 340.00 4.00 340.00 100.00% 0.00 0.00 0.00%
,1.20m DE LONG.
3.3.3.01.03.17 ABRAZADERA F°G°260MM DIAMETRO 2.00 70.00 2.00 70.00 100.00% 0.00 0.00 0.00%
3.3.3.01.04 CONDUCTORES, CABLES Y ACCESORIOS 1,710.80 1,710.80 0.00
CONDUCTOR COBRE TIPO TEMPLE DURO
3.3.3.01.04.01 20.00 360.00 20.00 360.00 100.00% 0.00 0.00 0.00%
CABLEADO DE 35MM2
CONDUCTOR DE COBRE DESNUDO,
3.3.3.01.04.02 CABLEADO, TEMPLE BLANCO, 25MM2 O 35.50 497.00 35.50 497.00 100.00% 0.00 0.00 0.00%
COOPERWELD N° 02AWG TIPO P
CONDUCTOR DE ALEACION DE ALUMINIO
3.3.3.01.04.03 105.00 367.50 105.00 367.50 100.00% 0.00 0.00 0.00%
6201-T81(AAAC), CABLEADO 35MM2
3.3.3.01.04.04 ALAMBRE DE AL 16MM2 PARA AMARRE 2.00 3.00 2.00 3.00 100.00% 0.00 0.00 0.00%
CINTA PLANA DE ARMARSEGUN
3.3.3.01.04.05 105.00 367.50 105.00 367.50 100.00% 0.00 0.00 0.00%
REQUERIMIENTO
VARILLA DE ARMAR SIMPLE AL-AL, PARA
3.3.3.01.04.06 12.00 115.80 12.00 115.80 100.00% 0.00 0.00 0.00%
CONDUCTOR DE 35MM2
3.3.3.01.05 PUESTA A TIERRA 1,691.13 1,691.13 0.00
CONDUCTOR PUESTA A TIERRA DE COBRE
3.3.3.01.05.01 RECOCIDO DE 25 MM2 O COOPERWELD N° 02 AWG 24.20 196.02 24.20 196.02 100.00% 0.00 0.00 0.00%
TIPO P
CONECTOR TIPO SPLIT BOLT PARA CABLE
3.3.3.01.05.02 12.00 122.40 12.00 122.40 100.00% 0.00 0.00 0.00%
DE 25MM2
ELECTRODO DE COOPERWELD DE 16MM Ø
3.3.3.01.05.03 4.00 173.60 4.00 173.60 100.00% 0.00 0.00 0.00%
x 2400 mm long.
CONECTOR DE BRONCE PARA ELECTRODO
3.3.3.01.05.04 10.00 127.00 10.00 127.00 100.00% 0.00 0.00 0.00%
DE 16MM
3.3.3.01.05.05 CAJA DE CONCRETO 4.00 180.00 4.00 180.00 100.00% 0.00 0.00 0.00%
REGISTRO DE CONCRETO PARA
3.3.3.01.05.06 2.00 33.60 2.00 33.60 100.00% 0.00 0.00 0.00%
INSPECCION DE PUESTA A TIERRA (TAPA)
3.3.3.01.05.07 BENTONITA (SACO DE 50KG) 8.00 280.00 8.00 280.00 100.00% 0.00 0.00 0.00%
3.3.3.01.05.08 SAL INDUSTRIAL (SACO DE 50KG) 12.00 222.00 12.00 222.00 100.00% 0.00 0.00 0.00%
3.3.3.01.05.09 TUBO PVC SAP 3/4 Ø x 1M DE LONG. 7.00 31.71 7.00 31.71 100.00% 0.00 0.00 0.00%
3.3.3.01.05.10 TIERRA VEGETAL CERNIDA 9.28 324.80 9.28 324.80 100.00% 0.00 0.00 0.00%
3.3.3.02 MONTAJE ELECTROMECANICO 4,019.88 4,019.88 19,700.00
3.3.3.02.01 OBRAS PRELIMINARES 303.51 303.51 0.00
REPLANTEO TOPOGRAFICO DE LA LINEA Y
3.3.3.02.01.01 0.07 106.59 0.07 106.59 100.00% 0.00 0.00 0.00%
UBICACION DE ESTRUCTURAS
INGENIERIA DE DETALLE Y EXPEDIENTE DE
3.3.3.02.01.02 0.07 196.92 0.07 196.92 100.00% 0.00 0.00 0.00%
REPLANTEO
3.3.3.02.02 MONTAJE DE POSTES 1,232.36 1,232.36 0.00
EXCAVACION HUECO PARA POSTE EN
3.3.3.02.02.01 2.00 90.56 2.00 90.56 100.00% 0.00 0.00 0.00%
TERRENO NORMAL
INSTALACION DE POSTES DE CONCRETO
3.3.3.02.02.02 2.00 752.74 2.00 752.74 100.00% 0.00 0.00 0.00%
ARMADO
3.3.3.02.02.03 CIMENTACION DE POSTE DE CONCRETO 2.00 241.66 2.00 241.66 100.00% 0.00 0.00 0.00%
CONSTRUCCION DE SOLADO DE
3.3.3.02.02.04 2.00 44.74 2.00 44.74 100.00% 0.00 0.00 0.00%
CONCRETO
RECUBRIMIENTO DE LA BASE EN
3.3.3.02.02.05 2.00 20.52 2.00 20.52 100.00% 0.00 0.00 0.00%
SUSTANCIA BITUMINOSA
RECUBRIMIENTO BASE DEL POSTE CON
3.3.3.02.02.06 2.00 27.58 2.00 27.58 100.00% 0.00 0.00 0.00%
SELLADOR IMPERMEABILIZANTE
3.3.3.02.02.07 SEÑALIZACION DE ESTRUCTURA 2.00 54.56 2.00 54.56 100.00% 0.00 0.00 0.00%
TENDIDO Y FLECHADO DE CONDUCTORES,
3.3.3.02.03 336.00 336.00 0.00
CABLES Y ACCESORIOS
TENDIDO Y PUESTA EN FLETA DE
3.3.3.02.03.01 210.00 336.00 210.00 336.00 100.00% 0.00 0.00 0.00%
CONDUCTOR AAAC 50 MM2/FASE
INSTALACION DE ARMADOS EN MEDIA
3.3.3.02.04 1,484.47 1,484.47 0.00
TENSION
3.3.3.02.04.01 ARMADO TIPO DR 3T3C-3C C.A.C 1.00 236.11 1.00 236.11 100.00% 0.00 0.00 0.00%
3.3.3.02.04.02 ARMADO TIPO PMI SEC C.A.C 1.00 633.19 1.00 633.19 100.00% 0.00 0.00 0.00%
3.3.3.02.04.03 ARMADO TIPO SAM-3FC 1.00 615.17 1.00 615.17 100.00% 0.00 0.00 0.00%
3.3.3.02.05 INSTALACION DE PUESTA A TIERRA 663.54 663.54 0.00
EXCAVACION DE HOYO PARA PUESTA
3.3.3.02.05.01 2.00 126.22 2.00 126.22 100.00% 0.00 0.00 0.00%
ATIERRA, EN TERRENO NORMAL
INSTALACION DE PUESTA ATIERRA TIPO
3.3.3.02.05.02 2.00 537.32 2.00 537.32 100.00% 0.00 0.00 0.00%
PAT-1 (INCLUYE RELLENO Y COMPACTACION)
3.3.3.03 TRANSPORTE DE MATERIALES 4,095.00 4,095.00 1,755.00