Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Agenda
Revision Session 1 Project Risk Management
Risk Management Processes Identifying Project Risks Risk Allocation with Contracts
Role of Advisors
2009
Revision Session 1
Debtor is a Project Company (SPV) Legally Independent from Sponsors Investing in a Capital Asset Lenders have limited recourse to Sponsors Assets
2009
Revision Session 1
Overall Project Finance market down 61% (3rd Qtr) Shift in Market Dynamics
2009
Proper Risk Management helps to ensure consistent cash flows throughout the life of the Project, thereby reducing likelihood of default on debt servicing requirements.
Risk Management helps to ensure that the probability & impact of Positive events are increased (negative events are decreased), thereby optimizing profitability of the venture.
2009
AS4360: Risk Management COSO ERM Framework IRM: Risk Management Standard OGC: Management of Risk PMI: Risk Management Standard
All documents have a similar methodology for the identification, analysis & treatment of Risks
2009
2009
Pre-completion Phase Activity Planning Technology Construction Post-Completion Phase Supply Risk Operational Risk Market Risk
Common Risks Interest Rate Risk Exchange Risk Inflation Risk Environmental Risk Regulatory Risk Legal Risk Credit / Counterparty Risk
2009
Planning
Scheduling
Procurement Construction
Scope Control
Controlling
Economic
External
Market Political
10
2009
Cumulative (%)
100 80 60 40
20 0 25 40 Time (min)
47 minutes
60
11
2009
Frequency%
The Project Company normally allocates risk through the config. of prelim. contracts before soliciting funds. However, Bank Analysis may reveal further risks, in which case:
12
2009
Construction Risk
The price paid to the contractor is usually the largest capital expenditure incurred by the project company. The contract is also the most likely source of significant cost overruns. Turnkey / EPC Contract
Is usually fixed price, the contractor taking the risk of any fluctuations in the cost of labour or materials FIDIC / NEC / Bespoke
13
2009
Features:
Damages (Liquidated)
Force Majeure
14
2009
Supply Risk
Put-or-Pay Agreements
Supplier Sells @ Pre-agreed Prices If supply is lacking, the Risk lies with the Supplier i.e. Compensates the Project Company
Input Supplier
The Input supplier bears the price risk on finding an alternative supplier either directly or indirectly
Indexed Payments
Project Company
Alternative Supplier
15
2009
Operational Risks
O&M Agreements
Fixed Price Contract: The Operator assumes risks relating to the fluctuations in operating costs
Pass-Through Contract: The Operator receives a fixed payment and performance bonuses
*Step-In Right: Lenders may request the right to remove the original operator and substitute with another.
16
2009
Market Risk
Offtake Agreements:
Long-term contracts where the Offtaker agrees to purchase nominated volumes/quantities of a good or services from the Project Company Take-or-Pay: the offtaker is obligated to pay even if it does not actually take the good or service i.e. PPA Shadow Toll System: payment is made by the Public Admin. on the basis of the volume of traffic & service level. Shadow refers to the fact that the end user does not actually pay the toll.
17
2009
18
2009
Although efficiency is questionable, the role of advisors is essential to the closure of Project Finance Deals
19
2009
Legal Advisors
Usually the first Advisors to be appointed by both Sponsors & Lenders Address specifics of International Legal Systems i.e. Civil Vs Common
Incorporation of the Project Company (SL) Due Diligence (AL) Legal Opinions (AL) Project Contracts (SL)
20
2009
Independent Engineer
Oversees & monitors the Project on behalf of the lending banks There may be a number of Independent Engineers dependent upon the technical nature of the project.
Due Diligence Reporting Certification / Issuing of Progress Reports Oversight of Testing & Commissioning Monitoring of Operations
21
2009
Insurance (General)
Insurance is an important risk mitigation tool that must be properly coordinated and linked to the projects contractual structure.
Insurance should be used when the Project Companys cost of risk mitigation using insurance policies is less than the premium for risk expressed in the interbank interest rates requested by banks if no coverage exists.
22
2009
Insurance Advisors
Preliminary Insurance Report Identifying analysis of contractual documentation & recommendations for risk coverage Final Insurance Report (Construction) Issued at the time of Financial Close typically constitutes a condition precedent for disbursement (drawdown). Conformity of Insurance Program Finance Insurance Report (Operations) Issued before start-up of Operations
23
2009
Construction / Contractors All-Risks Transport Policy Material & Damage All Risks Force Majeure
24
2009
Summary
Project Risk Management is an extremely important tool in the identification, analysis and mitigation of Project Risks. Advisors (Legal, Engineering & Insurance) play a crucial role in the mitigation of risks through:
25
2009