FILTER HOUSING ASSEMBLY

03-Feb -- Top dish in forming exp 02-Feb. -- CIP tower components ready for fab except rolled ring & weld flg -- Filter layout DVP suggested to wait till loading port decision -- Column tie back assembly parts in machining - Components available : Filter Collar; Lifting Boss; Cylinder Mtg Flg; Delta-p Mtg Flg; LW-120 Flg; LW-80 Flg; Bulkhead Adaptor, Upper Column (UC), UC top plt, UC clamp Plt; Ceiling Flange;
-

Components pending from purchase :

PRODUCT CONTAINER ASSEMBLY


03-Feb -- Cutout information made hold form GPSGB. -- 6thk plate packing list awaited from GPSGB. -- Bowl bot collar in fixturing for waterjet cutting -- Components available : Gill plate; Oval Sight Glass; Sample port; Pat port Tri clover; DN-80 discharge; Temp Sensor Flg; Trolley leg bends; Trolley Long handle; castor mtg pad; Loop Shackle; Guide Roller Support; pad for leg bend -- Components pending : DN-125 loading port;

LEG ASSEMBLY
03-Feb -- Skirt support part : plt components available dully formed; RHS fabricated; -- Lower Column fabricated & prepolished -- LC Clamp Plates available with studs fitted.

-- Components available :
LW-16 Flgs, Bulkhead Adaptor;
-- Components pending :

AUXILIARY ASSEMBLY
- Cable conduit Request given for subcontracting Material expected 27.03.10 & dully formed expected 31.03.2010 02-04-2010 Handles expected on 07-04-2010. 08-04-2010 Handles expected by 08-04-2010 - Ceiling Flange Cut & available to fit with Filter housing

HINGE COMPONENTS
COMPONENT HINGE PIN COVER HINGE PIN SKT SET SCREW THRUST BEARING HINGE BACK PLATE LOWER BEARING COVER BEARING CARRIER IGLIDUR-F BEARING BOWL HINGE SPACER HANDLE GUSSET PLATES HINGE MOUNTING BRACKET FASTNERS MATERIAL PTFE EN24T HTS UHMWPE SS-304 SS-304 SS-304 IGLIDUR SS-304 SS-304 SS-304 SS-304 SS-304 / SS 316 STATUS ORDER GIVEN TO GPSGB MATERIAL UNDER M/CING EXPECTED 18/03/2010 ORDER GIVEN TO GPSGB - MATERIAL AT MUMBAI CUSTOM ORDER GIVEN TO GPSGB - MATERIAL AT MUMBAI CUSTOM AVAILABLE AVAILABLE AVAILABLE ORDER GIVEN TO GPSGB - MATERIAL AT MUMBAI CUSTOM AVAILABLE MATERIAL TO BE CUT BY SHOP & TO BE BEND INHOUSE AVAILABLE AVAILABLE AVAILABLE

02-04-2010 -- All the hinge components are available & fitment in stacking in progress. 04-08-2010 -- The Hinge cover still awaited from GPSGB. All other components assembly made during stacking & now job in polishing.

Suggested work plan in order to catch the delivery 12.04.2010 Suggested work plan in order to catch the delivery 12.04.2010 20.04.2010

To, Shop GPSIN


1) Stacking of equipment with bowl hinge arrangement (30.03.2010 to 02.04.2010) 08-04-2010 job in polishing Weights of each subassembly needed by 02.04.2010 in order to plan for international transporter. 08-04-2010 Fiilter assembly & lower leg weight received. Still pending Exhaust manifold weight from shop. ----- The exhaust manifold fabrication (31.03.2010 to 05.04.2010) ----- 08-04-2010 Fabrication to complete by 13-04-2010 ----- Ensure all the items are welded on job like Bulkhead adaptor, Filter ring stops, ceiling flange, short handles, etc

2) QC clearance for stacking (02.04.2010) ---- Stacking inspection ensured by Mr. Dave & now parts in polishing. QC inspection can be done later on before/after hydrotest
3) Final Polishing of the job (03.04.2010 to 06.04.2010) Hydro test arrangement (31.03.2010 to 06.04.2010) - segregation all the connection/instruments/blanks used for Size 6 Shanxi Yabao project -Bottleneck can be highlighted at right time in order to have time to solve the problems) 08-04-2010 Polishing now to complete by 13.04.2010 Except DN155 blank flg(Mehul) & fastners (UKS), rest components are ensured by Mr. Nilesh. The CIP fittings (2 nos) fitted subsequent to seal valve bosses during hydro test are to be segregated . 4) Hydro test & dismantling/drying /cleaning + Dimension after hydro test stage (07.04.2010 to 10.04.2010) 08-04-2010 revised planned to 14.04.2010 to 17.04.2010) 5) Pre-desptach inspection 10.04.2010 19.04.2010. Shop to segregate all the loose items as per the packing list. 18.04.2010 --- Sunday - Holiday 6) Desptach on 12.04.2010 20.04.2010