Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
EAC TAB (CBB or PBB) Management Reserve (MR) PMB Performance Measurement Baseline (PMB) ETC UB BAC VAC NCC AUW CBB PBB
TAB
Plus Overrun
MR
CAs
SV CV
WPs
EVM Terminology
Projected Slippage
Time
Variances: (Favorable is Positive, Unfavorable is Negative) Cost Variance (CV): CV = BCWP ACWP Schedule Variance (SV): SV = BCWP BCWS Variance at Completion (VAC): VAC = BAC EAC Performance Indices: (Favorable is > 1.0, Unfavorable is < 1.0) Cost Performance Index (Efficiency): CPI = BCWP / ACWP Schedule Performance Index (Efficiency): SPI = BCWP / BCWS CV% = CV / BCWP x 100 SV% = SV / BCWS x 100
To Complete Performance Index (TCPI) TCPIEAC = Work Remaining / Cost Remaining = (BAC BCWPCum) / (EAC ACWPCum) TCPIBAC = Work Remaining / Budget Remaining = (BAC BCWPCum) / (BAC ACWPCum) Estimate at Completion (EAC) = ACWP + ETC EAC = Actuals to Date + Work Remaining / Performance Factor EACComposite = ACWPCum + (BAC BCWPCum) / (CPICum x SPICum) EACCPI = BAC / CPICum Favorable Causes: Poor initial planning or estimating Technical breakthrough Cost of labor & Material lower than plan Front end loading Method of earning BCWP Inaccurate costing methods
Revised July 2011
Status Percentage % Complete = BCWPCum / BAC x 100 % Spent = ACWPCum / BAC x 100 % Schedule = BCWSCum / BAC x 100
ACWP AUW BAC BCWS BCWP CA CBB EAC ETC MR NCC OTB PBB PMB PP TAB TCPI UB WP
Actual Cost of Work Performed (Actual cost incurred for work accomplished during a given period) Authorized Un-priced Work (Work contractually approved, but not yet negotiated) Budget At Completion (Total planned value for the project) Budgeted Cost for Work Scheduled (Planned Value - budget assigned to the planned scheduled work to be accomplished) Budgeted Cost for Work Performed (Earned Value - budget value for the physical work accomplished) Control Account (Management control point to plan and control scope, schedule, and budget) Contract Budget Baseline (Total negotiated cost plus AUW) Estimate At Completion (Expected total cost of the project when the scope of work will be completed) Estimate To Complete (Expected cost needed to complete all remaining work) Management Reserve (Budget withheld for unknowns / risk management) Negotiated Contract Cost (Contract price minus profit or fees or project value for in-house work) Over Target Baseline (Sum of CBB and recognized overrun) Project Budget Baseline (Same as CBB for in-house projects) Performance Measurement Baseline (Time-phased budget plan) Planning Package (Far term effort within a CA not yet defined into WPs) Total Allocated Budget (Sum of all budgets for work on project/contract = NCC, CBB/PBB, or OTB) To Complete Performance Index (Efficiency needed from status date to achieve an EAC or BAC) Undistributed Budget (Broadly defined effort not distributed into CAs) Work Package (Near term effort detailed planned within a CA)
Unfavorable Causes: Poor initial planning or estimating Technical problem Cost of labor or material higher than plan Inflation New labor contracts Work stoppage
NASA EVM Website: http://evm.nasa.gov