Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Electrical System
Topics for Discussion:
Electricity Billing Electrical Load Management Maximum demand Control Power Factor Improvement and its benefit Selection and location of capacitors Performance assessment of PF capacitors Distribution and transformer losses
Agriculture 30%
Residential 18%
Industry 39%
Others 13%
The 3-phase power is stepped up to a higher voltage for transmission on conductors strung on cross-country towers. High voltage (HV) and extra high voltage (EHV) transmission is usually carried out at 220 kV & 400 kV over long distances.
Where transmission is over 1000 kM, high voltage direct current transmission is also favoured to minimize the losses.
ELECTRICITY BILLING
The electricity billing by utilities for medium & large enterprises, in High Tension (HT) category, is often done on two-part tariff structure, i.e. one part for capacity (or demand) drawn
(Capacity or demand is in kVA (apparent power) or kW terms)
and the second part for actual energy drawn during the billing cycle or month. In addition to the above cost components, other components like Power factor penalty/bonus rates, fuel escalation charges, taxes, duties and surcharges, meter rentals, etc., are also included in the bill.
ELECTRICITY BILLING
Electricity bill indicates the following:
1. 2. 3. 4. 5.
6.
7. 8. 9. 10.
Maximum demand recorded and charges Energy consumed and charges Power factor Reactive energy consumed Fuel escalation charges Electricity duty charges Penalty for exceeding contract demand Penalty for low power factor Incentive for good power factor Time of the day rates
ELECTRICITY BILLING
Analysis of Electricity bill data and monitoring its trend continuously helps energy mangers to identify ways for electricity bill reduction through available provisions in tariff framework, apart from energy budgeting. The maximum demand is recorded, is not the instantaneous demand drawn, but it is the time integrated demand over predefined recording cycle.
ELECTRICITY BILLING
As example, in an industry, if the drawl over a recording cycle of 30 minutes is : 3500 kVA for 4 minutes; 4600 kVA for 12 minutes; 3100 kVA for 6 minutes; 3800 kVA for 8 minutes; The MD recorder will be computing MD as:
(3500x4) +(4600 x 12) + (3100 x 6) + (3800 x 8) 30
= 3940 kVA
ELECTRICITY BILLING
The monthly MD will be the highest among the demand values recorded every half hour
over the month The industry has to pay for the highest MD registered even if it occurred for just one recording cycle duration.
Demand Curve
Demand Management
Demand management commonly refers to a set of measures taken to reduce the maximum demand of the system without affecting the plant output.
As the demand charges constitute a considerable portion of the electricity bill, from user angle too there is a need for integrated load management to effectively control the maximum demand.
KVA
Hours
Make closer scrutiny of energy bills Identify variation in minimum & maximum of demand in various seasons. Analyse loads contributing to demand peak. Identify non-priority load. Determine when MD occurs (time/day) Define which loads could be Re-scheduled Reduced Turned off during peak load time
Manual type Load scheduling Demand monitoring activity Even alarm can be set-up Automatic demand controllers Large plant Load characteristics Energy Management system Acts as per demand + programmable Monitoring Capability
To understand power factor, well first start with the definition of some basic terms:
KW is Working Power (also called Actual Power or Active Power or Real Power). It is the power that actually powers the equipment and performs useful work. KVAR is Reactive Power.It is the power that magnetic equipment (transformer, motor and relay) needs to produce the magnetizing flux. KVA is Apparent Power. It is the vectorial summation of KVAR and KW.
increased magnetizing current for given kW leading to higher kVAr. Additional I2R loss of energy in the form of heat in every item of system Voltage drop in the reactive circuit kW output of transformer, T& D system is hampered. Thus handling capacity of the equipment reduces. Reduction of system efficiency.
Reactive power (KVArs), caused by inductive loads, always acts at a 90-degree angle to working power (KW).
Voltage level at the load end is increased. % voltage rise = kVAr of capacitor x % imp. of transformer kVA of transformer
kVA loading on the source generators as also on the transformers and lines upto capacitors reduces, giving capacity relief. A high power factor can help in utilizing the full capacity of the electrical system.
1. Reduced kVA (Maximum demand) charges in utility bill 2. Reduced distribution losses (KWH) within the plant network 3. Better voltage at motor terminals and improved performance of motors 4. A high power factor eliminates penalty charges imposed when operating with a low power factor 5. Investment on system facilities such as transformers, cables, switchgears etc for delivering load is reduced.
Selection of Capacitors
Capacitor sizing can be done by following equation: kVAr Rating = kW(Tan where,
Old
Tan
New
kVAr rating is the size of the capacitor needed, kW is the average power drawn, Old = Existing (Cos-1 PF) and New = Improved (Cos-1 PF)
Nomogram to determine Capacitor kVAr requirement for PF correction are available. Using the same one can suitably size the capacitor requirement to a desired power factor. Work out an example here
Location of Capacitors
It could be: At HT bus / transformer LT bus of transformer Main sub-plant buses Load points Remember: Maximum benefit, if pf correction is in the reverse order of flow of current. Hence: Identify the sources of low pf loads in plant Locate close to end equipment to reduce I2R loss Release of system capacity(kVA) happens if reactive current is reduced.
Location of Capacitors
Incoming supply
C4
C1 C3
M
C2
C2
Transformer
A transformer is an equipment which can accept energy at one voltage and deliver it at another voltage. Electrical energy generated at relatively low voltages is transmitted by transformers at high voltages and low currents, thus reducing line losses and voltage drop . Types of Transformers
Transformers are classified as two categories: 1. Power transformers: used in transmission network of higher voltages, deployed for step-up and step down transformer application (400 kV, 200 kV, 110 kV, 66 kV, 33kV)
2. Distribution transformers: used for lower voltage distribution networks as a means to end user connectivity. (11kV, 6.6 kV, 3.3 kV, 440V, 230V)
Transformer Losses
For a given transformer, the manufacturer gives the values for no-load loss, PNO-LOAD, and load loss, PLOAD.
The total transformer loss, PTOTAL, at any load level can then be calculated from:
PTOTAL = PNO-LOAD+ (% Load/100)2 x PLOAD Where transformer loading is known, the actual transformers loss at given load can be computed as: PTOTAL = No-Load Loss+ (kVA Load/Rated kVA)2 x Full Load Loss
10
Now a days semiconductor device technologies are popular to enhance efficiency and/or controllability of
load.
Use of these led to non linear loads requiring nonsinusoidal currents containing harmonics.
23
THANK YOU