GE 9FB

Main Inspection Events


MI CI HGP

High Temperatures

Combustion Inspection (CI), Hot Gas Path (HGP), Major (MI)

3 Presenter and Event 4/13/2012

Main Inspection events

Combustion Inspection (CI) (12,000FFH)


The combustion inspection consists in a short disassembly shutdown inspection of fuel nozzles, liners, transition pieces, crossfire tubes and retainers, spark plug assemblies, flame detectors and combustor flow sleeves. All those components may require repair or replacement at a CI Average budgetary amount for new parts & services: 12 Meuros (transactional) Average duration: 2 weeks Critical Inspection for Gas Turbine Reliability and emission levels control

4 Presenter and Event 4/13/2012

Combustor
DLN 2+ to DLN 2.6+ Design Features
Fuel Nozzle Cover with premix burners Cross-fire tube Flow Sleeve Combustion Casing Transition Piece

Liner

combustion zone

Factored Fired Hours (for a more detailed definition refer to GER 3620)

5 Presenter and Event 4/13/2012

Main Inspection events

Hot Gas Path Inspection (HGP) (24,000FFH)


The purpose of a hot gas path inspection is to examine those parts exposed to high temperatures from the hot gases discharged from the combustion process. The hot gas path inspection includes the full scope of the combustion inspection and, in addition, a detailed inspection of the turbine nozzles, stator shrouds and turbine buckets. All those components may require repair or replacement at a HGP Average budgetary amount for new parts & services: 42.5M Euros (transactional)

Average duration: 4 to 5 weeks


Critical Inspection for Gas Turbine Reliability, Safety and emission levels control
6 Presenter and Event 4/13/2012

Hot Gas Parts


Buckets

Shrouds

Nozzle

7 Presenter and Event 4/13/2012

Main Inspection events

Major Inspection (MI) (48,000 Hours)


The purpose of the major inspection is to examine all of the internal rotating and stationary components from the inlet of the machine through the exhaust. This inspection consists of complete combustion and hot gas path inspections, in addition to laying open the complete flange-to-flange gas turbine to the horizontal joints, Removal of all of the upper casings allows access to the compressor rotor and stationary compressor blades, as well as to the bearing assemblies. Average budget for new parts & services: 43.5M Euros (transactional) Average duration: 6 to 8 weeks Critical Inspection for Gas Turbine Reliability, Safety and emission levels control. More over this is also an essential operation to preserve and recover the Power and efficiency of the machine.
8 Presenter and Event 4/13/2012

Planned Maintenance Cost


Tx Reflects only cost to buy Parts/Repairs/Services bought on transaction per transaction basis (Tx) CSA payments are for the same supplies plus all the other services provided within a CSA
40 35 30 25 20 15 10 5 0 2009 2011 2013 2015 2017 2019 2021 2023

M Euros

Tx 143.29 CSA 88.2

By committing to long term services agreement customer receives GE services at competitive prices

9 Presenter and Event 4/13/2012

Planned Maintenance Cost


Only CSA provides added value for among others:

Technological risk coverage


If the planned intervals or the planned life of the parts vary from expectations, GE will cover all additional cost in a CSA, without a CSA this is extra costs to be beard by customer. Market Price Fluctuation risk coverage A CSA includes international indexes that vary with the overall economy, indexes can be adjusted to better match customer environment (European Labour)

Maintenance Management
CSA integrates a GE Contract Performance Manager to coordinate all GE actions with clients obligations CSA also integrates remote monitoring solution