EPRTM reactor: the path to certainty

An evolutionary approach to Gen III+ reactors

Generation I

Generation II

Generation III+

First prototypes of reactors

PWR, BWR, PHWR, RBMK, AGR

PWR, BWR PHWR

R&D on Innovative systems

1950
Chooz, Brennilis, Kahl, MZFR

1970
PWR, BWR < 1,400 MWe

1988
N4, KONVOI 1,300 to 1,500 MWe

2010
EPR, ATMEA1, KERENA 1100 to 1,600 MWe

2040

> EPRTM: the path to certainty Andreas Goebel

A complete range of Gen III+ reactors


TM

X Medium power output (1100+ MWe) X Evolutionary design (AREVA/MHI) X Design based on EPR and MHI model X Outstanding safety level X Minimal environmental impact

MWe) X Evolutionary design (Konvoi/N4)

X High power output (1600+

X Construction permits in Finland and France, China 2009. On-going construction in these countries X Low global power generation costs X Outstanding safety level X Minimal environmental impact X Maximized benefit from size effect

X Medium power output (1250+ MWe) X Evolutionary design (Gundremingen reference plant) with use of passive features in some safety systems XOutstanding safety level X Minimal environmental impact

> EPRTM: the path to certainty Andreas Goebel

The EPR reactor: performance with certitude

Evolutionary
Proven technology based on 87 PWRs built throughout the world, integrating numerous technological innovations

Safe
Double concrete shell designed to withstand the impact of a large airplane crash

Core meltdown prevention with 4 times 100% redundant safeguard systems, mitigation of severe accidents consequences, radiological protection, functional diversity of safety systems, robustness against external hazards such as airplane crash

Competitive
High power output (1600+ MWe), efficiency and availability, reduced power generation costs, extended life service
5 > EPRTM: the path to certainty Andreas Goebel 5

Projects
4 EPR under construction

Olkiluoto 3

Flamanville 3

Taishan 1&2

> EPRTM: the path to certainty Andreas Goebel

The EPR Olkiluoto 3 Project


Olkiluoto 3
Where Contract signed Customer Supplier Supply scope First Concrete Net electric output Reactor thermal output Target delivery date

Fast Facts
Olkiluoto, Finland Dec 18, 2003 Teollisuuden Voima Oy (TVO) Consortium formed by AREVA and Siemens AG (73% / 27%) and led by AREVA 1 EPR unit in turnkey construction Jul, 2005 1,600 MWe 4,300 MWth 2012

7 For internal use only

> EPRTM: the path to certainty Andreas Goebel

July 2007 FLASHBACK - General view

> EPRTM: the path to certainty Andreas Goebel

The EPR Olkiluoto 3 Project


Olkiluoto 3
2008
February 08 Steam Generator Blowdown Tank installation May 08 Reactor Compartment Pool Frame-work installed June 08 Erection started: First pipe installed in Fuel Building July 08 EDG tanks installation in Nuclear Auxiliary Building October 08 Start of electromechanical activities November 08 Next-to-last double ring liner installed in Reactor Building First heat exchanger lifted into Safeguard Building Installation of first accumulator in Reactor Building
9 For internal use only > EPRTM: the path to certainty Andreas Goebel 9

Milestones
2009
January 09 RPV and its head delivery at OL3 Temporary Control Room ready for operation March 09 Start of electromechanical activities in the spreading area May 09 Reactor dome delivered on site Completion of the cooling elements installation in the core catcher

2010

Civil construction status reactor building


April 2009

Reinforcement ongoing Concreted

July 2007

10

> EPRTM: the path to certainty Andreas Goebel

10

The EPR Olkiluoto 3 Project May 2009 OL3, the 1st of the EPR worldwide fleet

11

> EPRTM: the path to certainty Andreas Goebel

11

The EPR Olkiluoto 3 Project Nuclear Island - May 2009

12

> EPRTM: the path to certainty Andreas Goebel

12

The EPR Olkiluoto 3 Project Turbine Island - May 2009

13

> EPRTM: the path to certainty Andreas Goebel

13

The EPR Olkiluoto 3 Project Reactor Dome Delivery on site May 4

14

> EPRTM: the path to certainty Andreas Goebel

14

The EPR Olkiluoto 3 Project Installations completed at the Spreading area - May 2009

3D view of IRWST and Spreading Area

In containment Refueling Water Storage Tank (IRWST)

Spreading area

15

> EPRTM: the path to certainty Andreas Goebel

15

Transfer of activities from civil construction to electro-mechanical installation

16

> EPRTM: the path to certainty Andreas Goebel

16

The EPRTM Flamanville 3 Project

17

> EPRTM: the path to certainty Andreas Goebel

17

The EPRTM Flamanville 3 Project


Flamanville 3
Where Contract signed Customer Supplier Supply scope

Fast Facts
Flamanville, France Apr 11, 2007 Electricit de France (EDF) AREVA 1 EPR unit - Nuclear Island Nuclear Steam Supply System (NSSS) - Nuclear Island Engineering & Procurement (NI EP) Dec 2007 1,630 MWe 4,300 MWth 2012

First Concrete Net electric output Reactor thermal output Target delivery date

Copyright EDF
For 18 internal use only

March 2009
18

> EPRTM: the path to certainty Andreas Goebel

General Presentation

Products and Projects

Market and Outlook

The EPR Flamanville 3 Project View of the site May 2009

19

> EPRTM: the path to certainty Andreas Goebel

19

The EPR Flamanville 3 Project View of the site May 2009

COPYRIGHT EDF

20

> EPRTM: the path to certainty Andreas Goebel

20

The EPR Flamanville 3 Project Reactor Building May 2009

21

> EPRTM: the path to certainty Andreas Goebel

21

The EPR Flamanville 3 Project Turbine Building May 2009

22

> EPRTM: the path to certainty Andreas Goebel

22

The EPR Taishan 1&2 Project

23

> EPRTM: the path to certainty Andreas Goebel

23

The EPR Taishan 1&2 Project


Taishan 1&2
Where Contract signed Customer Supplier Supply scope

Fast Facts
Taishan, China Nov 26, 2007 Taishan Nuclear Power Company (TSNPC) AREVA in consortium with 2 subsidiaries of CGNPC 2 EPR units and the materials and services to operate them: -Nuclear Island Engineering & Procurement (NI EP) - Nuclear Steam Supply System (NSSS) - Balance of Nuclear Island (BNI) -Supply fuel and enriched uranium for 15 years Aug 2009 1,660 MWe 4,590 MWth 2013-14

First concrete Net electric output Reactor thermal output Target delivery date

2008
24 > EPRTM: the path to certainty Andreas Goebel 24

Site location

Daya Bay

TAISHAN

25

> EPRTM: the path to certainty Andreas Goebel

25

The EPR Taishan 1&2 Project View of the site - May 2009

For 26 internal use only

> EPRTM: the path to certainty Andreas Goebel

26

The EPR Taishan 1&2 Project Excavation - May 2009

For 27 internal use only

> EPRTM: the path to certainty Andreas Goebel

27

Future developments of the EPR reactor


UK
X EPR design pre-certification underway X EPR technology selected by EDF and E.ON

USA
X EPR technology selected by five utilities X Certification submitted in Dec. 2007 X Detailed Design underway

INDIA FRANCE
X 2nd EPRTM in Penly launched in March 2009 X MoU for 2 EPR reactors

EMIRATES
X EPR project under preparation with Suez and Total

28

> EPRTM: the path to certainty Andreas Goebel

28

We are building the new generation for power generation