Proper layout to be done with proper measurements. Excavation of the Ground for Equipment Foundations. Proper mixing of Concrete to be used Confirm the Concrete Temperature and its proper setting. Control of Measurements.
Welding
1. Welding is the major role in the projects. 2. Weld Type of Arc, Tig and Mig 3. Arc welding is considered for ducting, Unpressurised vessels, Structural, General etc. 4. Tig. welding is for Pressure vessels, Pipe lines of Low and High Lines. Ducting of Gas or Air flow. 5. Where the Expansion bellows are provided on Duct Lines, there is a chance of Leakage of gasses during sudden expansion. Tig welding is preferred. 6. Arc welding may not give that much chance for welding of ducts where the expansion joints are provided.
Welding
7. Testing of welding joints like, Penetrate test, Dip test, X-Ray Test, Magnetic Test, Ultrasonic Test etc. 8. Failure of Welding of joint will show by above tests. 9. For doing the welding joint, you have to take care about the edge preparation, Clearance between two faces. 10.For Tig welding, you have to care about the oxygen penetration while welding to avoid oxidation. There by failure of joint will take place.
Welding
11.Provide curtains to reduce the joint failure. 12.Better to provide closed area like Tig welding to be done with closed room. 13.Field joints are not possible to do like that, so you have to provide close atmosphere for doing the welding of joints of high or low pressure lines. 14.It is also important to take the welding joint into normality by doing the Annealing process. So that joint failure will reduce.
CLOSEUP
a. Plants should run at clean atmosphere. b. Plants should operate with in controlled environmental conditions. c. Plants should operate with in the recommended operating condition. d. Plant should be the unit, the Operating people as well as Management should feel happy to run. e. Management should not feel burden to run the plants with in the controlled conditions.
POWER GENERATION
a. For Economical Operation of Sulphuric Acid Plant should be minimum 250 MT/Day. So, that Power Generation should be 2500 HP. b. Plant will consume 865 KW the balance 1000 KW will be exported to other plants. c. We can save lot of energy from the plant. This cost will be: 1865x24x5=2,23,800 Rs per day. It means Rs. 800.00 Lacks will be generated from the plant. d. By Comparison we have to invest 20% more that the actual cost of the project of Sulphuric Acid Plant.
PREPARED BY
YALAMATI SATYANARAYANA PROJECT MANAGER M/S. HARIKA INDUSTRIES HYDERABAD INDIA CELL: +919849963639 / +966590288534 YALAMATI.SATYANARAYA@GMAIL.COM