Sei sulla pagina 1di 18

LANDSCAPING

Design & Implementation


PCM-2
Antonio, Felix Louie
Dela Cruz, Hazel Faith
Santos, Grace
Project Objectives
 To provide a visually pleasing environment
 To effectively manage and maximize the
resources and time available
 To create a space which encourages experience
of nature
Project Deliverables
 Planning  Execution
• Determine project limitations • Lawn
 Set project dimensions  Hardscape
 Determine required project spaces  Walkways
 Consult land title  Site furnishings
 Refer National Building Code for ordinances  Lighting
 Determine project finances  Sprinklers
 Make project estimates  Softscape
 Determine owner/client budget  Greeneries
• Design • Fence
 Draw sketches
 Seek client’s approval
 Repeat sketches for adjustments
 Finalize the design
 Draw working drawings
 Draw Floor plan
 Draw Elevation/s
 Draw Perspective/s
 Draw Plumbing Plan
 Draw Electrical Plan
 Draw Drainage Plan
Development Costs
Hardscape 4000 x 800 PHP 3,200,000.00
Softscape 4000 x 1200 PHP 4,800,000.00

TOTAL PHP 8,000,000.00

MAJOR WORK PACKAGE WEIGH IN % COST


1.0. INITIATION    
1.1. Pre-planning 2% PHP 160,000.00
1.2. Pre-engineering 3% PHP 240,000.00
1.3. Feasibility 3% PHP 240,000.00
1.4. Acquisition 10% PHP 800,000.00
TOTAL 18% PHP 1,440,000.00
2.0. PLANNING    
2.1. Architectural 10% PHP 800,000.00
2.2. Engineering 8% PHP 640,000.00
TOTAL 18% PHP 1,440,000.00
3.0. EXECUTION    
3.1. Materials
3.1.1. Hardscape
3.1.1.1. Fence 2.08% PHP 166,400.00
3.1.1.2. Structure 3.12% PHP 249,600.00
3.1.1.3. Sprinkler System 3.12% PHP 249,600.00
3.1.1.4. Lighting 2.08% PHP 166,400.00
3.1.2. Softscape 15.60% PHP 1,248,000.00
3.2. Labor 20% PHP 1,600,000.00
3.3. Insurance 2% PHP 160,000.00
3.4. Permits 2% PHP 160,000.00
3.5. Test/Inspection 2% PHP 160,000.00
3.6. Construction Overheads 5% PHP 400,000.00

3.7. Supervision 0.50% PHP 40,000.00


TOTAL 58% PHP 4,600,000.00
4.0. CLOSE OUT    

4.1. Inspection 1% PHP 80,000.00

4.2. Commissioning 0.50% PHP 40,000.00


4.3. Improvements 5% PHP 400,000.00
TOTAL 7% PHP 520,000.00

GROSS DEVELOPMENT COST 100% PHP 8,000,000.00


Network Table: Landscaping
Activity Description Preceding Activity Duration

A Site Clearing - 4

B Removal of Trees - 3

C General Excavation A 8

D General Grading of Area A 7

E Excavation of Trenches B,C 9

F Formworks/Rebars Placement B,C 12

G Install Sewer Lines D,E 2

H Install Other Utilities D,E 5

I Pour Concrete F,G 6


Network Diagram

D=7 H=5

A-4 E=9 G=2 I=6


C=8

F=12

B=3

CRITICAL PATH
0-1-2-4-5 = 30
CONCERT STAGE
PCM-2
Antonio, Felix Louie
Dela Cruz, Hazel Faith
Santos, Grace
Project Objectives
 To design a structurally stable and aesthetically
pleasing concert stage
 To come up with an efficient work scheduling and
organization
 To improve acoustical environment and eliminate
sound distortion and interference from the surrounding
 To toughen security around the premises of the concert
stage
 To induce dynamic mechanisms for creative stage play
effects
Project Deliverables
 Planning
• Determine project limitations
 Set project dimensions
 Determine required project spaces
 Consult land title
 Refer National Building Code for ordinances
 Determine project finances
 Make project estimates
 Determine owner/client budget
• Design Concert Stage
 Draw sketches
 Seek client’s approval
 Repeat sketches for adjustments
 Finalize the design
 Draw working drawings
 Draw Floor plan
 Draw Section/s
 Draw Elevation/s
 Draw Perspective/s
 Draw Structural Plan
 Draw Electrical Plan
 Conduct Fire and Life Assessment Report
 Acquire required signatures
 Implementation
• Stage
 Floor lights
 Overhead lights
 Monitor speakers (front and back)
 Audience speakers
 Monitor equipment
 Curtains
 Backdrop
• Security
 CCTV
 Entrance
 Exits
 Picket fence
• Backstage
 Equipment storage
 Dressing room
 Portable toilet
 Props storage
 Stage Lighting Control
 Roof
• Tensile membrane
• Steel framing
 Construct Foundation
• Inspect construction
 Rectify mistakes if any
 Construct Concert Stage
• Construct flooring
• Construct walls
 Construct exterior walls
 Construct partition walls
• Construct Roof
Plan
 DIMENSIONS IN
METERS (M)
 TOTAL LOT AREA
(TLA): 2450 sq.m.
Development Costs
Lot Value PHP 8000 (per sq.m.)x 2450 sq.m. PHP 19,600,000.00
Structure PHP 4000 (per sq.m.)x 312 sq. m. PHP 124,800.00
TOTAL PHP 19,724,800.00
MAJOR WORK PACKAGE WEIGH IN % COST
1.0. INITIATION    
1.1. Pre-planning 2% PHP 394,496.00
1.2. Pre-engineering 3% PHP 591,744.00
1.3. Feasibility 3% PHP 591,744.00
1.4. Acquisition 10% PHP 1,972,480.00
TOTAL 18% PHP 3,550,464.00
2.0. PLANNING    
2.1. Architectural 10% PHP 1,972,480.00
2.2. Engineering 8% PHP 1,577,984.00
TOTAL 18% PHP 3,550,464.00
3.0. EXECUTION    
3.1. Materials
3.1.1. Fence 6% PHP 1,183,488.00
3.1.2. Structure 10% PHP 1,972,480.00
3.1.3. Acoustical System 5% PHP 986,240.00
3.1.4. Electrical System & Lighting 5% PHP 986,240.00
3.2. Labor 20% PHP 3,944,960.00
3.3. Insurance 2% PHP 394,496.00
3.4. Permits 2% PHP 394,496.00
3.5. Test/Inspection 2% PHP 394,496.00
3.6. Construction Overheads 5% PHP 986,240.00
3.7. Supervision 0.50% PHP 98,624.00
TOTAL 58% PHP 11,341,760.00
4.0. CLOSE OUT    
4.1. Inspection 1% PHP 197,248.00
4.2. Commissioning 0.50% PHP 98,624.00
4.3. Improvements 5% PHP 986,240.00
TOTAL 7% PHP 1,282,112.00
GROSS DEVELOPMENT COST 100% PHP 19,724,800.00
Sequencing of Activities
Legend Activity Preceding Duration
Activity (days)

A Site Clearing ------------ 3


B General Grading A 3
C Erect Scaffolds B 1
D Set Up Backstage Tents B 3
E Set Up Picket Fence A 1
F Put Up Portable Toilet B 1
G Set Security E 2
H Set Up Stage C,D 2
I Disassemble Scaffolds H 1
J Electrical Assembly H 2
K Sound System Assembly J 1
L Lighting Assembly J 1
M Check All Functions K,L 1
N General Cleaning H,N 1
Network Diagram
1

0
3 3 1 2 2 1 1
1
3 0
1 1
1 0 0
1

Critical Path
START - A-B-D-H-J-L-M-N
1 = 14