Welcome to the Presentation on

• Project overview
• Civil Works related projection
• Land Acquisition
• Resettlement

June 26, 2018


1
Presentation Outline

Project Overview

Civil works related projection.

Land Acquisition

Resettlement
Presentation Outline

Project Overview

Civil works related projection.

Land Acquisition

Resettlement
Project Overview
•Original DPP Approved by ECNEC on: 06.07.2010
•Revised DPP Approved by ECNEC on: 19.04.2016
•Project Cost: BDT. 18034.47 Crore.
(GOB: 4919.07 Crore, PA: 13115.41 Crore)
•Implementation Period: July, 2010 to June, 2022.
•Development Partner: ADB.
•ADB Loan Amount: USD 1.500 Billion.
•First Tranche: 300 Million
•Loan Agreement Signed on: 21 June, 2017.
•Inclusion as Fast Track Project on: 27 April, 2016.
4
Major Components of Project

 Land Acquisition
 Resettlement Activities
 Civil/Construction Works
 Consultancy services
 CSC & PMC

5
Presentation Outline

Project Overview

Civil works related projection.

Land Acquisition

Resettlement
Construction Schedule

LOT-1
LOT-2
Disbursement Projection For LOT-1 & LOT-2

2018 2019 2020

USD BDT USD


Package  BDT Crore USD Million BDT Crore
Million Crore Million

LOT-1 296.71 37.76 1190.82 151.54 1010.50 128.60

LOT-2 875.57 111.42 1396.57 177.73 1010.74 128.63

Total 1172.27 149.18 2587.40 329.27 2021.24 257.22


Disbursement Update as on Feb 2018

Package BDT Crore USD Million

LOT-1 268.8 34.21

LOT-2 350.2 44.57

Total 619 78.77


Tranche of Loan

Total loan = USD 1500 USD Mil

1st Tranche = USD 300 Mil


2nd Tranche = USD 400 Mil
3rd Tranche = USD 500 Mil
4th Tranche = USD 300 Mil
1st Tranche

1st Tranche = 300 USD Mil

ADF 90 USD Mil


OCR 210 USD Mil
(For Consultancy
(For Civil works)
& Others)
Projection on Timeline of Tranche 2

• Disbursed USD 78.77 USD Mil


• Disbursement projection for 2018 is USD
149.18 Mil
• Disbursement projection upto 2018 is
(78.77+149.18)= USD 227.95 Mil which is
more than provision of Tranche 1 i.e USD 210
mil.
 Timeline for Tranche 2 is late 2018 or early
2019
Presentation Outline

Project Overview

Civil works related projection.

Land Acquisition

Resettlement
Timeline for Land Handover (Chittagong)

Track
LA Case Name of Required Chainage in Timeline for Land
Length Comments
No. Upazila Land (Acre) KM Handover by DC
(KM)
Handed over on 19
09/2016-17 Chandanaish 10.1725 -2 to +0.5 2.5
December,2017
Handed over on 14
31/2016-17 Satkania 55.0935 .5 to 6 km 5.5 Km
June,18
Handed over on 9
32/2016-17 Satkania 27.6325 6 to 8.1 2.1 km
April,18
Handed over on 12
33/2016-17 Satkania 51.115 8.2 to 11.6 3.4 Km
June,18
Handed over on 31
34/2016-17 Satkania 42.5105 11.7 to 15.4 3.7 Km
May,18
2 week of July
nd Estimate finalized
35/2016-17 Lohagara 85.0401 15.4 to 22.2
2018. by DC office.
PWD and Forest
13.515 department are
Lohagara
36/2016-17 92.8764 22.2 to 29 August ,18 preparing the
estimate for
affected assets.
Timeline for Land Handover (Cox’sbazar)

Required Track Timeline for


LA Case Name of Chainage in
Land Length Land Handover Comments
No. Upazila KM
(Acre) (KM) by DC
PWD completed
field assessment .
02/2016- +29.000 to Forest Department
Chakaria 514.0091 39.351 September-18
2017 +68.351 completed survey
of 7 mouza out of
15.
Estimate finalized
by DC office and
03/2016- +77.658 to + 1st week of July-
Ramu 278.4908 20.442 concurrence given
2017 98.100 18
by BR on 20 May,
2018
+68.351 to
9.307
+77.658
04/2016- Cox’s Bazar Handed over on
210.426
2017 Sadar 08 January 2018
+98.100
3.377
to101.477
Presentation Outline

Project Overview

Civil works related projection.

Land Acquisition

Resettlement
Resettlement Plan (RP)

 A time bound action plan that complies


with National regulations for land
acquisition and ADB’s Safeguard Policy
Statement (SPS) 2009;

 Mitigation of all the impacts;

 Measure to restore the assets and


livelihood of all affected persons.
Scope of Work for Implementation of
RP

 Conduct census & IOL and support Various


Committees;

 Assist in Land Acquisition Process;

 To ensure proper compensation for EP’s;

 Consultation and Participation activities;


Scope of Work…..(Continued)

 Data Entry in CMIS;

 Assistance in finding alternative place;

 Coordinate with and support ILRP INGO


conducting the Livelihood Improvement
Training Program (LITP);
Scope of Work…..(Continued)

 Conduct/liaise HIV/AIDS and Anti-Trafficking


Awareness Campaigns;

 Support in the implementation of gender-


related activities;
and

 Support the implementation of railway safety


awareness campaigns to the communities.
Type of losses As per Entitlement
Matrix in RP
Category Type of Losses
 Agricultural Land;
 Homestead Land;
Land  Industrial Land;
 Common Property Resources and
 Water bodies (all types of land).

 Residential Structures;
 Commercial/Industrial Structures;
Structure  PCRs/CPR Structures;
 Secondary Structure;
 Agriculture Infrastructure.
Type of losses…..(Continued)

Category Type of Losses


 Timber and Bamboos;
Trees  Fruits Tree;
 Fruits

 Standing Crops;
 Fish cultivation;
Crops/Fish
 Investment cost
Stock

23
Type of losses …..(Continued)

Category Type of Losses


 Share croppers, Licensees and Lessees
 Dismantled Commercial / Business
Premises;
Losses of  Employees/ Wage Earners;
Income  Rental assistance for renters.

24
Type of losses …..(Continued)

Category Type of Losses


 Vulnerable Households
Livelihood
 Severely Affected Household
Program

 Utilities Connection
Others  Transfer Grant
 Reconstruction Grant for Structure
 Reconstruction Grant for CPR’s

25
FGD with Affected Persons
Information Sharing is the first principle of
participation.

26
Consultation with Affected Women

27
FGD with Vulnerable HH.

28
Participation with Affected Persons
(up to 24 June,2018)

No. of Participants
Total
Activities
Number Male Female Total
Focus Group 93 892 427 1319
Discussion
Consultation 23 229 131 360
Meeting
Awareness 21 220 78 298
Session

29
Consultation with APs and other
Stakeholder
Achieved (up to 24
Activities June, 2018)
One to one discussion with
4560
Affected Persons (APs)
One to one discussion with
1745
EP Family
Interaction with local Elite
849
Persons
Interaction with UP 330
Chairman and Members
30
Information Campaign (Publication)
Achieved (Up to 24 June,
Activities 2018)

Distribution of Leaflet 7750 Nos

Distribution of Booklet 3700 Nos

31
Leaflet and Brochure

32
Leaflet Affixed in various locations

33
Survey on Inventory of losses (as of 24 June,
2018)
841

697

2657

Non
1492 Titled
1165 Titled

144

Chittagong Cox'sBazar Total

34
Formation of JVC, PVAC, GRC
• Gazette Notification for Different Committee by

MoR on dated 2nd November, 2017;

• All
Committee formed in Chandanaish,Lohagara,

Satkania,Chakaria, Ramu and Cox’sBazar Sadar

Upazila.
Activities of Committee at Chandanaish

• PVAC meeting completed for Assets


(Land, Structure, Trees, Crops and Fish);

• Two JVC meeting completed of 86 Non


Titled AP;

• One JVC meeting completed of 51 Titled AP.


Activities of Committee at Coxs Sadar

• PVAC meeting completed for Assets (Land,


Structure, Trees, Crops and Fish);

• Two JVC meeting completed of 123 Non


Titled AP;

• One JVC meeting completed of 25 Titled AP.


PVAC Meeting for Assets (Land & Fish) of
Chandanaish & Cox’sBazar sadar Upazila
Steps taken at Chandanaish and
cox’s Sadar for title Top-Up payment
• PVAC Meeting Minutes including PVAC
recommended rate (Land & Fish) sent to Ministry
for Approval on 07 May, 2018;
• A meeting was held for approval of recommended
rate (Land & Fish) with Ministry of Railways & BR
high officials at Rail Bhaban on 28 May, 2018;
• The meeting decided to review the recommended
rate;
• Necessary documents(CCL copy, Awardees
list etc) are collecting from DC office;
• Joint Verification Survey on going.

39
Payment status of Chandanish and
Cox’sBazar Sadar Upazila
• Payment Modality has been Approved.

• ID Card, EP file, Entitlement Card, Payment


Voucher and other necessary documents
completed for 209 EP.

• 56 Non titled EPs received compensation upto


24 June, 2018
Field visit of Deputy Director, Resettlement, BR
ID Card Distribution Among EP’s

42
Cheque distribution ceremony by DC office
Cheque Distribution Among EP’s at
Chandanaish

44
Cheque Distribution Among EP’s at
Cox’sBazar Sadar

45
Vulnerable Non titled EPs received
compensation

46
Payment status of Titled EP
Name of Name of LA case number Total Awardees Paid
District upazila
Chandanaish 09/2016-17 147 72
Satkania 31/2016-17 613 01

Satkania 32/2016-17 393 83


Chittagong
Satkania 33/2016-17 522 01

Satkania 34/2016-17 625 02

Cox’s bazar Cox’s bazar 04/2016-17 1142 257


sadar
Total: 3442 394
47
Payment status of Non Titled EP

Name of District Name of upazila Paid

Chandanaish 38
Chittagong

Cox’s bazar Cox’s bazar sadar 18

Total: 56

48
Steps taken at Lohagara, Chakaria
and Ramu for Non Title payment

• PVAC & JVC meeting will be organized;

• 295 NTH Survey completed;

• Joint Verification Survey ongoing;

• Necessary documents are collecting from


respective Non-titled EP.
Template of ADB

• CCL Monitoring

• CPR Status

• Vulnerable

• Non-Title
Timeline for upcoming Major task

• 1st Non Title JVS at Chakaria


• Submission of EP File and ID Card
distribution at Cox’sBazar Sadar • 3rd Title JVS at Cox’sBazar
sadar and Chandanaish

July August

Mid August September

• 1st PVAC meeting at Lohagara,


• 2nd Non title JVS at Chakaria
Chakaria and Ramu
• Submission of EP File and ID Card
• 1st JVC at Ramu
distribution at Ramu
• Submission of EP File and ID Card
• 2nd Title JVS at Cox’sBazar sadar and
distribution at Chandanaish and
Chandanaish
Cox’sBazar Sadar

51
Visit the Project by Honourable Minister,
Ministry of Railways
Mr. Mojibul Haque,MP, Honorable Minister, Ministry of Railways, visited
Dohazari Cox’s Bazar Railway Project on 8th to 9th September 2017 along with
MPs, GM (Railway Eastern zone),Project Director, Dohazari-Coxsbazar
Project,BR, others government high official and local political leaders. He visited
cox’s Bazar and Ramu rail station spot including freight facilities area.
Visit the Project by Secretary,
Ministry of Railways
Mr. Mofazzel Hossain, Honorable Secretary, Ministry of Railways, visited
Dohazari Cox’s Bazar Railway Project on 20 December, 2017 along with
Project Director, , Dohazari-Coxsbazar Project,BR and DORP-PATHMARK
officials. He visited some places of alignment.
Visit the Project by Director General,
Bangladesh Railway
Mr. Amjad Hossain, Director General, Bangladesh Railway, visited
Dohazari Cox’s Bazar Railway Project on 1st April, 2018 along with Project
Director, Dohazari-Coxsbazar Project,BR and DORP-PATHMARK officials. He
visited some places of alignment.
Last ADB mission on 18 March, 2018

55
Thank you