Checklist for repair of Power Criteria Remarks


Transformer
1 Service Life 20/25/30 years IEEMA
recommended 25
years

2 Capacity wise repairing criteria •10MVA= not


repair
•20/50 MVA= if
less than 25years
•100 MVA=if less
than 25years
3 Transformer element wise •Single winding/two
criteria(if Repairer agency is winding/Three
said transformer OEM) winding
•Core/OLTC

4 Repair cost •60% of


Transformer cost.
•50% of
Transformer cost.
•40% of
S.No. Checklist for repair of Power Criteria Remarks
Transformer

5 Scrap Value •60% of


Transformer cost.
•50% of
Transformer cost.
•40% of
Transformer cost.
6 Internal Inspection and •DP test(Insulation
healthiness test testing.)
•Furan analysis
•DGA
7 Repaired transformer (age less •OEM
than 20 years) •Other than OEM