DG Set –Non functional (Patna Zone)

Sr. Compliance dated 03.06.20


Name of GSS
no.
Quotation called for rectification and order to be
1. Buxar
placed by circle.

Jagdishpur Battery replaced by new one. commissioning work is


2.
left

3. Kudra Rectified. Battery replaced by new one.

AVR defective. Quotation called for rectification and


4. Pusauli
order to be placed by circle.
Governing control defective.
5. Hulasganj Quotation called for rectification and order to be
placed by circle.
DG Set –Non functional (Bhagalpur
Zone)

Sr. No. Name of GSS Compliance dated 03.06.20

1. Banka Rectified. Load trial has been taken.

Letter has been sent by field to M/s GEPDEC for


2. Banka(New) rectification of DG set. No action taken by agency. Letter
has been issued to project wing regarding rectification.

service engineer of M/S Jackson visited and inspected


3. Begusarai the DG set. Quotation for repair is awaited. In between
local agency is contacted for repair.
DG Set –Non functional (MUZ ZONE )
Sr.
Name of GSS Compliance dated 03.06.20
no.
Battery as well as AVR defective.
1. Vaishali
Procurement of Battery and AVR under process

2. Jainagar Rectified. Load test is pending

Rectified on dated 20.01.20 . Dg set becomes


functional but there is defect in battery,
3. Benipatti
Procurement of Battery is under process.

Service engineer visited and Estimate for


4. Phulparas
rectification has been placed .
Rectified. Procurement of Battery under process
5. Sheetalpur

6. Bettiah Rectified on dated 22.01.20