Project: VECTOR
Value Enhancement by Confidence in Team for Organized Restructure
Navitasys India
Private Limited
Strictly Private
and Confidential
13 Jan 2020
Agenda
Project Plan
Organization Structure/Design
2
Project Plan
PwC 3
Project Timelines 1 – Section 2
Project Plan
From Date To Date Activity Responsibilty
13.01.2020 14.01.2020 Organization Structure Discussions PwC/NIPL
14.01.2020 Organization Structure Sign Off NIPL
15.01.2020 20.01.2020 System Configuration PwC
20.01.2020 24.01.2020 Unit Testing & Developments (If Any) PwC
Unit Testing NIPL
27.01.2020 08.02.2020 Integration Testing & Development Testing PwC
Existing Developments Bug Fixing PwC
10.02.2020 19.02.2020 User Acceptance Testing NIPL/PwC
19.02.2020 UAT Sign Off NIPL
20.02.2020 25.02.2020 PRD Readiness for New Structure PwC/NIPL
28.02.2020 Go Live NIPL/PwC
PwC 5
Organisation Structure (1 of 2)
Org. Structure
S.No. OS Element OS Code Remarks
Description
NAVITASYS INDIA PRIVATE LTD.
PLOT NO-4, SECTOR 5, IMT
1 Plant 2540 Manesar Factory
MANESAR, GURUGRAM,
HARYANA, 122050
1001 External SC
6
Organisation Structure (2 of 2)
Org. Structure
S.No. OS Element OS Code Remarks
Description
BW10 - CORPORATE
BW20 - MOBILE PHONE
2530 Bawal BW30 - POWER BANK
BW40 - SMT
BW50 - ELCT.VECHILE BATTERY
Profit Center
7
Group
MN10 - CORPORATE
MN20 - MOBILE PHONE
2540 Manesar
MN30 - POWER BANK
MN50 - ELCT.VECHILE
7
Observations
1. There will not be any exclusive number range for Purchase Order, Sales Order,
Production Order, Purchase Requisition, PM Order, Material Document, MIRO
Document, OB Delivery.
2. Tax Invoice number range will continue same as existing one.
3. Intrastate STO will be supply through Delivery Challan.
8
User Acceptance Testing (UAT) - Scenario
UAT Submitted by Tested by
Scenario Description
ID PwC NIPL
Domestic Sale (Planning + Import Procurement +
Baneet Nag/
UAT01 Production + Domestic Sales) - Integrated with FICO, QM, Sudarshan K.
WM
Export Sales (Planning + Domestic Procurement with
Baneet Nag
UAT02 Advance + Production + Export Sales) – Integrated with /Sudarshan K.
FICO, QM, WM
UAT03 Subcontracting Procurement – Integrated with FI Manoj Singh
Manoj Singh/
UAT07 Purchase Return – Integrated with FI, QM & WM Gopinath
*UAT11
Variance test Stock
Intrastate cases performed
Transfer by core team for each SIT Script
(BawalManesarBawal) Gopinath /Manoj S.
9
Master Data
Extension
PwC 10
Master Data Migration
S.No. Master Data Remarks
1. Material Master • If any existing data need to extend then PwC will extend same in mass.
• Any new material will be created manually by NIPL directly into the PRD
system.
2. Purchase Info Record • Mass Extension
8. Profit Centre • All new PC & PC Group will be created manually by FICO
9. Cost Centre • All new CC & CC group will be created manually by FICO
10. Asset Master • Mass change in some of the existing Asset Master
• New Master will be created manually.
11. Vendor & Customer • No Extension is required , since use same company code
Master
11
Project Team (PwC & NIPL)
S.No Name Role SAP Module Entity Email ID Mobile No
Mr. Shirish Prasad Management Final Document Approver
PwC
Name Role Responsibility Signature Date
14