WEEKLY REPORT

PENYELENGGARAAN CERUN DI JALAN PERSEKUTUAN


SEMENANJUNG MALAYSIA MELALUI KONTRAK JANGKAMASA
PANJANG MULAI TAHUN 2017

Name Noor Affendi bn Dikkir Location Laluan B68 Seksyen 27.7

Position Assistant Resident Engineer Date 09/08/19 – 15/08/19

Method: Soil Nailing and Hydroseeding

Friday (9/8/2019)
-Site Clearing (cut trees)

Saturday (10/8/2019)
-No activity on Site

Sunday (11/8/2019)
-Public Holiday (Hari Raya Haji)

Monday ( 12/8/2019)
-Public Holiday (Hari Raya Haji)

Tuesday (13/8/2019)
-Cutting dead fallen trees

Wednesday ( 14/8/2019 )
-Pegging for soil nailing points

Thursday ( 15/8/2019)
-Housekeeping works

Prepared by,

……………………………………..
(Noor Affendi Bin Dikkir)
Date : 16/8/2019
WEEKLY REPORT
PENYELENGGARAAN CERUN DI JALAN PERSEKUTUAN
SEMENANJUNG MALAYSIA MELALUI KONTRAK JANGKAMASA
PANJANG MULAI TAHUN 2017

Name Noor Affendi bn Dikkir Location Laluan FT68 Seksyen 27.7

Position Assistant Resident Engineer Date 16/08/19 – 22/08/19

Method: Soil Nailing and Hydroseeding

Friday (16/8/2019)
-Site Clearing (cut trees)

Saturday (17/8/2019)
-No activity on Site

Sunday (18/8/2019)
-No activity on Site

Monday ( 19/8/2019)
-No activity on Site

Tuesday (20/8/2019)
-No activity on Site

Wednesday ( 21/8/2019 )
-No activity on Site

Thursday ( 22/8/2019)
-No activity on Site

Prepared by,

……………………………………..
(Noor Affendi Bin Dikkir)
Date : 26/8/2019
WEEKLY REPORT
PENYELENGGARAAN CERUN DI JALAN PERSEKUTUAN
SEMENANJUNG MALAYSIA MELALUI KONTRAK JANGKAMASA
PANJANG MULAI TAHUN 2017

Name Noor Affendi bin Location Laluan FT68 Seksyen Project 19/6/19
Dikkir 27.7 Start
Position Assistant Resident Month/ October/1st Week Project 18/11/19
Engineer(Central) Week End

District/State: Gombak/Selangor Method: Soil Nailing and Hydroseeding

Friday (16/8/2019)
Activity
-Insert TMP

Schedule % :
Actual % :

Saturday (17/8/2019)
-No activity on Site

Sunday (18/8/2019)
-No activity on Site

Monday ( 19/8/2019)
-No activity on Site

Tuesday (20/8/2019)
-No activity on Site

Wednesday ( 21/8/2019 )
-No activity on Site

Thursday ( 22/8/2019)
-No activity on Site

Prepared by, Checked by,

…………………………………….. ……………………………………..
(Noor Affendi Bin Dikkir) (Fadly Arif Bin Abdullah)
Assistant Resident Engineer Resident Engineer
Date : //2019 Date : //2019