Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
1 2 2 3 1 3 10 3 12
A B C
START FINISH
1 6 6 7 3 9 10 5 14
D E F
CPM Special Attention
Path Convergence ─ Backward Pass
Path Convergence − Backward
(Right to Left / LS and LF):
C and F flow Backward to E
Backward with Less: Choice of Successor Late Start
is between 10 and 12 − 10 is less. Therefore, Late Finish of Predecessor is 9.
1 2 2 3 1 3 10 3 12
9
A 10 11
B 11 12 C 14
START FINISH
1 6 6 7 3 9 10 5 14
1 D 6 7 E 9 10 F 14
CPM Special Attention
The Five-Step Approach ─ Summary
1. Determine the number of paths in the
network diagram.
2. Determine the Critical Path.
3. Complete the Critical Path.
4. For non-Critical Paths and activities,
do a Forward Pass and a Backward Pass.
5. For non-Critical Paths and activities,
determine Total Float and Free Float.
CPM Special Attention
The Five-Step Approach ─ Detailed
1. Determine the number of paths in the
network diagram.
2. Determine the Critical Path.
– Add the durations of each path.
– Path with the highest number is the Critical
Path.
CPM Special Attention
The Five-Step Approach ─ Detailed
CPM Special Attention
The Five-Step Approach ─ Detailed
Activity F
Late Late
Float
Start (LS) Finish (LF)
Backward Pass
To Establish LS and LF
CPM Special Attention
The Five-Step Approach ─ Detailed
EF = ES + AD - 1
CPM Special Attention
The Five-Step Approach ─ Detailed
b. For all following activities:
1) The Early Start (ES) of each Successor Activity
is “the next number up” from the EF of
Predecessor Activity: S P
ES = EF + 1
b.For the activity’s Late Start (LS), subtract the activity’s duration from
the activity’s Late Finish, and then add 1:
LS = LF - AD + 1
Non-CP Float = LF - EF
b. But Remember:
1) For each activity not on Critical Path, LF ─ EF = Float,
as shown above.
2) But for all activities on the Critical Path, there is
normally zero Float.
CPM Special Attention
The Five-Step Approach ─ Detailed
29
EVM Special Attention
EVM ─ In a Nutshell
– Do you remember…
EV – PV – AC – BAC ?
– You must know at least two of these Data Points
to solve any EVM problem.
– Which ones you must know depend on the EVM
calculation being asked.
30
EVM Special Attention
31
EVM Special Attention
Four Data Points
• Earned Value (EV)
– Budgeted Cost of Work Performed (BCWP).
– You can easily figure this out from the facts of the
situation.
– EV/BCWP is the money value of where you really
are at this date on your schedule – the money
value of the scheduled Activities you have really
completed.
– Not necessarily the scheduled Activities you had
planned to be completed up to this date.
32
EVM Special Attention
Four Data Points
• Earned Value (EV)
– EV = BCWP. How to Remember: “E” for Earned.
“P” for Performed. Earned and Performed are
closely related in meaning.
– EV answers the question: What is the money
value of where I really am on this date?
33
EVM Special Attention
Four Data Points
• Planned Value (PV)
– Budgeted Cost of Work Scheduled (BCWS).
– You already know the PV from your planning
documents.
– PV/BCWS is the money value of where you
planned to be at this date on your schedule – the
money value of the scheduled Activities you had
planned to be completed by this date.
34
EVM Special Attention
Four Data Points
35
EVM Special Attention
Four Data Points
36
EVM Special Attention
Four Data Points
38
EVM Special Attention
Variance Calculations
CV = EV – AC
CV = EV ─ AC
CV = 3,750 ─ 5,000
CV = ─ 250
Version 0.1 40
EVM Special Attention
Variance Calculations
SV = EV – PV
SV > 0 = Ahead of schedule.
SV < 0 = Behind schedule.
41
EVM Special Attention
Variance Calculations
SV = EV ─ PV
SV = 3,750 ─ 2,500
SV = +1,250
Version 0.1 42
EVM Special Attention
Variance Calculations
CPI = EV / AC
45
EVM Special Attention
Performance Indexes ─ Past
CPI = EV / AC
CPI = 3,750 / 5,000
CPI = 0.75
Version 0.1 46
EVM Special Attention
Performance Indexes ─ Past
SPI = EV / PV
47
EVM Special Attention
Performance Indexes ─ Past
SPI = EV / PV
SPI = 3,750 / 2,500
SPI = 1.5
Version 0.1 48
EVM Special Attention
Forecast Calculations: EAC and ETC
REPORTING
Good News − Bad News How much the team will
Day need to complete the
project from this day to
the end.
Project Project
Start Finish
= 4,750 / 0.75
= 3,947
Version 0.1 51
EVM Special Attention
Forecast Calculation: ETC
─ If the ETC is based on a new Cost Baseline…
2 ?
ETC = EAC – AC
Version 0.1 52
EVM Special Attention
Forecast Calculation: EAC
53
EVM Special Attention
Forecast Calculation: EAC
EAC1:
─ Accepts performance up to this point in the
project – as indicated by the AC – but assumes
performance will be at the original BAC-
budgeted rate from this point to the end.
1
EAC = AC + (BAC – EV)
54
EVM Special Attention
Forecast Calculation: EAC
= 5,000 + 4,750
= 9,750
Version 0.1 55
EVM Special Attention
Forecast Calculation: EAC
EAC2:
─ Assumes that the performance up to this point
in the project – as indicated by the CPI – will
continue through project to the end.
2
EAC = BAC / CPI
56
EVM Special Attention
Forecast Calculation: EAC
= 11,333
Version 0.1 57
EVM Special Attention
Forecast Calculation: EAC
EAC3:
─ Accepts negative cost performance up to this
point in the project but insists that project hit a
firm completion date.
3 (BAC – EV)
EAC = AC +
CPI x SPI
58
EVM Special Attention
Forecast Calculation: EAC
EAC3 = AC +
( [BAC – EV] ÷ [CPI x SPI] )
3
EAC = 5,000 +
( [8,500 – 3,750] ÷ [0.75 x 1.5] )
EAC3 = 5,000 + (4,750 ÷ 1.125)
= 9,222
Version 0.1 59
EVM Special Attention
Forecast Calculation: EAC
EAC4:
─ Requires a complete redo of ETC.
─ Builds on actuals costs and team’s experience up
to this point.
─ Therefore, accurate and most common ─ but
expensive and time-consuming!
4
EAC = AC + Bottom-Up ETC
60
EVM Special Attention
Performance Indexes ─ Future
1
TCPI = (BAC – EV) / (BAC – AC)
61
EVM Special Attention
Performance Indexes ─ Future
2
TCPI = (BAC – EV) / (EAC – AC)
– Result depends on which EAC is used.
62
EVM Special Attention
Performance Indexes ─ Future
63