Tandang Sora Station
Outline
• Demarcation Scope
• Table of Organization
• Project Milestone
• Project Layout & Zoning
• Overall Schedule
• Sequence & Methodology

2
Demarcation Scope
SCOPE OF WORK LIST for SPCI (工事範囲表)
METRO MANILA SUBWAY PROJECT TSS 17-Jul-19

項目 Civil Arch M/E by others REMARKS

COMMON WORKS

1. ECC, LLDA and DENR Permit, Application & Fee Payment ● DOTr scope, but JV support

2. Production Equipment Installation Permit, Application & Free Payment ●

3. Production Equipment Permit to Operate Application & Free Payment ●

4.   Building Permit (Building) ●

5.   Fee Payment to Government for above ●

6. Elevator and Escalator Permit Application ●

7.   Fee Payment to Government for above ●

8. Building Occupancy Permit Application (Building) ●

9.   Fee Payment to Government for above ●

10. Elevator Operation Permit Application ●

11. Fee Payment to Government for above ●

12. Utility Connection Application (Permanent Power, Water, Sewer) ●

13. Fee & Deposit Payment to Government for above ●

14. Contracting Work for the above ●

15. Utility Connection Application (Temporary Power, Water, Sewer) ● By Civil team. (Tapping charge to others)

3
Demarcation Scope
SCOPE OF WORK LIST for SPCI (工事範囲表)
METRO MANILA SUBWAY PROJECT TSS 17-Jul-19

項目 Civil Arch M/E by others REMARKS

COMMON WORKS

16. Fee & Deposit Payment to Government for above ● By Civil team.

17. Contracting Work for the above ● By Civil team.

18. Models BIM - Archi; waiting for the spec from GC.

19. As-Built Drawings ● Coordination by Civil

20. As-Built Photo ● Coordination by Civil

21. Temporary Site Office, Rest Area, Toilets ●

22. Temporary Car Park Area ● Coordinated by Civil team


Organized by Civil and setting by each team.
23. Storage Barricade ● ● ; Material shall be prepared by JV?
Further discussion is required.
Panel board installation by Civil team.
24. Temporary Electrical & Water Supply ●
Tapping by Subcon.
25. Power Bill after Permanent Power-on by DOTr

26. Electricity for Testing & Commissioning by DOTr


Shall be paid based on the consumption.
27. Consumption Fee of Electricity & Water ●
(by setting meter)
28. Delivery and installation of Product Equipment ● By each team.
By each team.
29. Disposal of Industrial Waste Material ●
But Disposal station shall be prepared by Civil team.
30. Security Guard at Gate and Working Area ● Civil team shall arrange at the begening stage.
4
Demarcation Scope
SCOPE OF WORK LIST for SPCI (工事範囲表)
METRO MANILA SUBWAY PROJECT TSS 17-Jul-19

項目 Civil Arch M/E by others REMARKS

COMMON WORKS
Mainly by Civil team, but specific temporary
31. Temporary Scaffoldings & Safety Management ● facility only for each team shall be installed/removed
by each team.
Existing obstacle removal is DOTr scope,
32. Removal of Existing Obstruction on Site ●
but if tehre some remainnig, Civil team shall remove.
Topo survey will be done by Civil team,
33. Lot Survey ●
at the begenning.
34. Soil Investigation Report ●

35. Site Development Works ●

36. Analysis of Soil Contamination & Removal of Pollution Soil ●

37. Any Work Outside the Property Line ●


by DOTr
38. Importation Taxes & Duties of Imported Equipment and Materials ● ●
; JV will prepare required document.
39. Ground Breaking Ceremony ●

40. Foundation Stone Ceremony ●

41. Grand Opening Ceremony ●

42. Manufacturing Opening Ceremony ●

43. Owner and Consultant Temporary Facilities ● Civil team shall arrange at the begening stage.

44. Power and water supply during owner's equipment installation ● Civil team shall arrange at the begening stage.

5
Demarcation Scope
SCOPE OF WORK LIST for SPCI (工事範囲表)
METRO MANILA SUBWAY PROJECT TSS 17-Jul-19

項目 Civil Arch M/E by others REMARKS

CONVEYING EQUIPMENT

1. Electric supply from Panel Board ● ● By each team

2. Water supply from main temporary supply ● ● By each team

3. Work Place Drain water to main supplied water basin ● ● By each team

4. Rubbish removal ● ● By each team


By each team for each area.
5. Daily cleaning (Rubbish to collect to one location) ● ●
; Clear demacation is required.
6. Handover cleaning ● ● By each team.

7. Marking for grid line and 1m level For what purpose?

8. Marking for individual work ● ● By each team.


First installation by Civil team,
9. Lighting for general area ●
Rearrangement by each team, if necessary.
First installation by Civil team,
10. Lighting for working area ● ●
Rearrangement by each team, if necessary.
Installation of incert shall be done by Civil team,
11. Hoisting crane ● but the equipment by each team.
; Location shall be fixed by each team.

6
Demarcation Scope
SCOPE OF WORK LIST for SPCI (工事範囲表)
METRO MANILA SUBWAY PROJECT TSS 17-Jul-19

項目 Civil Arch M/E by others REMARKS

CONVEYING EQUIPMENT

Civil team prepare.


12. Stage for temporary opening ●
Location shall be consider further, for each floor.
13. Scaffolding below 4.0m ● ● By each team.

14. Scaffolding above 4.0m ● ● By each team.


First installation by Civil team,
15. Temporary toilet ● Rearrangement by each team, if necessary.
Type of toilet shall be considered further.
16. Protection for finished area ● ● By each team.

17. Safety barriers for working place ● ● By each team.


As a temporary.
Firstly they are installed by Civil team, but remove/
18. Ventilation system for main area ● re-install shall be done by each team, if necesarry.
Fire alarm shall be set by Civil team.
(; Push-Button Alarm system)
Civil team will coordinate the storage area,
19. Storage area supply ●
considering each work.
Civil team will coordinate the storage area,
20. Storage facilities ● ●
considering each work.
21. Gas Detection System ● Constantly monitored by Civil safety team

7
Demarcation Scope
SCOPE OF WORK LIST for SPCI (工事範囲表)
METRO MANILA SUBWAY PROJECT TSS 17-Jul-19

項目 Civil Arch M/E by others REMARKS

ARCHITECTURAL WORKS

1. Construction of entrance building, ventilation tower and ancillaries ●

2. All architectural finishes, decoration in station boxes and passageway boxes.

a. B1F

Floor Finish for all the above ●

Wall Finish for all the above ●

Ceiling Finish for all the above ●

b. B2F

Floor Finish for all the above ●

Wall Finish for all the above ●

Ceiling Finish for all the above ●

c. B3F

Floor Finish for all the above ●

Wall Finish for all the above ●

Ceiling Finish for all the above ● 8


Demarcation Scope
SCOPE OF WORK LIST for SPCI (工事範囲表)
METRO MANILA SUBWAY PROJECT TSS 17-Jul-19

項目 Civil Arch M/E by others REMARKS

ARCHITECTURAL WORKS

d. GF

Floor Finish for all the above ●

Wall Finish for all the above ●

Ceiling Finish for all the above ●

3. Miscellaneous metal work

a. Maintenance Ladder ●

b. Guard Post ●

4. Curved Steel Ceiling Panel (Platform) ●

5. Entrance roofing steel frame with anchorage bolt ●

6. Built in Counter and Cabinets ●

7. Signages

a. General Signages ●

b. Directory Signages ●

c. Wayfinding Signages ●

d. Emergency Exit Signages ●


9
e. Exterior Signages ●
Demarcation Scope
SCOPE OF WORK LIST for SPCI (工事範囲表)
METRO MANILA SUBWAY PROJECT TSS 17-Jul-19

項目 Civil Arch M/E by others REMARKS

ARCHITECTURAL WORKS

8. Toilet Fixtures ● toilet sanitary and accesory is mechanical scope.

9. Lighting Fixtures

10. Waterproofing ●

11. Fire Rated Proofing ●

12. Metal insert for staircase ●

13. Temporary opening closure ●

CONVEYING EQUIPMENT

1. Elevator, Japanese Supplier preferably Mitsubishi ●

2. Escalator, Japanese Supplier preferably Mitsubishi ●

3. Application Fee for the above ●

10
Table of Organization

11
Project Milestone

12
Project Layout & Zoning

13
Sequence and
Methodology

14
Road Diversion

15
( 03 Jan. ‘ 22 ~ 29 April ’22 )~( 03 April ‘ 22 ~ 30 Aug. ‘23 )
Sequence of Activities

( TYPICAL
SECTION )
SECTION A-A ~ J-J

16
Sequence of Activities

17
Scaffolding Layout / Sequence

18
Temporary Facilities

19
Site Office

20
MMSP Office

21
Isometric View

Lorem ipsum dolor sit amet, consectetur


adipiscing elit.

22
ThankYou
Metro Manila Subway Project
Tandang Sora Station