Subway Project
Tandang Sora Station
Outline
• Demarcation Scope
• Table of Organization
• Project Milestone
• Project Layout & Zoning
• Overall Schedule
• Sequence & Methodology
2
Demarcation Scope
SCOPE OF WORK LIST for SPCI (工事範囲表)
METRO MANILA SUBWAY PROJECT TSS 17-Jul-19
COMMON WORKS
1. ECC, LLDA and DENR Permit, Application & Fee Payment ● DOTr scope, but JV support
15. Utility Connection Application (Temporary Power, Water, Sewer) ● By Civil team. (Tapping charge to others)
3
Demarcation Scope
SCOPE OF WORK LIST for SPCI (工事範囲表)
METRO MANILA SUBWAY PROJECT TSS 17-Jul-19
COMMON WORKS
16. Fee & Deposit Payment to Government for above ● By Civil team.
18. Models BIM - Archi; waiting for the spec from GC.
COMMON WORKS
Mainly by Civil team, but specific temporary
31. Temporary Scaffoldings & Safety Management ● facility only for each team shall be installed/removed
by each team.
Existing obstacle removal is DOTr scope,
32. Removal of Existing Obstruction on Site ●
but if tehre some remainnig, Civil team shall remove.
Topo survey will be done by Civil team,
33. Lot Survey ●
at the begenning.
34. Soil Investigation Report ●
43. Owner and Consultant Temporary Facilities ● Civil team shall arrange at the begening stage.
44. Power and water supply during owner's equipment installation ● Civil team shall arrange at the begening stage.
5
Demarcation Scope
SCOPE OF WORK LIST for SPCI (工事範囲表)
METRO MANILA SUBWAY PROJECT TSS 17-Jul-19
CONVEYING EQUIPMENT
3. Work Place Drain water to main supplied water basin ● ● By each team
6
Demarcation Scope
SCOPE OF WORK LIST for SPCI (工事範囲表)
METRO MANILA SUBWAY PROJECT TSS 17-Jul-19
CONVEYING EQUIPMENT
7
Demarcation Scope
SCOPE OF WORK LIST for SPCI (工事範囲表)
METRO MANILA SUBWAY PROJECT TSS 17-Jul-19
ARCHITECTURAL WORKS
a. B1F
b. B2F
c. B3F
ARCHITECTURAL WORKS
d. GF
a. Maintenance Ladder ●
b. Guard Post ●
7. Signages
a. General Signages ●
b. Directory Signages ●
c. Wayfinding Signages ●
ARCHITECTURAL WORKS
9. Lighting Fixtures
10. Waterproofing ●
CONVEYING EQUIPMENT
10
Table of Organization
11
Project Milestone
12
Project Layout & Zoning
13
Sequence and
Methodology
14
Road Diversion
15
( 03 Jan. ‘ 22 ~ 29 April ’22 )~( 03 April ‘ 22 ~ 30 Aug. ‘23 )
Sequence of Activities
( TYPICAL
SECTION )
SECTION A-A ~ J-J
16
Sequence of Activities
17
Scaffolding Layout / Sequence
18
Temporary Facilities
19
Site Office
20
MMSP Office
21
Isometric View
22
ThankYou
Metro Manila Subway Project
Tandang Sora Station