Sei sulla pagina 1di 84

KHD Humboldt Wedag GmbH

Joerg Binner
Kerman Momtazan
KMCC Off-Shore Training Program
Cement Grinding Process
Germany, Wednesday, August 29th, 2007
KHD Humboldt Wedag GmbH

CONTENT

 Power demand
 Grindability of the feed material
 Process description
 Design data of main equipment
 Ball mill
 Design
 Slide shoe bearings
 Lubrication
 Lining and diaphragm wall
 Water dosing system

Wednesday, March 25, 2020 3


KHD Humboldt Wedag GmbH

CONTENT

 Dynamic separator
 Drive and coarse discharge
 Function principle
 Classifying
process
Operation diagram
 Sealing between cage wheel and housing
 The cage wheel
 Separator features
 Lubrication of the drive and bearings
 Gear box
 Separator fan

Wednesday, March 25, 2020 4


KHD Humboldt Wedag GmbH

CONTENT

 General layout
 Measuring points
 Control loops
 Starting procedure
 Shutting down of the grinding plant
 Blaine measurement according to EN 196 – 6
 Cement classification according to EN 197 – 1
 Early and final strengths of cement types

Wednesday, March 25, 2020 5


KHD Humboldt Wedag GmbH

POWER DEMAND

 How much is the total electrical energy consumed by a complete


cement plant?

 How many percentage is used for raw material and clinker grinding?

 What is the percentage consumption for the cement grinding?

Wednesday, March 25, 2020 6


KHD Humboldt Wedag GmbH

POWER DEMAND

 The total electrical power consumption of a complete cement plant


varies about 80 -100 kWh/t of cement.

 About 80 % of the total power consumption of a cement plant is


consumed by the grinding process of raw- and cement mills.

 The main motor of a ball mill consumes about 30-60 kWh per ton of
cement, depending on cement type.

 In average the motor of a ball mill consumes more than 50% of the
total electrical power of a cement plant.

Wednesday, March 25, 2020 7


KHD Humboldt Wedag GmbH

GRINDABILITY OF THE FEED MATERIAL


Specific energy consumption / kWh/t .

closed circuit

open circuit

Cement fineness / m²/kg (Blaine)

Wednesday, March 25, 2020 8


KHD Humboldt Wedag GmbH

PROCESS FLOW SHEET


Feed material: A)
d: 190,000 m³/h (90 °C) d: 90,000 m³/h (100°C) d: 605 t/h
1. Clinker 95.0%
2. Gypsum 5.0%
Feed size: 0 - 30 mm
5416AS2
350,000 m³/h ( 90°C)
5423FN1 5417FN1

165,000 m³/h ( 40°C)


2 1

5413DA11
5423CN1-4 5417BF1 5415BE1
5111WF2 5111WF1 5413SR1

5115BC1 5416AS3 5614AS4

A) 210 t/h

5416FM1 5417FN2 3,000 cm²/g (BL)


max. 90°C
5417BF2

Gehe zu
0

5411BM1
Water injection
d: 250 t/h d: 395 t/h chamber 1 and 2 4516AS1
d: Design
A) 210 t/h A) 315 t/h Altitude a.s.l.: 1710 m

Wednesday, March 25, 2020 9


KHD Humboldt Wedag GmbH

PROCESS DESCRIPTION

The clinker grinding plant mainly consists of a ball mill and a dynamic separator.
The initial product is a mixture of clinker and gypsum.
All components are fed under control from the prebins via proportioning weigh feeder
and a belt conveyor into the ball mill.
The ball mill is divided into two grinding chambers.
The first grinding chamber is the coarse grinding chamber.
Lifting liners are installed in the first chamber to lift the balls for achieving a good
crushing- and comminuting result.
The two chambers are separated by an intermediate wall.
To ensure the grinding material transport from the first to the second chamber, the
transition wall is provided with slots.
The fine grinding takes place in the second chamber.
This chamber is equipped with a classifying lining to sort the different ball sizes.
The larger balls at the chamber inlet and the smaller balls at the outlet.
The material is discharged by a screw into the outlet housing.

Wednesday, March 25, 2020 10


KHD Humboldt Wedag GmbH

DESIGN DATA OF MAIN EQUIPMENT

Ball mill Ø 5.0 x 16.0 m


motor: 1 x 6,700 kW

Wednesday, March 25, 2020 11


KHD Humboldt Wedag GmbH

BALL MILL – WITH SLIDE SHOE BEARINGS

Wednesday, March 25, 2020 12


KHD Humboldt Wedag GmbH

BALL MILL – FEATURES

 The two-shoe support for ball mills up to 4.6 meter diameter.

 The four-shoe support for larger mills.

 During the 1980’s ball mills became bigger and bigger, plants capacity
became larger and there was a need to change the mill design from trunnion
support to slide shoe support to meet this requirement.

 Change from trunnion to slide shoe support in 1988

 Today, our ball mills are generally equipped with slide shoes for a drive
power of 1,000 to more than 8,000 kilowatt.

Wednesday, March 25, 2020 13


KHD Humboldt Wedag GmbH

BALL MILL – FEATURES

 The main features of slide shoe supported mills are


 lower stresses of the mill shell.
 Less weight, and the overall length is reduced.
 No cast parts are required, which makes manufacturing easier.

 KHD design is the easy alignment during the initial erection and a simple
foundation.

 We are building the slide shoe construction in steel, and do not leave it up to
the customer to make a relatively complicated foundation.

Wednesday, March 25, 2020 14


KHD Humboldt Wedag GmbH

BALL MILL - DESIGN

 mill with slide shoe bearing


and integral drive

 mill with slide shoe


bearing and central drive

 mill with trunnion bearing


and central drive

Wednesday, March 25, 2020 15


KHD Humboldt Wedag GmbH

BALL MILL - DRAWING

16.5 m

5.0 m

Wednesday, March 25, 2020 16


KHD Humboldt Wedag GmbH

BALL MILL - DESIGN


 Speed
nmill = 73 – 76 % of the critical speed

ncrit = 42.3 / di

 Filling degree 28 – 32 %

 Type of main drive

 Girth gear Power factor = 1 (up to 4,500 kW)

 Central drive Power factor = 0.97 (5,000 to 10,000 kW)

 Integral drive Power factor = 0.95 (up to 6,500 kW)

Wednesday, March 25, 2020 17


KHD Humboldt Wedag GmbH

BALL MILL - DESIGN

 from 3.0 to 6.0 meter shell diameter,


with slide shoe support

 mill length from 8.0 to 19.0 m

 design up to 10 000 kW, in operation:


up to 7700 kW

Wednesday, March 25, 2020 18


KHD Humboldt Wedag GmbH

BALL MILL – TRANSPORT

Wednesday, March 25, 2020 19


KHD Humboldt Wedag GmbH

BALL MILL – ERECTION

Slide shoes
pre-assembled

Slide ring
housing

axial bearing

Wednesday, March 25, 2020 20


KHD Humboldt Wedag GmbH

BALL MILL – SLIDE SHOE SUPPORT

 1989: first application


 2006: more than 50 mills equipped with slide
shoes for 1000 to 8000 kW in operation

main features of slide shoe bearings:


- less weight of mill shell, reduced length, no cast parts

features of KHD design:


- easy alignement, simple foundation

Wednesday, March 25, 2020 21


KHD Humboldt Wedag GmbH

BALL MILL – SLIDE SHOE BEARINGS


view before erection of slide
ring housing
4 - Shoe Support
swing-support for 2 shoes
each

Wednesday, March 25, 2020 22


KHD Humboldt Wedag GmbH

BALL MILL – SLIDE SHOE BEARINGS

 oil cooling system for


slide ring and bearing
 high pressure start up system
 oil lubrication

Wednesday, March 25, 2020 23


KHD Humboldt Wedag GmbH

BALL MILL – HOUSING OF SLIDE SHOE BEARINGS

Wednesday, March 25, 2020 24


KHD Humboldt Wedag GmbH

BALL MILL – OIL LUBRICATION UNIT FOR MILL BEARINGS

Wednesday, March 25, 2020 25


KHD Humboldt Wedag GmbH

BALL MILL - OIL LUBRICATION UNIT FOR MILL BEARINGS

Wednesday, March 25, 2020 26


KHD Humboldt Wedag GmbH

BALL MILL – MILL INTERNALS


6 mm 8 mm

Wednesday, March 25, 2020 27


KHD Humboldt Wedag GmbH

BALL MILL – INSIDE

Inlet chute

Wednesday, March 25, 2020 28


KHD Humboldt Wedag GmbH

BALL MILL - INSIDE

Diaphragm
Wednesday, March 25, 2020 29
KHD Humboldt Wedag GmbH

BALL MILL - LINING

Lifting liners Classifying liners

Wednesday, March 25, 2020 30


KHD Humboldt Wedag GmbH

BALL MILL - LINING

FH
FH Mill outlet

FG FG
Wednesday, March 25, 2020 31
KHD Humboldt Wedag GmbH

BALL MILL – WATER DOSING SYSTEM

Wednesday, March 25, 2020 32


KHD Humboldt Wedag GmbH

PROCESS FLOW SHEET


Feed material: A)
d: 190,000 m³/h (90 °C) d: 90,000 m³/h (100°C) d: 605 t/h
1. Clinker 95.0%
2. Gypsum 5.0%
Feed size: 0 - 30 mm
5416AS2
350,000 m³/h ( 90°C)
5423FN1 5417FN1

165,000 m³/h ( 40°C)


2 1

5413DA11
5423CN1-4 5417BF1 5415BE1
5111WF2 5111WF1 5413SR1

5115BC1 5416AS3 5614AS4

A) 210 t/h

5416FM1 5417FN2
3,000 cm²/g (BL)
max. 90°C
5417BF2

5411BM1
Water injection
d: 250 t/h d: 395 t/h chamber 1 and 2 4516AS1
d: Design
A) 210 t/h A) 315 t/h Altitude a.s.l.: 1710 m

Wednesday, March 25, 2020 33


KHD Humboldt Wedag GmbH

PROCESS DESCRIPTION

The air slide conveys the mill discharge and the material of the mill dedusting
filter to the bucket elevator.
From there, it‘s conveyed via airslide to the SKS-separator for classifying.
The fine classified by the rotating cage wheel is collected into cyclones.
The separated coarse fraction (rejects) is returned to the mill for further grinding.
The rejects volume is measured by a flow meter.
The SKS-separator is dedusted into a separate bag filter.
The discharge of the cyclones is transported to the Airlift via airslides.
The accruing filter dust from the separator is also fed into the airslides to the
Airlift.
The cement is transported to the silos via Airlift.
Before the Airlift, a sampling device is installed for taking samples from the
product for analysing fineness and quality.

Wednesday, March 25, 2020 34


KHD Humboldt Wedag GmbH

DESIGN DATA OF MAIN EQUIPMENT

Ball mill Ø 5.0 x 16.0 m


motor: 1 x 6,700 kW

Separator SEPMASTER® SKS – Z 3500


motor: 265 kW
Cyclone: 4 x Ø 3.2 m

System fan 384,000m³/h (inlet)


40 mbar
motor: 630 kW

Wednesday, March 25, 2020 35


KHD Humboldt Wedag GmbH

SEPMASTER® - SKS
outlet head

fan cyclone

coarse
drive

Wednesday, March 25, 2020 36


KHD Humboldt Wedag GmbH

SEPMASTER® - SKS

 First application: 1988


 in 2006: 250 Sepmaster sold
 rotor diameter: 400 to 4600 mm
 air volume: 2.000 to 760.000 m3/h
 different models: SKS-M, SKS-Z, SKS-L

Wednesday, March 25, 2020 37


KHD Humboldt Wedag GmbH

SEPMASTER® - DRIVE AND COARSE DISCHARGE

Coarsedischarge
1 Coarse discharge
1 1
4 Drive
2 Drive
Gearbox
3 Gear box

Cagewheel
4 Cage wheelshaft
shaft
2
3

Wednesday, March 25, 2020 38


KHD Humboldt Wedag GmbH

SEPMASTER® - PNEUMATIC COARSE DISCHARGE

Wednesday, March 25, 2020 39


KHD Humboldt Wedag GmbH

SEPMASTER® - FUNCTION PRINCIPLE

1
2
1 Feed
Feed

2 Fine++air
Fine air

3 Reject
Reject
4
4 Air
Air

Wednesday, March 25, 2020 40


KHD Humboldt Wedag GmbH

SEPMASTER® – CLASSIFYING PROCESS

classifying
zone

Wednesday, March 25, 2020 41


KHD Humboldt Wedag GmbH

SEPMASTER® – OPERATION DIAGRAM

SKS - Z 3500
180
Air Flow
160
365,000 m³/h
140
cut point "d-95" / µm

100%
120
85%
100
70%
80

60

40

20
25 50 75 100
cage speed / %

Wednesday, March 25, 2020 42


KHD Humboldt Wedag GmbH

SEPMASTER® - SEALING

air

Airgap
Air gap
rinsedby
rinsed by
self
self
gap
propelled
propelled
airflow
airflow

Wednesday, March 25, 2020 43


KHD Humboldt Wedag GmbH

SEPMASTER® - CAGE WHEEL

Wednesday, March 25, 2020 44


KHD Humboldt Wedag GmbH

SEPMASTER® - CAGE WHEEL

Wednesday, March 25, 2020 45


KHD Humboldt Wedag GmbH

SEPMASTER® - CAGE WHEEL

Wednesday, March 25, 2020 46


KHD Humboldt Wedag GmbH

SEPMASTER® - FEATURES

 Rotor shaft supported at both ends (stable run)


 Rotor bearings outside (cool, no dust ingress)
 Shaft ends are flanged on (easy maintenance)
 Drive below (easy access for maintenance)
 All wear parts exchangeable (quick action)
 Air rinsed rotor gap (good against wear, no OSP`s)
 excellent performance (high efficiency for plant)

Wednesday, March 25, 2020 47


KHD Humboldt Wedag GmbH

SEPMASTER® – LUBRICATION

Temperature
Warning:90 °C
Stop: 100 °C

S = Lubrication point
T = Temperature sensor

Wednesday, March 25, 2020 48


KHD Humboldt Wedag GmbH

SEPMASTER® – GEAR BOX

Flow controller Filter


Pump
4 – 13 l/min p = 2 bar ALARM
cleaning required
> 2.5 bar STOP
Oil cooler Temperature
> 75 °C ALARM
> 85 °C STOP

Wednesday, March 25, 2020 49


KHD Humboldt Wedag GmbH

SEPARATOR FAN
Fan Impeller Guide vane controller

actuator

Wednesday, March 25, 2020 50


KHD Humboldt Wedag GmbH

FAN – CHARACTERISTIC CURVE

Wednesday, March 25, 2020 51


KHD Humboldt Wedag GmbH

GENERAL LAYOUT

Wednesday, March 25, 2020 52


KHD Humboldt Wedag GmbH

GENERAL LAYOUT

Wednesday, March 25, 2020 53


KHD Humboldt Wedag GmbH

GENERAL LAYOUT

Wednesday, March 25, 2020 54


KHD Humboldt Wedag GmbH

GENERAL LAYOUT

Wednesday, March 25, 2020 55


KHD Humboldt Wedag GmbH

Measuring points
GIC
PdI
GIC PIC GIC

PdS M
LSA GIC
2 1 LSA
IIA
WISA M
WISA
FIC
SIC TI
FIC
IIA
QIC
FI
PI PdS GIC
To silo

1st LETTER PROCESSING TIC


A ALARM M IIA
F FLOW Gehe zu M IIA
G GAUGING
I CURRENT
L LEVEL
M MOTOR
P PRESSURE
Q QUALITY GIC GIC
S SPEED SWITCHING
T TEMPERATURE FIC FIC
W WEIGHT

Wednesday, March 25, 2020 56


KHD Humboldt Wedag GmbH

BALL MILL – SCREEN SHOT

BALL MILL

Wednesday, March 25, 2020 57


KHD Humboldt Wedag GmbH

CONTROL LOOPS

Loop 1: Fresh feed


The feed rate to the ball mill inlet should be constant.
 Fresh feed + separator rejects = constant

Loop 2: Cement fineness


The cement fineness is controlled by the speed of the separator cage wheel.
The fineness is measured as specific surface acc. to Blaine

Loop 3: Temperature of mill discharge


The temperature is controlled by the quantity of water which is injected into the ball
mill.
 The water injection is starting first into chamber 2.
 The temperature should be maintained at 100 - 115°C.

Wednesday, March 25, 2020 58


KHD Humboldt Wedag GmbH

CONTROL LOOPS

PIC GIC
2 1 C5

FIC FIC GIC


M

C4 TI
SIC
C1 FI C2 QIC

PIC C6 GIC

1st LETTER PROCESSING To silo


A ALARM
F FLOW
G GAUGING Gehe zu M
I CURRENT
L LEVEL TIC
M MOTOR
P PRESSURE
Q QUALITY
S SPEED SWITCHING GIC GIC
T TEMPERATURE
W WEIGHT FIC FIC

C3

Wednesday, March 25, 2020 59


KHD Humboldt Wedag GmbH

CONTROL LOOPS

Loop 4: Cement temperature


Cooling air into the separator is used for cooling of the cement.
The amount of cooling air is controlled by the damper position at the fresh air inlet
of the separator
Loop 5: Pressure at the separator fan outlet
Controlled by the damper position of the dedusting duct.
 Dedusting of the separator

Loop 6: Draught after the mill


Controlled by the damper position of the mill fan.
 Dedusting of the mill
 Transport of fines inside the mill
 Cooling of the cement

Wednesday, March 25, 2020 60


KHD Humboldt Wedag GmbH

CONTROL LOOPS

PIC GIC

2 1 C5

FIC FIC GIC


M

C4 TI
SIC
C1 FI C2 QIC

PIC C6 GIC

1st LETTER PROCESSING To silo


A ALARM
F FLOW
G GAUGING Gehe zu M
I CURRENT
L LEVEL TIC
M MOTOR
P PRESSURE
Q QUALITY
S SPEED SWITCHING GIC GIC
T TEMPERATURE
W WEIGHT FIC FIC

C3

Wednesday, March 25, 2020 61


KHD Humboldt Wedag GmbH

STARTING PROCEDURE

 Starting takes place according to the specified interlocking system.

 It is permitted only in interlocked condition.

 The grinding plant is sub-divided into groups and is also started by groups.

Wednesday, March 25, 2020 62


KHD Humboldt Wedag GmbH

STARTING PROCEDURE – CEMENT TRANSPORT AND DEDUSTING

 Group 5417

Selection of silo 1
Airslide reversing system 5416 DG 1 to silo 1 5811 SO1
Filter control 5817BF1
Filter fan 5817FN1
Airslide blower 5416FN9
Selection of silo 2
Airslide reversing system 5416 DG 1 and 2 to silo 2 5821 SO1
Filter control 5827BF1
Filter fan 5827FN1
Airslide blower 5416FN10 to 9
Selection of silo 3
Airslide reversing system 5416 DG 1 and 2to silo 3 5831 SO1
Filter control 5837BF1
Filter fan 5837FN1
Airslide blower 5416FN11 to 9
Wednesday, March 25, 2020 63
KHD Humboldt Wedag GmbH

PROCESS FLOW SHEET – SILO SYSTEM

Wednesday, March 25, 2020 64


KHD Humboldt Wedag GmbH

STARTING PROCEDURE – CEMENT TRANSPORT AND DEDUSTING

Air lift bag filter and transport


Rotary lock 5417RF5
Rotary lock 5416RF1
Screw conveyor 5417SC5
Filter control 5417BF5
Filter fan 5417FN

Air lift
Airlift blower 5416BL1

Bag filter and transport


Filter control 5417BF4
Filter fan 5417FN4
Airslide blower 5416FN8 to 6 Rotary
lock 5417RF4

Wednesday, March 25, 2020 65


KHD Humboldt Wedag GmbH

PROCESS FLOW SHEET – MILL SYSTEM

to silo

Wednesday, March 25, 2020 66


KHD Humboldt Wedag GmbH

STARTING PROCEDURE – CEMENT TRANSPORT AND DEDUSTING

SKS bag filter and transport


Screw conveyor 5415SC2
Screw conveyor 5415SC1
Rotary lock 5417RF1
Rotary lock 5417RF2
Screw conveyor 5417SC1
Screw conveyor 5417SC2
Filter control 5417BF1
Filter fan 5417FN1
Filter fan damper 5417LD1
Airslide blower 5416FN4

Wednesday, March 25, 2020 67


KHD Humboldt Wedag GmbH

PROCESS FLOW SHEET – MILL SYSTEM

Wednesday, March 25, 2020 68


KHD Humboldt Wedag GmbH

STARTING PROCEDURE – SKS-SEPARATOR

 Group 5413
SKS-Separator
Separator gear lubrication 5413LQ1
Separator drive 5413SR1
Separator fan 5413FN1
Separator fan flap 5413LD1

Wednesday, March 25, 2020 69


KHD Humboldt Wedag GmbH

PROCESS FLOW SHEET – MILL SYSTEM

Wednesday, March 25, 2020 70


KHD Humboldt Wedag GmbH

STARTING PROCEDURE – MILL MATERIAL CIRCUIT

 Group 5416
Mill material circuit
Filter control 5417BF3
Filter fan 5417FN3
Filter fan flap 5417LD3
Scavenging air fan 5419FN2
Scavenging air fan 5419FN1
Airslide blower 5416FN3
Airslide blower 5416FN2
Bucket elevator 5415BE1
Airslide blower 5416FN1
Rotary lock 5417RF3
Screw conveyor 5417SC3

Wednesday, March 25, 2020 71


KHD Humboldt Wedag GmbH

PROCESS FLOW SHEET – MILL SYSTEM

Wednesday, March 25, 2020 72


KHD Humboldt Wedag GmbH

STARTING PROCEDURE – AUXILIARY BALL MILL DRIVES

 Group 5411
Auxiliary ball mill drives
Circulation pump 5411LQ1M02
Circulation pump 5411LQ2M02
High-pressure starting lubrication 5411LQ1M01+3
High-pressure starting lubrication 5411LQ2M01+3
Mill lubrication 5411LQ1M04
Mill lubrication 5411LQ2M04
Mill gear lubrication 5411LQ3M01

To avoid delays upon starting the mill, the lubrication systems of the ball mill and of the
separator must be started during or prior to the other connection processes.
In particular with cold oil, starting- and control delays for pumps and monitoring instruments can
occur.

Wednesday, March 25, 2020 73


KHD Humboldt Wedag GmbH

PROCESS FLOW SHEET – MILL SYSTEM

Wednesday, March 25, 2020 74


KHD Humboldt Wedag GmbH

STARTING PROCEDURE – BALL MILL

 Group 5315
Material transport, clinker, additives transport and dedusting
Filter control 5117BF3
Filter fan 5117FN3
Belt conveyor 5115BC1
Rotary lock 5117RF3
Proportioning belt weightmeter 5111WF1
Proportioning belt weightmeter 5111WF2

 Group 5411
Ball mill
Ball mill drive 5411BM1
For heating up, all heating systems shall already have been connected a long time before.
if possible, it should be permanently running.

Wednesday, March 25, 2020 75


KHD Humboldt Wedag GmbH

PROCESS FLOW SHEET – FEEDING AND DOSING

Wednesday, March 25, 2020 76


KHD Humboldt Wedag GmbH

SHUTTING DOWN OF THE GRINDING PLANT

 The grinding plant is shut down approximately in reverse sequence


than when being started.

 If possible, the circuits should always be run empty to permit the


performance of repair-, setting- and maintenance works without any
problem.

 The automatic disconnection of the drives takes place at stop intervals


with respective delay times to run empty all sets and transport paths.

 In particular dedusting systems must be run empty for a sufficient time.

Wednesday, March 25, 2020 77


KHD Humboldt Wedag GmbH

SHUTTING DOWN OF THE GRINDING PLANT

 Group 5111 The fresh feed system is stopped first.

 Group 5315 The material transport runs empty for a sufficient time.

 Group 5411 The ball mill can be stopped when the rejects volume is
sufficiently reduced, the ball.

 Group 5411 The ball mill lubrication is disconnected after the mill has
come to a standstill, abt. 2 minutes after the mill stop. The
high-pressure lubrication automatically starts upon
stopping of the mill. During interval turning of the mill, the
high-pressure lubrication remains connected.

Wednesday, March 25, 2020 78


KHD Humboldt Wedag GmbH

SHUTTING DOWN OF THE GRINDING PLANT

 Group 5416/17/19 The ball mill material circuit can be disconnected if


no rejects are measured any more.

 Group 5413 Separator and separator fan are disconnected.

 Group 5416 The material transport should be run empty for a


sufficient time prior to shutting down.

 Group 5817/27/37 The silo dedusting system is only shut down, if nothing is
withdrawn from the respective silo.

Wednesday, March 25, 2020 79


KHD Humboldt Wedag GmbH

BLAINE MEASUREMENT ACC. TO EN 196 - 6


socket
piston
cell stop cock

manometer
compacted
cement bed

filter paper

bulb
perforated disc

Wednesday, March 25, 2020 80


KHD Humboldt Wedag GmbH

BLAINE MEASUREMENT ACC. TO EN 196 - 6

Wednesday, March 25, 2020 81


KHD Humboldt Wedag GmbH

CEMENT CLASSIFICATION ACC. TO EN 197-1

Wednesday, March 25, 2020 82


KHD Humboldt Wedag GmbH

EARLY AND FINAL COMPRESSIVE STRENGTHS OF


CEMENT TYPES

Wednesday, March 25, 2020 83


KHD Humboldt Wedag GmbH

KHD Humboldt Wedag GmbH


Joerg Binner
Kerman Momtazan
KMCC Off-Shore Training Program
Cement Grinding Process
Germany, Wednesday, August 29th, 2007

Wednesday, March 25, 2020 84

Potrebbero piacerti anche