Cross Check
• Cross Checking the Quantity Accuracy in a BOQ
• Using summary page of a BOQ to check the accuracy. Eg. Cost percentages of each
element
• in relation to the total cost can be compared with past similar nature projects and if there
is
• any huge deviation then the deviated particular element can be cross checked in detail.
• Comparing square feet rate for current project against a past similar project after
making
• necessary alterations to suit the current project in terms of time, location etc
• Using check list – this check list consist a list of major elements of building projects. this
• check list helps to avoid error due to omission or double counting of elements