Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
MANAGEMENT
1
2
What is a contract?
• As per section 2(h) of the Indian Contract Act, 1872, “Contract is an
agreement enforceable by law”
• It is a legally binding written agreement between two parties i.e. owner and the
contractor to initiate construction of a project.
• It is a set of promises mutually made by the owner and contractor under the
enforcement of prevailing laws, rules and regulations of the government.
3
4
• For award of the contract, offers are invited, evaluated, the best agency
selected and contracts drawn up to bind the parties together.
• The contract agreement also lays down procedure for settlement of claims,
solving disputes through arbitration or otherwise.
5
OBJECTIVES OF A CONTRACT:
The objective of a contract is
• equipment and services in the right quantity and quality at the right
time and right place after giving fair and equal chances to all tenderers
as per the work policies of the organization.
6
ESSENTIAL FEATURES OF A CONTRACT
• Both the owner and the contractor should know exactly what is expected from
each of them and what are the financial commitments.
• The quality of materials and workmanship required should be elaborated
clearly.
• The conditions of contract should be reasonable, specific and clear.
• Targets of desired quantity of finished work ensuring quality and its planning
and monitoring system should be specified in the contract so as to avoid cost
over-run,
• Provision should be made for contract progress review meeting to be held
between the contractor and clients and consultants, target completion in a
chronological pattern
7
TERMS USED IN CONTRACT
8
DOCUMENTS IN A CONTRACT
• Enquiry or invitation to offer or Notice Inviting Tenders (NIT)
Percentage
Rate
Contract 10
Item Rate Contract
• Here the work is divided into a number of items, rates of which are
estimated by either rate Analysis or by adopting some Standard
Schedule of Rates. The tender documents are prepared by including
the bill of quantities i.e. the estimated quantities for each item of work
giving full nomenclature
11
Lump-Sum Contract
12
Cost Plus Contract
• In these contracts, the contractor is given the job on turn-key basis. In
this case quantities and rates are not given to the contractor.
13
14
PREPERATION OF TENDER DOCUMENTS
• Notice Inviting Tender (NIT) • Payment Terms
• Clauses of Contract • Escalation of Contract
• Security Deposit • Execution of Extra Items
• Contract Duration • Variations in Quantities
• Defective Work • Payment of Taxes
• Defect Liability Period • Schedule of Tools (Plants
• Rescinding of the contract and Machineries)
15
16
LABOUR LAWS
• Indian Contract Act 1872
• Contract Labor Act 1970
• Contract labor Central Rules 1971
• Payment of Wages Act 1936
• Minimum Wages Act 1948
• Maternity Benefits Act 1961
• Workmen’s Compensation Act 1923
• Industrial Dispute Act 1947
• Central GOODS AND SERVICE TAX (GST)
17
SPECIAL CONDITIONS OF CONTRACT
18
19
Project Planning
by
Project Planning
• What is Project?
• A specific activity on which money is spent in the expectation of
returns.
• While selecting, the decision is taken after careful consideration of cost and
benefits
• To maximize the present value for all the benefits – all costs subject to
constraints
• The costs involved may be private costs (individual costs & overhead
charges) or public costs (social costs, cost to the nation, societal sacrifice,
marginal & opportunity costs)
Aspects considered while Evaluating a
Project
• All the inputs & outputs must reflect social and economic aspects
• Certain costs & benefits are unquantifiable, as they accrue over time
• A project includes all the activities which are necessary and aimed at:
3. Project Appraisal,
4. Negotiations
5. Project approval
6. Detailed project planning
7. Project implementation
8. Project monitoring and control,
Phase of Project
Project
Project Project Detailed Project Project Project
Project Appraisal Negotiations Project Approval Monitoring &
Identification preparation Planning Implementation Evaluation
Control
1. Project Identification
1. Project Identification
2. Project Preparation:
• Divided in two stages
i. Preliminary Project study
• Preliminary information is collected
• Rough estimation of resources and cost is done
• If results are unfavorable, project is dropped and vice versa.
ii. Feasibility Study
• Most exhaustive stage in the project planning
• To see if project is realistic & recommendations in previous study are technically sound
Project
Project Project Detailed Project Project Project
Project Appraisal Negotiations Project Approval Monitoring &
Identification preparation Planning Implementation Evaluation
Control
2. Project Preparation
3. Project Appraisal
3. Project Appraisal
4. Negotiations:
4. Negotiations
5. Approval of Project:
5. Approval of Project:
6. Detailed Project Planning (pre-project construction plan):
• Each and every stage of planning needs to worked out, while considering all
the relevant project provisions well in advance
• Physical facilities are to planned w.r.t time and cost to meet predetermined
objectives.
• Resource Mobilization and effective utilization are one of the key aspects
• Different authorities for different activities and tasks are developed, estimates
are more precisely prepared
Project
Project Project Detailed Project Project Project
Project Appraisal Negotiations Project Approval Monitoring &
Identification preparation Planning Implementation Evaluation
Control
7. Project Implementation
8. Project Monitoring & Control
Following are the aspects
• Collection of information regarding physical progress & cost incurred of
project
• Information regarding future progress & resource availability & their effect on
target completion
• Finding out shortfalls & determining the reasons for the same
• Initiating corrective actions if required
Project
Project Project Detailed Project Project Project
Project Appraisal Negotiations Project Approval Monitoring &
Identification preparation Planning Implementation Evaluation
Control
7. Project Implementation
8. Project Monitoring & Control
• Project Delay and Cost Overrun:
• It occurs due to
• Inadequate Planning
• Delay in finalization of any technical specification
• Delay in order placement
• Inadequate funds
• Delayed Resource Mobilization
• Deficiencies in Organization
Project
Project Project Detailed Project Project Project
Project Appraisal Negotiations Project Approval Monitoring &
Identification preparation Planning Implementation Evaluation
Control
• Project auditing and evaluation is done w.r.t to the level of fulfillment of vision
• Tool for management & control to efficiently use manpower, resources &
information to achieve the objectives at every level of organization
• Ensuring the objectives are achieved well within the budget, on schedule & at
desired performance level while adjusting to certain changes at same time
• Project Manager
• A person nominated for successful implementation of project from Detailed Project
Report stage till successful completion of project
Successful Completion of Project