Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
GRIT CHAMBER
1
grit chamber
2/17/2020
• Grit chamber is the second unit operation used in primary treatment of
wastewater and it is intended to remove suspended inorganic particles
such as sandy and gritty matter from the wastewater.
2/17/2020
• Based on the process of sedimentation in which the organic matter
present in sewage which is having specific gravity greater than that
of water (ie 1.0) is made to settle.
3
Principle of grit chamber
2/17/2020
• Settling of discrete particles (Type I sedimentation
or settling).
4
Functions of grit chambers
2/17/2020
Grit chambers are provided
5
Functions of grit chambers
2/17/2020
Separate removal of suspended inorganic solids in grit chamber and
suspended organic solids in primary sedimentation tank is necessary
due to different nature and mode of disposal of these solids.
Grit can be disposed off after washing, to remove higher size organic
matter settled along with grit particles
6
2/17/2020
Horizontal Velocity in Flow Though Grit Chamber
• The settling of grit particles in the chamber is assumed as particles settling as
individual entities and referred as Type – I settling. The grit chamber is
divided in four compartments as inlet zone, outlet zone, settling zone and
sludge zone
7
Horizontal Velocity in Flow Though Grit Chamber
2/17/2020
Compartments of grit chamber
• Zone – I: Inlet zone: This zone distributes the incoming wastewater uniformly
to entire cross section of the grit chamber.
• Zone – II: Outlet zone: This zone collects the wastewater after grit removal.
• Zone – III: Settling zone: In this zone settling of grit material occurs.
• Zone – IV: Sludge zone: This is a zone where settled grit accumulates.
8
Design of grit chambers
2/17/2020
• Now, if Vs is the settling velocity of any particle, then
• The smallest particle expected to be removed in the grit chamber has size 0.2 mm and
sometimes in practice even size of the smallest particle is considered as 0.15 mm. The
terminal velocity with which this smallest particle will settle is considered as Vo. This
velocity can be expressed as flow or discharge per unit surface area of the tank, and is
usually called as ‘surface overflow rate’ or ‘surface settling velocity’.
9
Design of grit chambers
2/17/2020
• Now for 100 percent removal of the particles with settling
velocity Vs >= Vo, we have
L / H = Vc / Vo
10
Design of grit chambers
2/17/2020
• The critical velocity, Vc, can be given by the following equation
11
2/17/2020
Design of grit chambers
• The grit chambers are designed to remove the smallest particle
of size 0.2 mm with specific gravity around 2.65. For these
particles, using above expression the critical velocity comes out
to be Vc = 0.228 m/sec.
12
Settling Velocity of the Particles
2/17/2020
• Settling velocity of any discrete particle depends on its individual
characteristics and also on the characteristics of the fluid.
Assuming particles to be spherical, the settling velocity of any
particle, Vs, can be given by the following
formula:
2/17/2020
Horizontal flow grit chamber
14
Horizontal Flow Rectangular Grit Chamber
2/17/2020
• A long narrow channel is used in this type of grit chamber.
The wastewater moves through this channel in more or
less plug flow condition with minimal mixing to support
settling of the particles.
16
Control of Velocity Through
2/17/2020
the Grit Chamber
With variation in sewage flow received at treatment plant, it is important that
velocity of the wastewater in the grit chamber should be maintained nearly
constant.
Otherwise when flow is lower, deposition of not only inorganic solids but also
organic solids will occur in grit chamber due to lowering of velocity.
With flow higher than average, when the velocity will exceed the critical velocity,
scouring of already deposited grit particles will occur leading to failure of
performance.
17
Control of Velocity Through
2/17/2020
the Grit Chamber
Hence for proper functioning, the velocity should not be allowed
to change in spite of change in flow in the grit chamber.
18
2/17/2020
Proportional Weir Parshall flume
19
Disposal of Grit
2/17/2020
• Considerable quantities of grit will be collected at the sewage treatment plant,
about 0.004 to 0.2 m3/ML. Quantity of grit will be more particularly for combined
system. Necessary arrangement should be made at the treatment plant for
collection, storage and disposal of this grit matter. The grit collected can be
disposed in the following manner:
• In the past, grits along with screening was dumped into sea.
2/17/2020
Design a grit chamber for population 50000 with water
consumption of 135 LPCD.
Solution
Average quantity of sewage, considering sewage generation 80%
of water supply, is
= 135 x 50000 x 0.8 = 5400 m3/day = 0.0625 m3/sec
2/17/2020
Length of the grit chamber
= velocity x detention time = 0.2 x 60 = 12.0 m
Volume of the grit chamber
= Discharge x detention time
= 0.156 x 60 = 9.36 m3
Cross section area of flow ‘A’
= Volume / Length = 9.36/12 = 0.777 m2
Provide width of the chamber = 1.0 m,
hence depth = 0.777 m
Provide 25% additional length to accommodate inlet and
outlet zones.
22
Design of Grit Chamber
2/17/2020
The length of the grit chamber
= 12 x 1.25 = 15.0 m
Provide 0.3 m free board and 0.25 m grit accumulation zone
depth, hence total depth
= 0.777 + 0.3 + 0.25 = 1.33 m
and width = 1.0 m
23
2/17/2020
Design of Aerated Grit Chamber
Design aerated grit chamber for treatment of sewage with average
flow of 60 MLD. Consider the peak factor of 2.
Solution:
1. Average flow = 60 MLD = 0.694 m3 /sec, and
Peak flow = 0.694 x 2.0 = 1.389 m3/sec
2. Volume of grit chamber
Provide two chambers to facilitate periodic cleaning and
maintenance
Provide detention time = 3.0 min
Volume of each tank = 1.389 x 3 x 60 /2 = 125.01 m3
24
Design of Aerated Grit Chamber
2/17/2020
3. Dimensions of aeration basin:
Provide depth to width ratio of 1: 1.2
Provide depth = 3.0 m
hence width = 1.2 x 3.0 = 3.6 m
Length = 125.01 / (3 x 3.6) = 11.575 m
Increase length by 20% to account for inlet and outlet conditions.
Total length = 11.575 x 1.2 = 13.89 m.
4. Determine the air-supply requirement
Consider 0.3 m3 /min.m of length air supply
Air Requirement = 13.89 x 0.3 = 4.17 m3 /min
Provide air swing arrangement at 0.5 m from floor
25
Design of Aerated Grit Chamber
2/17/2020
5. Quantity of grit :
Consider grit collection 0.015 m3/103 m3
Volume of grit = 1.389 x 60 x 60 x 24 x 0.015 x 10-3
= 1.8 m3/d
6. Check for surface overflow rate (SOR)
Settling velocity of the smallest particle = 0.228 m/sec,
Actual SOR in the grit chamber
= 1.389 / (3.6 x 11.575)
= 0.033 m/s
= which is less than the settling velocity of the smallest
particle hence design is safe.
26
2/17/2020
SEDIMENTATION TANK
27
Principle of sedimentation tanks
2/17/2020
• Based on the process of sedimentation in which the suspended organic solid
matter present in sewage which is too light to be removed by grit chamber is
removed.
• In still sewage these particles will tend to settle down by gravity whereas in
flowing sewage they are kept in suspension because of turbulence in water.
Hence as soon as turbulence is retarded by offering storage to sewage these
impurities tend to settle down at the bottom of the tank offering such storage.
28
Principle of sedimentation tanks
2/17/2020
Settling of Flocculated particles
Flocculated particles are those which change their size, shape and weight and thus
lose their identity.
29
function of primary sedimentation
2/17/2020
tanks
The purpose and function of the clarifier is threefold:
• Allow settling of light organic suspended solids coming out of the Grit
chamber to the bottom of the clarifier
• The clarifier tank is only a passive device: All the above actions occur
due to gravity.
30
2/17/2020
design of primary sedimentation tanks
• The primary sedimentation tank generally removes 30 to 40% of the total
BOD and 50 to 70% of suspended solids from the raw sewage.
• The flow through velocity of 1 cm/sec at average flow is used for design
with detention period in the range of 90 to 150 minutes.
• Effluent weirs are provided at the effluent end of the rectangular tanks, and
around the periphery in the circular tanks.
31
2/17/2020
design of primary sedimentation tanks
• Weir loading less than 185 m3/m.d is used for designing effluent weir length
(125 to 500 m3 /m.d). Where primary treatment follows secondary treatment,
higher weir loading rates can be used.
• The sludge collection hopper is provided near the center in circular tank and
near the influent end in rectangular tanks.
• A baffle is provided ahead of the effluent weir for removal of floating matter.
This scum formed on the surface is periodically removed from the tank
mechanically or manually.
32
design of primary sedimentation tanks
2/17/2020
• Primary sedimentation tanks can be circular or rectangular tanks designed using
average dry weather flow and checked for peak flow condition.
• The numbers of tanks are determined by limitation of tank size. Two tanks in
parallel are normally used to facilitate maintenance of any tank.
• The diameter of circular tank may range from 3 to 60 m (up to 45 m typical) and
it is governed by structural requirements of the trusses which supports scrapper in
case of mechanically cleaned tank.
33
design of primary sedimentation tanks
2/17/2020
• Rectangular tank with length 90 m are in use, but usually length more than 40 m is not
preferred.
• Width of the tank is governed by the size of the scrappers available for mechanically
cleaned tank.
• The depth of mechanically cleaned tank should be as shallow as possible, with minimum
2.15 m.
• The average depth of the tank used in practice is about 3.5 m. In addition, 0.25 m for
sludge zone and 0.3 to 0.5 m free board is provided.
• The floor of the tank is provided with slope 6 to 16 % (8 to 12 % typical)for circular tank
and 2 to 8% for rectangular tanks.
34
2/17/2020
design of primary sedimentation tanks
• The scrappers are attached to rotating arms in case of circular tanks and to endless
chain in case of rectangular tanks.
• These scrappers collect the solids in a central sump and the solids are withdrawn
regularly in circular tanks.
• In rectangular tanks, the solids are collected in the sludge hoppers at the influent end,
and are withdrawn at fixed time intervals.
• The scrapper velocity of 0.6 to 1.2 m/min (0.9 m/min typical) is used in rectangular
tank and flight speed of 0.02 to 0.05 rpm (0.03 typical) is used in circular tank.
35
design of primary sedimentation tanks
2/17/2020
• Inlets for both rectangular and circular tanks are to be designed to distribute the
flow equally across the cross section.
• Scum removal arrangement is provided ahead of the effluent weir in all the PST.
• The surface overflow rate of 40 m3/m2.d (in the range 35 to 50 m3/m2.d ) is used
for design at average flow.
• At peak flow the surface overflow rate of 60 to 120 m3/m2.d could be used when
this PST is followed by secondary treatment.
36
2/17/2020
design of primary sedimentation tanks
• The weir loading rate less than 185 m3 /m.d is used for designing effluent weir
length (in the range 125 to 500 m3 /m.d). Weir loading rate up to 300 m3 /m.d is
acceptable under peak flow condition.
37
2/17/2020
design of primary sedimentation tanks
• Higher weir loading can be acceptable when primary treatment is
followed by secondary treatment.
• As such the weir loading rate has very less impact on the overall
performance of sewage treatment plant when secondary treatment is
provided after primary treatment.
38
2/17/2020
drawing of rectangular sedimentation tank
39
drawing of circular sedimentation
2/17/2020
tank
40
drawing of circular sedimentation
2/17/2020
tank
The figure shows only some part of the tank floor (1). A
bucket-shaped sludge collection pit
(2) collects the sludge that is swept by the squeegees.
The collected sludge is pumped out through the outlet port
(3) and outlet pipe
(4) In the center of the pit, an RCC pillar (5) is provided. A
bush housing (6) is mounted on this pillar. The housing
contains a bush, which provides a frictionless support to the
rotating rake (7).
41
Design of primary sedimentation tank
2/17/2020
Design the primary sedimentation tank to treat wastewater with average flow rate of
10 MLD and peak flow of 22.5 MLD.
Solution
= 10 x 106 / 40 x 103
= 250 m2
The SOR at peak flow = 22.5 x 103 /250 = 90 m3/m2.d < recommended value at peak flow. 42
Design of primary sedimentation tank
2/17/2020
Assume width = 6.0 m
Total length of each tank = 41.66/2 + 2 (inlet) + 2 (outlet) = 24.83 say 24.85 m
Flow rate x detention time = depth x surface area = VOLUME OF THE TANK
43
Design of primary sedimentation tank
2/17/2020
Flow through velocity = (0.116 m3 /sec) / (2 x 2.5 x 6)
= 0.0039 m/sec.
= 3.25 m
44
Operation and Maintenance aspects.
2/17/2020
• If properly designed, engineered and constructed, clarifiers call for very little attention
in terms of operation and maintenance.
• Some parts of the mechanical rake (such as the motor, gearbox etc.) call for only
routine maintenance.
• The sacrificial rubber squeegees sweeping the floor of the clarifier need to be checked
and replaced, possibly once in two years.
46