CONTENT
2
1. Origin of The Request
MSA declared about production planning ramp up until 2024.
For that case, we need to do analysis about supporting element in order to achieve the target
year by year.
Utility Department is one of the many important element that realize the plan because it
provides the energy source for overall production activity (Electricity, Steam, Compressed air,
Water & Cooling Water, Nitrogen).
To Ensure the production continuity we need to calculate the utility capacity related to the
production planning 2024.
So, the results are as follows :
a. There are deficiencies in the compressed air supply energy if the production capacity is
increased.
The Purchase of 2 units of Air Compressor (1 unit at 2019 & 1 unit at 2021) with Capacity 22 m3/min
is needed.
b. There should be a back up System and modification in the Chilled Water System for Stability
& quality supply.
c. Power Factor Value Improvement for Optimizing Electrical Usage
3
A. AIR COMPRESSOR UNIT FOR SUPPORT PRODUCTION PLANNING
Subject Unit 2019 2020 2021 2022 2023 2024 Maximum
Ramp Up
Production Plan (MAX) Production
PCR PCS/DAY 28.106 30.862 33.066 33.727 33.948 33.948 2019 ~ 2024
Compressed Air Capacity Actual (b) m3/min 373,82 373,82 373,82 373,82 373,82 373,82
Starting from 2020 the Factory will be lack of Compressed Air Supply if the
production planning is increased
4
B. CHILLED WATER BACK UP SYSTEM & MODIFICATION
At Sept. 2019 ===> Bulging at Chilled Water Storage Tank System
The Chilled Water Storage System Supply all cooling system for TCU & Production Machine
IMPACT ====> If Anything Happen to Chiller System will Interupt the Production Process
for that case we need 7 days to repairment the chiller system.
Production Lost Cost = USD 1.930.000
ACTION PLAN :
1. Additional More Steel Support to decrease the deflection ( Sept ~ Nop 2019) DONE
2. Install Stiffener to stop the deflection (Dec 2019 ~ Jan 2020) DONE (RESULT : OK)
3. Need some modification at the Chilled Water Storage Tank (2020)
4. Define & Execute the contigency plan to avoid the similar problem
5
C. POWER FACTOR VALUE IMPROVEMENT
SUBSTATION PARAMETER PERFORMANCE Standard Judgement
Capacitor Load 65% 65% Max. 80%
Cabin 1.1
Trafo 1
Power Factor KVAR Energy Need to0,95
be Compensated
0,95 0,95
OK
Capacitor Load 50% 50% Max. 80%
Trafo 2
Power Factor by using Capacitor
0,95 0,95 0,95
OK
Trafo 1
Capacitor Load
Power Factor
40% So it can be transformed into
0,95
Active
40% Power
0,95
Max. 80%
0,95
OK
Cabin 2.1
Capacitor Load 40% 40% Max. 80%
Trafo 2 OK
Power Factor 0,95 0,95 0,95
Capacitor Load 60% 60% Max. 80%
Trafo 1 OK
Power Factor 0,95 0,95 0,95
Cabin 3.1
Capacitor Load 50% 50% Max. 80%
Trafo 2 OK
Power Factor 0,95 0,95 0,95
Capacitor Load 45% 45% Max. 80%
Cabin 5.1 Trafo 1 OK
Power Factor 0,95 0,95 0,95
Capacitor Load 50% 50% Max. 80%
Cabin 6.1 Trafo 1 OK
Power Factor 0,95 0,95 0,95
Capacitor Load 30% 30% Max. 80%
Trafo 1 OK
Power Factor 0,95 0,95 0,95
Cabin 7.1
Capacitor Load 40% 40% Max. 80%
Trafo 2 OK
Power Factor 0,95 0,9 0,95
Capacitor Load 100% 100% Max. 80%
Cabin 8.1 Trafo 1 Δ
Power Factor 0,95 0,95 0,95
Capacitor Load 20% 20% Max. 80%
Cabin 1.2 Trafo 1 OK
Power Factor 0,95 0,95 0,95
Capacitor Load 100% 100% Max. 80%
Cabin 2.2 Trafo 1 X
Power Factor 0,90 0,90 0,95
Capacitor Load 25% 25% Max. 80%
Trafo 1 OK
Power Factor 0,95 0,95 0,95
Capacitor Load 30% 30% Max. 80%
Cabin 3.2 Trafo 2 OK
Power Electricity Can’t Absrob Optimally due to the low value of Power
Power Factor 0,95 0,95 0,95
Capacitor Load 70% 70% Max. 80%
Trafo 2 OK
Factor (PF)
Power Factor 0,95 0,95 0,95
Power Substation
StandardCabin
of 2.2 & 8.1Factor
Power show the poor performance of power factor
is 0,95
It means The Electricity doesn’t absorb optimaly due to the lack of Capacitor Capacity 6
2. PROJECT ORGANIZATION
• Project Sponsor : Kuntarso
• Steering Committee
– Kevin Grant
– Michail Sutiono
– Kuntarso
– Hery Arsandy
– Donald McLanders
• Project Leader
– Witarman / Ribut
• Team Member
– Joko Utomo (Utility Maintenance)
– Eman Jaya (Utility Project)
– Winarto (Utility Operation)
– Rosdiana Fajar (Project Administrator)
7
3. STAKE & OBJECTIVE
To ensure the business continuity by calculate the utility capacity & review the utility
system related to the production planning 2024 :
a. Purchase 2 units of Air Compressor (1 unit at 2019 & 1 unit at 2021).
with Capacity 22 m3/min.
b. Chilled Water Storage Tank Modification & Contigency Plan for Stability Supply of Cooling
System
c. Extend Capacitor unit at Power Substation Cabin 2.2
8
4. CURRENT CONDITION & COST PROPOSAL NATURE : 42 IFR
a). Purchase 1 unit of New Air Compressor 2019 ~ 2021
Subject Unit 2019 2020 2021 2022 2023 2024 Maximum
Ramp Up
Production Plan (MAX)
Production
PCR PCS/DAY 28.106 30.862 33.066 33.727 33.948 33.948 2019 ~ 2024
MC PCS/DAY 22.965 25.469 27.561 28.112 28.296 28.296
Compressed Air Capacity Actual (b) m3/min 373,82 373,82 373,82 373,82 373,82 373,82
m3/min 22 28
-17 40
-49 28
-61 22
-67 22
-67
Δ (Shortage Capacity) (a-b)
Unit 0,5 0,6
-0,4 0,9
-1,1 0,6
-1,3 0,5
-1,5 0,5
-1,5
1 TRANSFORMATOR Existing
NEED TO
2 2 1 3 2 NORMALIZATION
2 MV PANEL NEW (Buy)
LV PANEL
3 CABLE NEW (Buy)
NEW AIR COMPRESSOR 300 kW
4 AIR COMPRESSOR NEW (Buy)
3 UNIT
TO PLANT
4
PRODUCTION Air Compressor Unit Already
Purchased at 2019
ETA : Mid Februari 2020
10
4. CURRENT CONDITION & COST PROPOSAL NATURE : 42 IFR
a). Purchase New Air Compressor 2019 ~ 2020 (Budget & Realization Detail)
No Item Spec Qty PR NUMBER Budget Realization
Transformator (Service) 2000 Kva (Normalisation Unit) 1 unit 0001/PR/01/20/A3043 USD 3.820 -
SUPPORT INSTALLATION TRAFO
Civil Building for New TRAFO Civil Building +Ventilating System 1 Lot 0009/PR/08/19/A3043 USD 9.710 -
Busduct 400 V sekunder trafo BUS Duct 4000 A 1 Lot 0002/PR/01/20/A3043 USD 185.000 -
Kabel to Panel Air Compressor 1 x 185 mm Cu (8x Pulling Cable) 800 meter 0025/PR/09/19/A3043 USD 14.474 USD 14.474
AIR COMPRESSOR NEW 300KW Flowrate : 2.860 m3/h (8 barg) 1 UNIT 0004/PR/08/19/A3043 USD 241.279 USD 48.276
AIR COMPRSSOR
DISMANTLING COMPRESSOR ATLAS COPCO Dismantling Unit existing (Scrap) 1 Lot 0015/PR/01/20/A3043 USD 38.50 -
Air Compressor & Pipeline installation Mech & Elect Installation 1 Lot 0014/PR/01/20/A3043 USD 13.000 -
On Progress
Install New
Reinforcement
Januari 2019 Additional Support Stiffener Failed
Start Piping & to Stop the Bulging
Chiller Installation / Deformation
SOUTH NORTH The Tank shell on south and north side was
bulging Due to the lack of Vertical external
support UNP 150x75.
13
b.2) Modification & Repairment Process
1st Step Repairment Process for Storage Tank
SOUTH NORTH SOUTH NORTH
BEFORE AFTER
September 2019 : December 2019 At Maintenance Day :
Bulging at the north & south side of Storage Tank Install Stiffener Structure to Stop the deformation
RESULT ===> FAILED (STILL BULGING / DEFORMED)
DUE TO POOR OF WELDING SPOTS
14
b.2) Modification & Repairment Process
2nd Step Repairment Process for Storage Tank
SOUTH NORTH SOUTH NORTH
H-Beam
200x200
WF
150x75
Beam Reinforcement
at south & north side
BEFORE AFTER
Install Stiffener Structure to Stop the deformation Replacement of Stiffener Structure using Beam
RESULT ===> FAILED (STILL BULGING / DEFORMED) Reinforcement at South & North Side
RESULT = GOOD
For Step 2 Need Additional
CAPEX Budget : USD 102.000
15
b.2) Modification & Repairment Process
3rd Step Repairment Process for Storage Tank
WF
150x75
Beam Reinforcement
at south & north side Beam Reinforcement
BEFORE AFTER at East & West side
Install Beam Reinforcement at East & West Side to Avoid another bulging / deflection
16
b.2) Modification & Repairment Process
4th Step Repairment Process for Storage Tank
SOUTH NORTH
NEW CHILLER
NEW PIPING
INSTALATION
ESTIMATE BUDGET
===> USD 47.000
1. Install New Pump for Circulating Chiller
2. The maximum Chilled Water temperature
that can be produced is 26ºC
18
4. CURRENT CONDITION & COST PROPOSAL NATURE : 42 IFR
C). CAPACITIVE LOAD REVIEW to IMPROVE POWER FACTOR AT POWER SUBSTATION 2.2
Cabin 2.2 Trafo 1 At the Maximum Load
Kapasitas Trafo 3208 A (Trafo Capacity = 3.208 A)
Load Trafo 2900 A ===> 1.900 kW
Cos phi Actual 0,9
By Using Multiplier Factor (0,69)
PF = 0,95 Running Step Capacitor 12 to reach power factor until 0,95
PF = 0,68 (AFTER) Total Step Capacitor 12
(Before) Exisiting Capacitor Unit that Capacitive Load that need to
already Install = 1.200 kVar Compensated :
= (1.900 kW x 0,75)/0,8
Lack of Capacitor Capacity = 1.781 kVar
= 1.781 – 1.200 kVar
Estimate Budget
= 581 kVar
= USD 70.000
20
5. PROJECT PLANS
Plan X0 X1 X2
2 CHILLER TANK MODIFICATION 162.000
USD 102.000 6.000 54.000
Plan X0 X0 X1 X2
4 CAPACITOR UNIT CABIN 2.2 60.000
USD 6.000 48.000 6.000
Total Budget 750.434 USD - 150.143 310.260 - 86.900 149.130 48.000 6.000 - - - -
21
6. RISK ANALYSIS
CAPEX Potential risk Cause Effect Proposed Action(s)
Can’t Support Production Lack of Compressed Air Capacity to fullfill Lost the opportunity to achieve the Reduce production planning in accordance to
Planning until 2021 the demand production planning the Compressed Air Supply Capability
Air Compressor that have been
Inventory of Spare parts will Increased Maintenance Cost for Air
purchased are not used (Pending for
AIR COMPRESSOR PROJECT increase Compressor Inventory
Installation) Air compressor unit must be properly stored
There will be any addiitonal and covered in the box
Air Compressor that have been installed Increased Operational & Maintenance
annual operational and
need to maintain at good condition Costs for Air Compressor Operation
maintenance costs
22
THANK YOU