Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Estimating Project
Times and Costs
McGraw-Hill/Irwin
Copyright © 2011 by The McGraw-Hill Companies, Inc. All
rights reserved.
Where We Are Now
5–2
Estimating Projects
• Project estimation is a yardstick for project cost control. If the
yardstick is faulty, you start on the “wrong foot”.
Do not underestimate the estimate!!
• Estimating
–The process of forecasting or approximating the time and
cost of completing project deliverables.
–The task of balancing expectations of stakeholders and
need for control while the project is implemented.
• Types of Estimates
1. Top-down (macro) estimates: analogy, group
consensus, or mathematical relationships
2. Bottom-up (micro) estimates: estimates of elements
of the work breakdown structure 5–3
Why Estimating Time and Cost Are Important?
EXHIBIT 5.1
5–4
Factors Influencing the Quality (Accuracy) of Estimates
Planning Horizon
Other
Project
(Nonproject)
Duration
Factors
Quality of
Organization Estimates People
Culture
5–5
Estimating Guidelines for Times,
Costs, and Resources
5–6
Top-Down versus Bottom-Up Estimating
Two main Approaches
• Top-Down Estimates https://www.youtube.com/watch?v=34nxX_VP1fo
–Are usually derived from someone who uses
experience and/or information to determine the project
duration and total cost.
–Are made by top managers who have little knowledge
of the (detailed) processes used to complete the
project.
• Bottom-Up Approach https://www.youtube.com/watch?v=oQxgaVw0fWs
–Can serve as a check on cost elements in the WBS
by rolling up the work packages and associated cost
accounts to major deliverables at the work package
level.
5–7
Top-Down versus Bottom-Up Estimating
TABLE 5.1
5–8
Estimating Projects: Preferred Approach
5–9
Top-Down Approaches for Estimating
Project Times and Costs
• Consensus methods
• Ratio methods
• Apportion method
Project Estimate
Times
• Function point methods for Costs
software and system projects
• Learning curves
5–10
Apportion Method of Allocating Project Costs
Using the Work Breakdown Structure
TABLE 5.2
5–13
Example: Function Point Count Method
TABLE A5.1
5–16
Table A5.2: Learning Curves Cumulative Values
TABLE A5.2
5–17
Bottom-Up Approaches for Estimating
Project Times and Costs
There is
a range in
No of days
FIGURE 5.2
5–19
Phase Estimating over Product Life Cycle
5–20
Top-Down and Bottom-Up Estimates
FIGURE 5.4
5–21
Level of Detail
5–22
Types of Costs
• Direct Costs
–Costs that are clearly chargeable
to a specific work package.
• Labor, materials, equipment, and other
• Direct (Project) Overhead Costs
–Costs incurred that are directly tied to an identifiable
project deliverable or work package.
• Salary, rents, supplies, specialized machinery
• General and Administrative Overhead Costs
–Organization costs indirectly linked to a specific
package that are apportioned to the project
5–23
Contract Bid Summary Costs
FIGURE 5.5
5–24
Three Views (Perspectives) of Cost
(Known to PM,
but not to Finance)
5–26
Creating a Database for Estimating
FIGURE 5.7
5–27
Variability in Activity Times
• 3 time estimates (Will be practiced in Lab 3)
–Optimistic times (o)
–Most-likely time (m)
–Pessimistic time (p)
• Follow beta distribution
• Expected time: Et = (o + 4m + p)/6
• Variance of times: v = (p - o)2/62
• Project Variance = sum of variances of all activities on
the critical path
• Example: An activity has optimistic estimate (o) of 1, pessimistic estimate (p)
of 9, most likely estimate (m) of 2.
• Its Expected Time = 3 = (1+4*2+9)/6;
• Its Variance = 1.78 = (9 − 1)2 / 36 = 1.8 28