Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Open Access.-
(1) A Captive Generating Plant shall have right to ‘open access’ for carrying
electricity from its plant to the destination of its use by using transmission lines or
distribution system or associated facilities with such lines or system and for that
matter, rules or regulations notified by the Commission in that regard shall apply:
Provided that the plant shall ensure to dispatch electricity as per the schedule
and unscheduled interchange, if any with the grid, shall not exceed 10
percent of the total dispatch in a day restricted to 5 percent during peak
hours, beyond which a penalty may be imposed by the Commission, in
addition to the Unscheduled Interchange Charges payable under the intra
state ABT scheme, on the recommendation of the State Load Despatch
Centre:
Provided also that the ‘open access’ shall be subject to the availability of
transmission capacity as determined by State Transmission Utility or the
Central Transmission Utility, as the case may be:
(2) The plant seeking ‘open access’ shall approach State Transmission Utility
and/or Central Transmission Utility and/or intervening transmission licensee
and/or distribution licensee who shall determine and allow non discriminatory
‘open access’ subject to availability of transmission capacity.
DRAFT REGULATION ON Terms and Conditions for Supply of Power from
Captive Generating Plants to Distribution Licensees Regulations 2006
Reactive power.-
Wind energy generators shall maintain their own capacitors and shall not
draw reactive power as far as possible. There will be disincentive for drawing
reactive power on the basis of monthly average power factor. If the average
power factor is less than 0.9 the disincentive fixed is 1% of energy generated for
every reduction of 0.01 below 0.9 PF
Surcharge.-
A Captive Power plant shall not be liable to pay surcharge in addition to
the charges for transmission and wheeling for carrying the electricity to the
destination of his own use.
DRAFT REGULATION ON Terms and Conditions for Supply of Power from
Captive Generating Plants to Distribution Licensees Regulations 2006
Sale of Power.-
(1) A captive generating plant may enter into an agreement with the distribution
licensee for sale of its surplus capacity based on PPA approved by the
Commission. The parties to the agreement may make plant/site specific
conditions in the PPA not inconsistent with the Act, these Regulations and other
relevant regulations. Provided that the plant may also supply electricity to a
consumer who is permitted open access as per provisions of Open Access
Regulations. Such consumers shall pay Transmission charges, wheeling charges
and such other charges as determined by the Commission under Open Access
Regulation.
The distribution licensee shall pay the transmission charges and wheeling
charges for such supply , as may be determined by the Commission by an order:
Provided further that Distribution Licensee may require emergency
assistance following an extensive failure in the system. Subject to technical
feasibility, the Captive Generating Plant may, if requested by the licensee, extend
power supply from its generating station to the licensee’s system. In such
circumstances, the tariff for such supply shall be mutually agreed.
DRAFT REGULATION ON Terms and Conditions for Supply of Power from
Captive Generating Plants to Distribution Licensees Regulations 2006
Purchase of Electricity.-
Any person, who establishes, maintains and operates a Captive Power
Plant, may purchase electricity from a generating company or a distribution
licensee in case his plant is not in a position to generate electricity to meet the
requirement of his own use and consequently additional power is required:
Provided that such purchase of electricity, from a distribution licensee,
shall be charged as per the tariff determined by the Commission under
appropriate ‘Rate Schedule of tariff under which the total load requirement of the
plant shall belong to:
Provided also that in case of purchase of power though a trader or a
generating company or a distribution licensee other than a distribution licensee of
the area in which the plant is located, the rate shall be as mutually agreed
however, surcharge and additional surcharge besides other charges shall be
payable as determined by the Commission under open access regulations.
Provided further that the tariff payable by a captive plant to a distribution
licensee, in case of banking of energy, shall be as per Clause 21 if that plant has
an arrangement of banking of energy with such distribution licensee.
DRAFT REGULATION ON Terms and Conditions for Supply of Power from
Captive Generating Plants to Distribution Licensees Regulations 2006
Metering Arrangement.-
The Generating Plant shall provide ABT compatible Special Energy Meters
at the point of injection and point of drawal and shall comply with all metering
requirements as notified by the State Transmission Utility.
Provided that the point of injection and point of drawl for the purpose of
recording and billing purposes shall be the substation of the licensee and
point of drawal shall be the consumer premises.
The State Load Dispatch Centre shall do energy accounting and billing
and the same shall be communicated to the utilities interacting with the grid .
Provided that in case of sale to the distribution licensee of the area, the
power purchase agreement may provide for joint metering and in such
cases, energy accounting and billing shall be done by the generating plant in
association with the concerned distribution licensee.
DRAFT REGULATION ON Terms and Conditions for Supply of Power from
Captive Generating Plants to Distribution Licensees Regulations 2006
Banking of Power.-
The Generating Plants shall be allowed to bank power, for the purpose of
withdrawal of the banked power in the event of emergency or shut down or
maintenance of the plant, subject to following conditions:
Units generated during higher tariff TOD slot could be consumed at lower
tariff TOD slot at the option of generators/ users, but the reverse will not be
allowed. No carryover is allowed during next month. The unutilized banked
energy as on 31st March shall be treated as sold to the licensee at the rate
approved by the Commission and slot to slot adjustment will not be
applicable for such unutilized portion. Excess drawal at any point of time will
be charged under respective tariff applicable to the user. The peak hour extra
charges and off peak hour rebate shall be on net energy consumption after
DRAFT REGULATION ON Terms and Conditions for Supply of Power from
Captive Generating Plants to Distribution Licensees Regulations 2006
Payment Mechanism.-
The Distribution Licensee shall make payment through a revolving
selfreplenishing Letter of Credit (LC) in favour of the plant. The value of LC
shall be determined on the basis of average monthly energy scheduled for a
particular calendar quarter under the power purchase agreement. The LC
shall be updated by 5th working day of the quarter. The Licensee shall bear
the charges for opening and maintenance of LC. Any shortfall in the amount
of LC shall be payable within thirty days from the date of billing. In such
case, a rebate of 1.25 percent shall be allowed and for default in payment
beyond thirty days from the date of billing, a surcharge at the rate of 1.25
percent per month or part thereof shall be levied on the billed amount. If the
payment is made by a mode other than through LC within a period of one
month of presentation of bill by the generating company, a rebate of 1.0
percent shall be allowed, however a surcharge at the rate of 1.25 percent per
month or part thereof shall be levied on the billed amount in case of default
in payment beyond 30 days.
Provided further that the rate and payment terms approved by KSERC
from time to time for the respective consumer category under ‘Rate
Schedule for Tariff’ shall apply for purchase of electricity by the plant.
Power to Relax.-
SLDC shall undertake the accounting of energy for each time block on monthly basis
with the assistance of the Energy Billing Centre (EBC) of the State Transmission Utility
(STU) in respect of the Open Access Generators, Scheduled Consumers and the OA
Consumers who are connected to the transmission system, In respect of the Open
Access Generators, Scheduled Consumers and the OA Consumers who are connected
to the distribution system, it is the EBC that shall be responsible for energy accounting
and settlement in co-ordination with the DISCOMs.
Such Account shall be examined and signed by a Committee comprising the STU,
DISCOMs and Generators:
Provided that in the case of Generators, only one representative, as approved by the
Commission, from each class of Generators mentioned below shall be represented on
the Committee:
The Scheduled energy (in kWh) at exit point shall be calculated for each time block from the
scheduled capacity (kW) at the Exit point, as provided in the wheeling schedule, by multiplying
it with the period of time block in hours.
Scheduled demand at exit point shall be calculated by dividing the scheduled capacity (kW) at
exit point by the power factor for the time block, for which purpose the Power factor shall be
equal to the recorded kWh divided by kVAh.
The Scheduled energy of a Scheduled Consumer from an OA Generator for each time-block
shall be deducted from the recorded energy (in the inter-se order of such Generators, as and
if intimated by the consumer, in case the consumer is availing of energy from more than one
Generator) as a first charge. The balance energy shall be deemed to have been supplied by
the DISCOM and shall have to be paid for as per the terms of the supply agreement with the
DISCOM:
Provided that where there is a deviation between the scheduled capacity and actual capacity
being injected at an Entry point in a time block, the shortfall, if any, in the capacity allocated to
the Scheduled Consumer shall be deemed to have been drawn by the Scheduled Consumer
from the DISCOM and the energy corresponding to such shortfall shall be paid for by the party
which has contracted for the Open Access capacity with the Licensee to the DISCOM as per
the energy tariff applicable for the same consumer category of DISCOM under which the
Scheduled Consumer would normally fall.
ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION
INTERIM BALANCING AND SETTLEMENT CODE FOR
OPEN ACCESS TRANSACTIONS
Regulation No. 2 of 2006
SETTLEMENT OF ENERGY/DEMAND AT EXIT POINT IN RESPECT OF SCHEDULED
CONSUMER
The Scheduled Energy at Exit point of an OA Consumer shall be calculated from the
Scheduled capacity from an OA Generator at the Exit point for each time block as
provided in clause Scheduled consumer above.
In case the Open Access Consumer is receiving supply from more than one Open
Access generator, the total energy and demand recorded shall be deemed to have
been consumed from the respective Open Access Generators in the inter-se order of
Generators as confirmed by the SLDC while finalizing the day-ahead schedule.
The excess energy recorded, if any, at the exit point for any time block with reference to
scheduled energy or the actual energy available at that Exit point, whichever is less,
shall be deemed to have been consumed by the Generator or the OA consumer
whoever has contracted for the Open Access capacity with the Licensee, from the
DISCOM and shall be paid for by the Open Access Generator/Consumer at the energy
tariff applicable for the same consumer category of DISCOM to which the OA Consumer
would normally belong. Such excess consumption shall also attract all penal
provisions provided in the applicable Tariff Order like those in respect of Low Power
Factor, voltage surcharge, etc and wherever applicable, the relevant charges shall also
be paid for by the OA generator/OA consumer.
The Scheduled demand at Exit point or the actual demand made available to a
consumer from each OA Generator at that Exit point in a time-block whichever is less,
shall be deducted from the recorded demand (in the inter-se order of such Generators,
as confirmed by the SLDC while finalising the day-ahead schedule, in case the
consumer is availing of energy from more than one Generator). The balance demand
for each time-block shall be deemed to have been consumed from the DISCOM and
shall be paid at twice the demand charges applicable for the same consumer category
INTERIM BALANCING AND SETTLEMENT CODE FOR
OPEN ACCESS TRANSACTIONS
Regulation No. 2 of 2006
FOR OA GENERATORS AT ENTRY POINT:
BANKING
No generators other than the Wind and Mini Hydel power generators shall be allowed
the facility of banking the electricity generated by them:
Provided that in the case of existing users of wheeling facility, the energy already
banked as per the subsisting agreements as on the date of coming into force of this
Regulation, shall be allowed to be wheeled as hithertofore till the expiry of the balance
period available for utilization of the banked energy:
Provided, however, that in the case of generators whose cases are pending
appeals in the Hon’ble High Court of Andhra Pradesh and/or the Hon’ble Supreme
Court, this provision shall be applicable subject to the final decision of the High Court
and / or the Supreme Court, as the case may be.
The banking facility to the Wind and Mini Hydel power generators shall be subject
to the conditions specified
Tamil Nadu Electricity Regulatory Commission
Intra State Open Access Regulations 2005
Categorization of intra state Open Access Customers
(a) The payment for the reactive energy charges for the direct
customers on account of open access shall be in accordance with
the charges to be approved by the Commission from time to time.
These charges shall be based on the requirements to be met by the
direct customer with regard to reactive power generation / drawal,
as stipulated in the State Grid Code / Distribution Code / Supply
Code, as the case may be.