Sei sulla pagina 1di 14

Ground Floor ZONE (A1) MEP /01/2020

Item Check Why? When? Note


1- Painting
MECH 2- Sprinklers
3- Support
Fire
4- Labels
Fighting
5- Builder Work
6- FHC & rigid support
1- Insulation
MECH
2- Hookup & PICV
HVAC 3- Grilles Necks
Duct 4- Wrapping
5- Painting
6- Labels
7- BMS
8- Power Supply
9- Check Directions & Level
10- Hookup Insulation
11- Builder Work
12-Duct support & alignment
Ground Floor ZONE (A1) MEP /01/2020
Item Check Why? When? Note
1- Gate Valves
2- Support
Water
3- EWH Power Supply
Supply
4- WHA
5- Labels
6- Builder Work
1- Pipe Level, Slope
Drainage
2- Support
3- AC Drain
4- Connection W/FCU
5- Builder Work
6- Labels
Ground Floor ZONE (A2) MEP /01/2020
Item Check Why? When? Note
1- Painting
MECH 2- Sprinklers
3- Support
Fire
4- Labels
Fighting
5- Builder Work
6- FHC & rigid support
1- Insulation
MECH
2- Hookup & PICV
HVAC 3- Grilles Necks
Duct 4- Wrapping
5- Painting
6- Labels
7- BMS
8- Power Supply
9- Check Directions & Level
10- Hookup Insulation
11- Builder Work
12-Duct support & alignment
Ground Floor ZONE (A2) MEP /01/2020
Item Check Why? When? Note
1- Gate Valves
2- Support
Water
3- EWH Power Supply
Supply
4- WHA
5- Labels
6- Builder Work
1- Pipe Level, Slope
Drainage
2- Support
3- AC Drain
4- Connection W/FCU
5- Builder Work
6- Labels
Ground Floor ZONE (A3) MEP /01/2020
Item Check Why? When? Note
1- Painting
MECH 2- Sprinklers
3- Support
Fire
4- Labels
Fighting
5- Builder Work
6- FHC & rigid support
1- Insulation
MECH
2- Hookup & PICV
HVAC 3- Grilles Necks
Duct 4- Wrapping
5- Painting
6- Labels
7- BMS
8- Power Supply
9- Check Directions & Level
10- Hookup Insulation
11- Builder Work
12-Duct support & alignment
Ground Floor ZONE (A3) MEP /01/2020
Item Check Why? When? Note
1- Gate Valves
2- Support
Water
3- EWH Power Supply
Supply
4- WHA
5- Labels
6- Builder Work
1- Pipe Level, Slope
Drainage
2- Support
3- AC Drain
4- Connection W/FCU
5- Builder Work
6- Labels
Ground Floor ZONE (B1) MEP /01/2020
Item Check Why? When? Note
1- Painting
MECH 2- Sprinklers
3- Support
Fire
4- Labels
Fighting
5- Builder Work
6- FHC & rigid support
1- Insulation
MECH
2- Hookup & PICV
HVAC 3- Grilles Necks
Duct 4- Wrapping
5- Painting
6- Labels
7- BMS
8- Power Supply
9- Check Directions & Level
10- Hookup Insulation
11- Builder Work
12-Duct support & alignment
Ground Floor ZONE (B1) MEP /01/2020
Item Check Why? When? Note
1- Gate Valves
2- Support
Water
3- EWH Power Supply
Supply
4- WHA
5- Labels
6- Builder Work
1- Pipe Level, Slope
Drainage
2- Support
3- AC Drain
4- Connection W/FCU
5- Builder Work
6- Labels
Ground Floor ZONE (B2) MEP /01/2020
Item Check Why? When? Note
1- Painting
MECH 2- Sprinklers
3- Support
Fire
4- Labels
Fighting
5- Builder Work
6- FHC & rigid support
1- Insulation
MECH
2- Hookup & PICV
HVAC 3- Grilles Necks
Duct 4- Wrapping
5- Painting
6- Labels
7- BMS
8- Power Supply
9- Check Directions & Level
10- Hookup Insulation
11- Builder Work
12-Duct support & alignment
Ground Floor ZONE (B2) MEP /01/2020
Item Check Why? When? Note
1- Gate Valves
2- Support
Water
3- EWH Power Supply
Supply
4- WHA
5- Labels
6- Builder Work
1- Pipe Level, Slope
Drainage
2- Support
3- AC Drain
4- Connection W/FCU
5- Builder Work
6- Labels
Ground Floor ZONE (C) MEP /01/2020
Item Check Why? When? Note
1- Painting
MECH 2- Sprinklers
3- Support
Fire
4- Labels
Fighting
5- Builder Work
6- FHC & rigid support
1- Insulation
MECH
2- Hookup & PICV
HVAC 3- Grilles Necks
Duct 4- Wrapping
5- Painting
6- Labels
7- BMS
8- Power Supply
9- Check Directions & Level
10- Hookup Insulation
11- Builder Work
12-Duct support & alignment
Ground Floor ZONE (C) MEP /01/2020
Item Check Why? When? Note
1- Gate Valves
2- Support
Water
3- EWH Power Supply
Supply
4- WHA
5- Labels
6- Builder Work
1- Pipe Level, Slope
Drainage
2- Support
3- AC Drain
4- Connection W/FCU
5- Builder Work
6- Labels
Ground Floor ZONE (D) MEP /01/2020
Item Check Why? When? Note
1- Painting
MECH 2- Sprinklers
3- Support
Fire
4- Labels
Fighting
5- Builder Work
6- FHC & rigid support
1- Insulation
MECH
2- Hookup & PICV
HVAC 3- Grilles Necks
Duct 4- Wrapping
5- Painting
6- Labels
7- BMS
8- Power Supply
9- Check Directions & Level
10- Hookup Insulation
11- Builder Work
12-Duct support & alignment
Ground Floor ZONE (D) MEP /01/2020
Item Check Why? When? Note
1- Gate Valves
2- Support
Water
3- EWH Power Supply
Supply
4- WHA
5- Labels
6- Builder Work
1- Pipe Level, Slope
Drainage
2- Support
3- AC Drain
4- Connection W/FCU
5- Builder Work
6- Labels

Potrebbero piacerti anche