Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
RESERVOIR
A reservoir is an enlarged natural or artificial lake, pond or impoundment created using a dam or lock to store
water.
There are three basic types of
reservoir:
1. Costal Reservoir
2. Valley dam Reservoir
3. Service Reservoir
• Above Ground Reservoir
• Under Ground Reservoir (Covered Costal Reservoir Valley Dam Reservoir
and Open)
One of the most important issues
that builders confront with while
constructing concrete water
reservoirs is waterproofing.
The requirements, which must be
satisfied, differ according to
whether it is located above or
below ground. Above Ground Reservoir Under Ground Reservoir
SERVICE RESERVIOR
Geo Synthetic Materials Available: Available Sizes: Rolls of 100 x 6 meters, 100 X 7 meters
•Geomembrane Thickness : 100 to 1500 Micron
•Geotextile Market Price: Rs 145 / Sq.meter, 500 Micron thick
•Geonet Rs 195 / Sq.meter, 1500 Micron Thick
•Geogrid
•Geosynthetic clayliner
•GeoComposites
LINER INSTALLATION
1. SITE SELECTION :
Whenever possible, site selection should avoid areas where flooding or ground
water pressure can occur. The lining "bottom" should be well above the water
table. If the site selected is in an area where organics are in the soil, or if gases
can be generated by chemical reaction, the design must allow for venting.
2. SURFACE TREATMENT :
Surfaces should be level and free of all sharp rocks (all rock and stone greater
than .05 diameter), objects, vegetation and stubble. (Soil sterilization may be
necessary to kill roots and certain types of grasses.) The subgrade surface should
provide a unyielding foundation for the geomembrane with no sharp or abrupt
changes or break in grade. Proper compaction assures stability and support of the
liner.
3. SLOPES :
Side slopes should be no steeper than 3:1 whenever feasible. Slopes are usually
hand-raked to achieve proper smoothness.
Panels are rolled on 6" cores and can be unloaded using a 10' section of schedule
80 pipe and handling straps.
We also offer 12 mil tarps to cover and protect delivered liner rolls.
5. ANCHOR TRENCHES :
To secure the edges of the lining in an earthen pit, an "anchor trench" is dug. Anchor
trenches are approx. two foot wide by two foot deep (2' x 2') and one foot back from
the crest of the berm (standard trench dimensions and depth vary according to project
design)
Dirt removed should be raked out flat on the far side of the trench, away from the pit,
to be used to backfill after the liner edges are laid out in the anchor trench, while
allowing the panels to be unrolled along the berm.
Liner Deployment
6. SITE STRUCTURES :
Structures, piping, concrete, drains, and any associated work should be completed
prior to lining installation.
7. LINER DEPLOYMENT :
The roll is raised by a loader, forklift, or other lifting equipment, and then unrolled in
one direction, and unfolded in the other direction
8. PANEL PLACEMENT
Panel Placement
9. FIELD SEAMING
Air venting
To remove residual air from under the MIZUSHEET and air and
various gases generated in the base soil, install, as necessary, pieces
of air vent pipe under the slope. Install pieces of perforated pipe
under the slope from the bottom of the slope up to the crown of the
embankment at a distance of 20 m to 30 m from the adjacent pipe to
remove air from the shoulder of the slope. This is the standard
method. On some occasions, the bottom may be sloped at a gradient
of 1/500 to 1/200