DEPARTMENT OF BUILDING ENGINEERING AND MANAGEMENT,SPA,DELHI 5TH GROUP--PROJECT PLANNING AND SCHEDULING

RE-DEVELOPMENT OF PRAGATI MAIDAN INTO


INTEGRATED EXHIBITION CUM CONVENTION CENTRE

APOORV AGARWAL ANUBHA SINGHAL SANDEEP SINGH


THOUFEER MUHAMMED N RAYMON PRAKASH SHINEY ELIZABETH ABRAHAM
BRIEF INTRODUCTION

• NAME OF PROJECT: RE-DEVELOPMENT OF PRAGATI


MAIDAN INTO INTEGRATED EXHIBITION CUM
CONVENTION CENTRE
• PART CHOSEN: CONVENTION CENTRE
• SITE LOCATION: PRAGATI MAIDAN, NEW DELHI,11001
• PHASES:II Phases.
• SITE AREA: 53 Acres
• BUILT UP AREA: 3,71,612 SQM
• FAR ACHIEVED: 0.70
• PROJECT COST: RS 1260 cr
• NO. OF BLOCKS: 8
• DATE OF START: 2006, Ahead of Commonwealth
Games
• DATE OF COMPLETION: 2020 (estimated)
• PARKING: 4500 CARS (BASEMENT)

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
STAKEHOLDERS

ARCHITECT- ARCOP
ASSOCIATES(DELHI BASED),
AEDAS (SINGAPORE
BASED),CP KUKREJA

CONTRACTORS- LARSEN &


TOUBRO CONSTRUCTIONS
PMC- SHAPOORJI PALLONJI

CLIENT-Indian Trade STRUCTURAL CONSULTANT:


Promotion Organisation/NBCC

ELECTRICAL CONSULTANT-

PLUMBING CONSULTANT-

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SITE LOCATION

1 INDIA GATE

4 2 NATIONAL CRAFTS MUSEUM

6 3 ITO

BHAIRON MARG
3 5 PRAGATI MAIDAN 4 IG ARENA
2
PRAGATI MAIDAN
5 METRO STATION

6 NATIONAL ZOOLOGICAL PARK

METRO TRACK

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
ARCHITECTURAL APPRAISAL

RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC


SITE PLAN

SITE PLAN

PHASE-2

PHASE-2

1.CONVENTION
2 9 CENTRE.
2.EXHIBITION
PHASE-1 AREA.
1 7 3.PRAGATI
MAIDAN PLAZA
3 4.HOTEL.
8 5.SLOPING GREENS
5 6 6.BUSINESS CENTRE
7.F&B
8.ADMIN BLOCK
9.EXHIBITION
HALLS.

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
CHOSEN SITE

SITE PLAN

VEHICULAR ENTRY/ EXITS


PEDESTRAIN ENTRY/ EXITS

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SITE PLAN

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SCOPE OF WORK

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
AREA STATEMENT

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
INTERNAL MOVEMENT PATTERN

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SCOPE OF WORK AT BASEMENT LEVEL

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
CONVENTION CENTRE VIEWS

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
PLAN AT LVL +1.00M PART-1

PERFORMANCE SPACES

MEETING ROOM/FACILITIES
CUTOUTS/SHAFT

COURTYARD/RAMP/FOYER

SERVICE SPACES

VERTICAL CIRCULATION

TOILETS

LOBBY &CIRCULATION AREA

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
PLAN AT LVL +1.00M PART-2

MEETING ROOM/SHOPS
CUTOUTS/SHAFT

COURTYARD/RAMP/FOYER

TOILETS

LOBBY &CIRCULATION AREA

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
PLAN AT LVL +6.40M PART-1

PERFORMANCE SPACES

MEETING ROOM/FACILITIES
CUTOUTS/SHAFT

COURTYARD/FOYER

SERVICE SPACES

VERTICAL CIRCULATION

TOILETS

LOBBY &CIRCULATION AREA

THEATRE

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
PLAN AT LVL +6.40M PART-2

F&B ,BUSINESS CENTRE

LANDSCAPE AREA

COURTYARD/RAMP/FOYER

LOBBY &CIRCULATION AREA

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
PLAN AT LVL +15.40M

PERFORMANCE SPACES

MEETING ROOM/FACILITIES
CUTOUTS/SHAFT

COURTYARD/RAMP/FOYER

SERVICE SPACES

VERTICAL CIRCULATION

TOILETS

LOBBY &CIRCULATION AREA

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
PLAN AT LVL +22.30M

PERFORMANCE SPACES

MEETING ROOM/FACILITIES
CUTOUTS/SHAFT

COURTYARD/RAMP/FOYER

SERVICE SPACES

VERTICAL CIRCULATION

TOILETS

LOBBY &CIRCULATION AREA

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
PLAN AT ROOF LVL +32.30M

SERVICE SPACES

VERTICAL CIRCULATION

TERRACE GARDEN

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SECTIONS

SECTION A-A

SECTION B-B

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
ELEVATIONS

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
FAÇADE DETAILS

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SECTIONAL DETAILS

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SERVICE APPRAISAL

RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC


HVAC

CHILLER PLANT
CONVENTION CENTRE

CHILLER PLANT
ADMINISTRATION

SERVICE APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
PLANT ROOM –CONVENTION CENTRE

3 NOS CENTRIFUGAL CHILLER OF


CAPACITY 850TR EACH

SIZE : 5.05MX2.6MX3.5M EACH

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
HVAC LAOUT-SECTION

COOLING TOWER

CHILLER PLANTS

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
MAIN RECEIVING STATION LAYOUT

SERVICE APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
ELECTRICAL

ELECTRICAL
SUBSTATION 2
2 TRANSFORMER -1250 KVA

ELECTRICAL
SUBSTATION 1
3 TRANSFORMER -1500 KVA

ELECTRICAL SUBSTATION 7
2 TRANSFORMER -630KVA

SERVICE APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
ELECTRICAL

STRUCTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
PLUMBING

WATER TANKS

SERVICE APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
PLUMBING

DOMESTIC WATER TANK 5KL WATER TANK 5KL


FIRE WATER TANK 20 KL

ARCHITECTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
WATER TANKS
PUMP ROOM

FIRE TANKS
(2NOS of 158 KL each)
RAIN WATER TANK
(2 NOS of 90 KL each)

TREATED WATERTANK
(2NOS of 90 KL each) FIRE TANKS (2NOS of 158 KL each)

RAIN WATER TANK (2 NOS of 90 KL each)

TREATED WATERTANK (2NOS of 90 KL each)

SERVICE APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
PUMPS FOR CONVENTIONAL CENTRE & ADMINISTRATION
RAIN WATER TANK -100KL
11Mx4.57Mx4M

FIRE TANK -225KL


11Mx8.2Mx2.5M
1.6M WIDE PASSAGE

PUMP ROOM
37.37MX8M

PUMP ROOM
37.37MX8M
1.6M WIDE PASSAGE

TREATED WATER TANK -200KL


FIRE TANK -225KL
11Mx4.57Mx4M
11Mx8.2Mx2.5M

ROAD LVL 0 M

WATER LVL -0.5M


WATER DEPTH -4.5M WATER DEPTH -3.0M
FILLING 0.5M
PUMPROOM LVL -5.4M

SERVICE APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
STRUCTURAL APPRAISAL

RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC


GENERAL OVERVIEW OF SOIL INVESTIGATION
1. DEPTH, SIZE, NO. OF BOREHOLES.
• 25 nos of Boreholes carried out at the site of Pragati Maidan.
• size of borehole shall be min. (100-150mm Ø )
• Boreholes under the convention center block have depth 25 M below ground level.

2. OBSERVATIONS 3. RECOMMENDATIONS
 WATER TABLE  TYPE OF FOUNDATION
• The area of site has the water table at 3.0 M. • Considering the anticipated loads due to the
• The ground water table was encountered during building as well as seismic loads , proposed
borehole drilling, thus there will be a building structural members can be supported . .
requirement of dewatering during the over Pile foundation.
construction of the foundation.  DEPTH OF FOUNDATION
 BEARING CAPACITY • In view of Single Basement provision i.e. For parking
• Conducted Average ‘N’ value –20 and underground tunnel, foundation will be placed
• Raft foundation has to be designed for at a depth of 7.0 m below existing G.L.
Qnet-17.5t/sq.m.  ALLOWABLE BEARING CAPACITY
Qgross-27.5t/sq.m • Gross allowable bearing capacity value of 23.4
• For pile foundation following shear strength ton/sq.m.
parameters are to be considered: • Net allowable bearing capacity value of 17.5
Cohesion (c)-2 t/sq.m ton/sq.m.
Angle of internal friction (Φ) -33° • Modulus of Subgrade reaction value of 2.00
• Shear strength , Q = 5.5 kg./sq.cm. kg./cub.cm. may be adopted for design of raft
• The weighted average specific gravity-2.69 foundation.

STRUCTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
COLUMN LAYOUT OF LEVEL 1
Sample Calculation for identifying the number of piles under the column

Load bearing capacity of a single pile 4824 KN

Column C2/C11 are carrying the maximum load

Load Carried by C2/C11 column 45828 KN

No. of piles to be provided under C2/C11 column 10 nos


No. of piles to be provided under C4/C5 column
4 nos
No. of piles to be provided under C14/C16 column
6 nos

STRUCTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
COLUMN LAYOUT OF LEVEL2

SIZES OF STRUCTURAL MEMBERS

COLUMN SIZES

STRUCTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
COLUMN LAYOUT OF ROOF LEVEL

SIZES OF STRUCTURAL MEMBERS

COLUMN SIZES

STRUCTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
PILE FOUNDATION CALCULATIONS

Calculations for Pile Foundation

Angle of Internal Friction 33 degree

Cohesion 20 KN/m3

Diameter 0.6 m

Length of pile 25 m

Dry Density 20.05 KN/m3

Submerged Density 11.139 KN/m3

Grade of Concrete Pile 35 Mpa

Grade of Reinforcement 500 MPa

Load Bearing Capacity of pile using (IS:2911 Part 1/Sec 2) 4824 KN

Longitudinal Reinforcement 0.005652 sq.m

Use 13#24mm dia bars .

Use 10mm lateral ties @ 250mm c/c. In the upper and lower 180cm length of the pile

reduce the pitch to 100mm c/c.

Depth of Pile cap 600 mm

Use 12mm bars @ 100mm c/c both ways.

STRUCTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
RAFT FOUNDATION CALCULATIONS

Maximum Size of column = 1200mm X 1800mm


Area of column = 2160000sq.mm
Area of steel reinforcement = 4%
Steel Reinforcement Grade = Fe415
Concrete Grade = M25
Load Carrying Capacity = 46000KN
Distance b/w two columns = 10450mm
Concrete Grade for Raft = M30
Steel Reinforcement Grade for Raft = Fe500
The depth of the raft shall be governed by 2-way shear
Shear Strength of Concrete = 1.37N/mm2
Shear force = 46000KN
Adopted effective depth = 2300mm
Adopted overall depth = 2400mm
Bending Moment = 240350KN.m
Area of reinforcement = 6896sq.mm/m
Provide 30mm bars @ 100mm c/c at top and bottom in both directions.

STRUCTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
PILE FOUNDATION

PILE CONCRETE IS PUT BEFORE COMPLETE


EXCAVATION WHICH RESULTS IN EXTRUDED PILES

COMBINATION OF 3 TO 4 PILES WITH PILE CAPS


HAS BEEN USED FOR STRUCTURAL SUPPORT

PILE WILL BE CUT FROM THIS END AND THE


REINFORCEMENT WILL BE JOINED WITH THE PILE CAP

PILE CAPS HAS BEEN USED FOR STRUCTURAL SUPPORT

PILE FOUNDATION USED IN THE SITE. PILE CONCRETE IS PUT BEFORE COMPLETE EXCAVATION WHICH RESULTS IN EXTRUDED PILES.

STRUCTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
DEWATERING-WELL POINT DEWATERING

CALCULATION FOR DEWATERING

COEFFICIENT OF PERMEABILITY 0.0001 m/sec

RADIUS OF WELL 0.5 m

RADIUS OF INFLUENCE 160 m


DRAWDOWN REQUIRED AT INFLUENCE
7 m
POINT

DRAWDOWN REQUIRED AT THE WELL 23.333 m

173.33
FLOW RATE REQUIRED cumec
3
43.333
FLOW RATE OF ONE PUMP cumec
3
NO. OF PUMPS REQUIRED 2 Nos

 Dewatering is done through well point


dewatering system. Water is sent to the
nearby corporation sewer line.

 Individual small well points, are generally


40 to 50mm in diameter and is 7 metres
in length

STRUCTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
WATER PROOFING

BASEMENT WATER PROOFING REATAINING WALL WATER PROOFING

REATAINING WALL WATER PROOFING BASEMENT WATER PROOFING


FOUNDATION SYSTEMS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
WATER PROOFING DETAILS

1. PRIMER
2. WATERPROOFING PIPE PENETRATIONS
3. PREPARING WALL/FLOOR
4. INSTALLING FILLETS
5. WATERPROOFING LAYER
6. PROTECTION OF THE WATERPROOFING
LAYER

• The use of bituminous products belongs to the standard solutions for the positive side waterproofing of
basements.
• The systems are applied in a paste-like form and are therefore seamless. They are easy and safe to use
and have crack bridging properties. On clean, solid, stable, gypsum free mineral substrates is applied as
a primer. This immobilizes salts present in the substrate and the substrate is solidified. When preparing
to waterproof on top of old bituminous coatings Bitumen Primer is used.

FOUNDATION SYSTEMS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SECTIONS AT A-A &C-C
Section at A-A

TRUSS MEMBER SIZES


Section at C-C
UC 305X305X158

UC 35X309X136.9

UC 305X305X283 -P20

UC 305X305X282.9
UC 305X305X283 -P25

UC 305X305X136.9
UC 305X305X240

UC 450X450X32

UC 450X450X32
UC 450X450X40

UC 356X368X177 -P16

STRUCTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
OBSERVATION AND INFERENCES
Section at B-B

OBSERVATION AND INFERENCES


• The shear wall has been provided which has thickness of 450mm.
Truss M

Truss H Truss K

450mm 600mm
450mm

450mm
450mm
450mm

STRUCTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
DECK FLOORING DETAIL

STRUCTURAL APPRAISAL
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
DEPARTMENT OF BUILDING ENGINEERING AND MANAGEMENT,SPA,DELHI 5TH GROUP--PROJECT PLANNING AND SCHEDULING

CONSTRUCTION LOGIC
IIEC,PRAGATI MAIDAN

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
ACCESS ROADS

ACCESS ROAD

LIGHT VEHICULAR ENTRANCE

HEAVY VEHICULAR ENTRANCE

PEDESTRAIN ENTRANCE

MATHURA ROAD

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
MOVEMENT INSIDE SITE

ACCESS ROAD

MOVEMENT OF DUMPER

MOVEMENT OF MATERIALS

LABOUR ACCESS

MOVEMENT OF LIGHT VEHICLE

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
TOWER CRANE AND SITE ZONNG

ACCESS ROAD

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
3D VIEW
CONVENTION CENTRE EXCAVATION BACK FILL SOIL

TOWER CRANE RAMPS


CUTTING AND BENDING YARD

QC AND MT LAB
SAFETY OFFICE
TRAINING
CANTEN
WORKSHOP
STORAGE

STEEL YARD SCRAP YARD


SCAFFOLDING RO PLANT
STEEL YARD YARD
NBCC SITE OFFICE BATCHING PLANT

EXCAVATED SOL CANTEEN


STP DG SET
SHAPOORJI SITE OFFICE

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
BARICADING
BARRICADING – 10 METRE HIGH

BARRICADING

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SOIL STABILISATION TECHNIQUE--SHEET PILING FOR EXCAVATION
CANTILIVER SHEET PILING

SHEET PILING

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
ROAD NETWORKS LAID

EXCAVATION EXCAVATION
EXCAVATION AREA upto 3 m upto 6.5m

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
IST PHASE EXCAVATION AREA OF BASEMNET AND CONVENTION AREA

EXCAVATION EXCAVATION
EXCAVATION AREA upto 3 m upto 6.5m

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
1ST PHASE EXCAVATION UPTO -3 M RAMP

RAMP

EXCAVATION EXCAVATION
EXCAVATION AREA upto 3 m upto 6.5m

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
1ST PHASE EXCAVATION AREA UPTO -3 METRE RAMP
RAMP

2ND PHASE EXCAVATION AREA

EXCAVATION EXCAVATION
EXCAVATION AREA upto 3 m upto 6.5m

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
1ST PHASE EXCAVATION COMPLETED TO -6.5 METRE
CONVENTION AREA EXCAVATION COMPLETED TO -3 METRE

2ND PHASE EXCAVATION UPTO -3 METRE

RAMP

EXCAVATION EXCAVATION
EXCAVATION AREA upto 3 m upto 6.5m

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
1ST PHASE EXCAVATION COMPLETED TO - 6.5 METRE
CONVENTION AREA EXCAVATION COMPLETED TO -3 METRE

2ND PHASE EXCAVATION COMPLETED TO -6.5 METRE

EXCAVATION EXCAVATION
EXCAVATION AREA upto 3 m upto 6.5m

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
FINAL STATUS AFTER EXCAVATION

EXCAVATION EXCAVATION
EXCAVATION AREA upto 3 m upto 6.5m

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
CONSTRUCTION SEQUENCE

Excavation

Pile Casting

Column Casting
CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
CONSTRUCTION SEQUENCE

Backfilling

Steel Slab

Basement & Mezzanine


CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
CONSTRUCTION
CONSTRUCTION SEQUENCE
SEQUENCE

RCC Structure

Interior

Interior & Roof


CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
DEWATERING-WELL POINT DEWATERING
CALCULATION FOR DEWATERING

COEFFICIENT OF PERMEABILITY 0.0001 m/sec

RADIUS OF WELL 0.5 m

RADIUS OF INFLUENCE 160 m

DRAWDOWN REQUIRED AT INFLUENCE POINT 7 m

DRAWDOWN REQUIRED AT THE WELL 23.333 m

FLOW RATE REQUIRED 173.333 cumec

FLOW RATE OF ONE PUMP 43.3333 cumec

NO. OF PUMPS REQUIRED 2 Nos

DEWATERING IS DONE THROUGH WELL


POINT DEWATERING SYSTEM.WATER IS
SENT TO THE NEARBY CORPORATION
SEWER LINE.

INDIVIDUAL SMALL WELL POINTS, ARE


GENERALLY 40 TO 50MM IN DIAMETER
AND IS 7 METRES IN LENGTH

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SOIL CALCULATIONS
EXCAVATED SOIL CALCULATIONS BACK FILL SOIL CALCULATIONS
Exavation Area of Depth of Volume of Capacity of Cycles of
Zone Excavation(sq.m.) Excavation(m) Excavation(cum) dumper(cum) dumper Backfill Zone Volume of soil(cum.)

Basement Area 50564 6.5 328666 20 16433 Repose soil 407

Convention Convention Center 70523


25444 3 76332 20 3817
Center
Extra Excavation 1352
Piles 846 25 21150 20 1058

Total Cycles of Total Backfill 72282


25,798
Dumper

EQUIPMENT AND LABOUR REQUIREMENT – EXCAVATION OVERALL AVERAGES


TOTAL EXCAVATED SOIL :3,86,962.63 M3
EXCAVATION FOR STAGE 1 (Area : 35363.6 m2)
• CAPACITY OF ONE HYDRAULIC EXCAVATOR = 250 CUM/DAY NO: OF DUMER CYCLE : 25,798 TIMES
• TOTAL EARTH TO BE EXCAVATED IN ZONE 1 = 2,29,862.75 CUM
• TOTAL NO. OF EXCAVATORS TO BE DEPLOYED ON SITE = 6 TOTAL TIME OF COMPLETION OF PROJECT : 2 YEAR
• TOTAL TIME TAKEN = 160 DAYS
• DUMPER CYCLES= 95 NOS/DAY EXPECTED COMPLETION OF EXCAVATION : 300 DAYS
• CAPACITY OF 1 BELDAR = 25 CUM/DAY
• NO. OF BELDARS TO BE DEPLOYED ON SITE (25 CUM/DAY) = 60 NOS EXCAVATED SOIL IN ONE DAY :1298.87 M3
• NO. OF COOLIES TO BE DEPLOYED ON SITE 4.8 CUM/DAY) = 300 NOS
NO: DAMPER CYLCE REQUIRED
(TATA PRIMA LX) :87 NOS/DAY
EXCAVATION FOR STAGE 2 (Area : 35807.6 m2)
• TOTAL EARTH TO BE EXCAVATED IN ZONE 1
VOLUME OF EXCAVATED SOIL AREA
CONVENTION CENTRE = 64,841.55 CUM
FOR FOR 5 DAYS. : 6500 M3
BASEMENT AREA = 92,258.33 CUM
TOTAL =1,57,099.88 CUM
AREA OF EXCAVATED SOIL
• TOTAL NO. OF EXCAVATORS TO BE DEPLOYED ON SITE = 5
FOR STORING UPTO 8 METRE
• TOTAL TIME TAKEN = 140 DAYS
OF VOLUME OF 5 DAY EXCAVATION : 812 M2
• DUMPER CYCLES= 75 NOS/DAY
• NO. OF BELDARS TO BE DEPLOYED ON SITE(25 CUM/DAY) = 48 NOS
BACK FILL SOIL AREA REQUIRED
• NO. OF COOLIES TO BE DEPLOYED ON SITE(4.8 CUM/DAY) = 235 NOS
FOR STORAGE :9035 M2

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
CONCRETE CALCULATION
VOLUME OF CONCRETE
VOLUME OF CONCRETE
TYPE TOTAL NO AREA HEIGHT VOLUME
RECTANGULAR COLUMNS 26 2 36 1872
SQUARE COLUMNS 15 6 36 3240
CIRCULAR COLUMNS 191 2.1 36 14439.6
PILES 696 0.2826 25 4917.24
PILE CAP 232 12.5 3 8700
DECK FLOORING 4 23267 0.15 13960.2
BASEMENT SLAB 1 50527 0.3 15158.1
STAIRCASE 22 27 0.15 89.1
BASEMENT RAFT 1 50527 0.9 45474.3
TOTAL IN M3 107850.54

ADDITIONAL REQUIREMENT OF CONCRETE IS BY


RMC. AT NIGHT MORE THAN 100 VEHICLE
REACH AT SITE. RMC WILL REDUCE THE
POLLUTION FROM BATCHING PLANTS.

CAPACITY TRANSIT MIXER= 6-16CUM

CAPACITY = 30cum per hour


CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SERVICE CALCULATIONS

CALCULATION FOR WATER REQUIREMENT CONSTRUCTION PHASE CALCULATION FOR WATER SUPPLY REQUIREMENTS FOR CONVENTION
CENTRE
DIAMETER OF PIPE FOR CURING 0.025 m
TOTAL POPULATION 26334 NOS
NO OF PIPES FOR CURING 2 nos
VELOCITY OF WATER IN PIPE 6 m/sec
WATER REQUIRED PER HEAD 15 LPCD
0.00294
FLOW RATE IN ONE PIPE cumec
38
TOTAL WATER REQUIRED 395000 LITRE
0.00588
TOTAL FLOW RATE cumec
75
CAPACITY OF WATER TANK 400000 LITRE
3
AMOUNT OF WATER REQUIRED FOR CURING PER DAY 84.78 m

NO OF PERSONS WORKING AT THE SITE PER DAY 400 nos CALCULATION FOR SEWAGE TREATMENT PLANT

AMOUNT OF WATER REQUIRED PER HEAD 0.015 m3 TOTAL DOMESTIC WATER DEMAND 400000 LITRE
AMOUNT OF WATER REQUIRED BY THE WORKERS FOR
6 m3
DOMESTIC USE ESTIMATED SEWAGE 360000 LITRE
TOTAL AMOUNT OF WATER REQUIRED PER DAY 90.78 m3
VOLUME REQUIRED FOR STP 360 M3
TOTAL AMOUNT OF WATER REQUIRED PER DAY IN LITRES 90780 LITRES

CALCULATION FOR FIRE WATER DEMAND LIQUID DEPTH 2.5 M

POPULATION IN THOUSAND 26.334 FREE BOARD 0.5 M


FIRE WATER DEMAND PER MINUTE (ACC. TO BOSTON 29060.6 LITRE/
FORMULA) 3 MIN AREA REQUIRED 144 M2
DURATION OF WATER SUPPLY 15 MIN
435909. LENGTH 12 M
TOTAL WATER DEMAND LITRE
4
CAPACITY OF FIRE WATER TANK PROVIDED 450000 LITRE BREADTH 12 M

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
CONCRETE MIX DESIGN

Mix Requirements
Grade of Concrete M35
• The Bureau of Indian Standards,
Slump 125-175
recommended a set of
procedures for design of concrete Exposure Type Moderate
mix mainly on the work done in Maximum Size of Aggregate 20 mm
national laboratories.
Target Mean Strength 47 MPa
• Following Standards have been
used for the concrete mix design Maximum W/C Ratio as per exposure 0.4

IS 10262 – 2009 : Guidelines Material


for Concrete Mix Design Specific Gravity of Cement 3.15
Proportioning
Specific Gravity of Coarse Aggregate 20mm 2.796
IS 456 – 2000 : Specific Gravity of Coarse Aggregate 12-15mm 2.749
Plain and Reinforced Concrete –
Specific Gravity of Admixture (SIKAMENT 5114NS-SNF
Code of Practice 1.27
Based)
Specific Gravity of Fine Aggregate 2.54
1.4% by wt of
Quantity of Admixture
cement
Type of Cement Used – Ordinary Portland Cement 53 Grade (IS 12269 : 1987)
Admixture Used – SIKAMENT 5114NS-SNF Based

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
CONCRETE MIX DESIGN
Concrete Batch Mix Plant Requirements
Concrete Mix Calculation
Capacity 30 m3/hr
Volume of Concrete 1 m3
Weight of Cement 400 kg Weight of Cement required per hour 12000 kg

Weight of Water 160 kg Volume of water required per hour 4.8 m3


Weight of Admixture 5.6 kg 0.132
Volume of admixture required per hour m3
27
Volume of Cement 0.127 m3
Volume of fine aggregate required per hour 8.502 m3
Volume of Water 0.16 m3
Volume of 20mm coarse aggregate required 5.316
0.0044 m3
Volume of Admixture m3 per hour 6
09
Volume of 12.5mm coarse aggregate
Volume of Total Aggregate 0.7086 m3 7.44 m3
required per hour
Volume of Fine Aggregate (40) 0.2834 m3 28800
Weight of cement required in a day kg
0
Volume of Coarse Aggregate(60) 0.4252 m3
Volume of water required per day 115.2 m3
0.1772
Volume of 20mm Coarse Aggregate(25) m3 3.174
2 Volume of admixture required per day m3
48
Volume of 12.5mm Coarse Aggregate(35) 0.248 m3
204.0
Volume of fine aggregate required per day m3
Weight of Fine Aggregate 720 kg 48
Volume of 20mm coarse aggregate required 127.5
Weight of 20mm Coarse aggregate 495 kg m3
per day 984
Wight of 12.5mm coarse aggregate 682 kg Volume of 12.5mm coarse aggregate 178.5
m3
required per day 6

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
EQUIPMENTS
TOWER CRANE--MATERIAL
HANDLING EQUIPMENT ROLLER OR COMPACTOR

MAXIMUM UNSUPPORTED HEIGHT: MIN TURNING RADIUS: 3.9 M


80 METRE(265 FEET). TRANSVERSE MOVING
MAXIMUM REACH: 70 METRE(230 DISTANCE: 200 MM
FEET). CLIMBING ABILITY: 30%.
MAXIMUM LIFTING POWER: 18 MIN GROUND CLEARANCE :
METRIC TON. 410 MM
COUNTER WEIGHTS: 16.3 METRIC WHEEL BASE : 4000MM
TON. OPERATING WEIGHT : 13100
FOR HOISTING HEAVY MATERIALS LIKE KG
STEEL TRUSSES, FRAMES ETC.
CONCRETE MIXER
HYDRA MOBILE CRANE
MIXING UNIT: 500 LITERS
CAPACITY: 15-20 TONS.,20-25 TON DRUM CAPACITY
AND GREATER THAN 25 TON CONCRETE OUTPUT: 4 M3
MAXIMUM HEIGHT: 20-40 FEET,40-60 PER BATCH
FEET,60-80 FEET DISCHARGE: OVER 2 M TO
POWER SOURCE : THE FOUR SIDES OF THE
HYDRAULIC,DIESEL,MECHANICAL. VEHICLE

MOBILE BATCHING PLANT NEEDLE VIBRATOR

DELIVERY DISTANCE VOLTAGE: 200-400V


HORIZONTAL: 320 M,240 M,300 AUTOMATION GRADE:
M,400 M AUTOMATIC
VERTICAL: 80 M,60 M,75 M,100 M SPEED: 14000VPM

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
EQUIPMENTS
PLATE VIBRATOR

WEIGHT 93 KG
COMPACTING DEPTH 30 CM
TRAVELLING SPEED 0-30 M/MIN
ENGINE POWER: 5-5.5 HP

BACK HOE LOADER

OPERATING WEIGHT : 8.4 TONS


BUCKET CAPACITY: 0.8-1.2 M3
EXCAVATOR CAPACITY: 0.2-0.25 M3
USEFUL FOR EXCAVATING TRENCHES BELOW THE MACHINE
LEVEL AND USING FRONT BUCKET LOADING, UNLOADING AND
LIFTING OF MATERIALS CAN BE DONE

CONCRETE PUMB

VERTICAL REACH OF BOOM: 41.9 M


HORIZONTAL REACH OF BOOM: 38 M
PUMBING RATE : 140M3/HOUR
CONCRETE PRESSURE: 70 BAR
CYLINDER LENGTH: 2100 MM

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
EQUIPMENTS

MOVABLE TOWER CRANE OF 750 METRIC TONNE OF 2 TYPES OF BOOM LENGTH VERTICAL AND HORIZONTAL
CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
EQUIPMENTS

TOWER CRANE OF BOOM LENGTH 45 M USED AT SITE DIFFERENT TYPES OF LIFTING CRANES USED

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
EQUIPMENTS

HYDRA MOBILE CRANE USED AT SITE

TOWER CRANE OF BOOM LENGTH 45 M USED AT SITE HYDRA MOBILE CRANE USED AT SITE

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SAFE SITE PRACTICES

SAFE SITE PRACTICES(NATIONAL BUILDING


CODE 2016)
AND GRIHA CONSIDERATON

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
NBC 2016 CLAUSE 8.2 - STORAGE, STACKING AND HANDLING OF MATERIALS

CEMENT
• Stored in a building or a shed which is dry,
leak-proof and moisture-proof
• Bags to be kept at about 150 mm to 200
mm clear above the floor
• Space of 600 mm minimum shall be left
around between the exterior walls and the
stacks
• Height of stack shall not be more than 10
bags to prevent the possibility of lumping
up under pressure
• Width of stack shall be not more than four
bags length or 3 m

BRICKS
• Bricks shall be stacked in regular tiers
• Stacks shall be 50 bricks long, 10 bricks high
and not more than 4 bricks in width
• Bricks being placed, two at a time along the
width of stack
• Clear distance between adjacent stacks
shall not be less than 0.8 m
SOURCE: NBC 2016

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
NBC 2016 CLAUSE 8.2 - STORAGE, STACKING AND HANDLING OF MATERIALS

STEEL
• Ends of bars and sections of each class be
painted in distinct separate colours
• Bars of different classification, sizes and
lengths shall be stored separately
• Structural steel of different sections, sizes and
lengths shall be stored separately
• Stored above ground level by at least 150 mm
upon platforms, skids or any other suitable
supports to avoid distortion of sections IMAGE SOURCE:
GRIHA V 2015

CONCRETE BLOCKS
• Height of stack shall not be more than 1.2 m
• Length of stack shall not be more than 3.0 m
• Width shall be of two or three blocks
• Blocks cured for 28 days only should be
received at site
• In case of uncured blocks, they shall be cured
at site
IMAGE SOURCE:
www.civilblog.org

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
GRIHA CONSIDERATIOONS

SPECIAL CONDITIONS FOR GREEN BUILDING

GRIHA- the National Rating System will evaluate the environmental performance of a
building holistically over its entire life cycle, thereby providing a definitive standard for what
constitutes a ‘green building’.

A building is assessed based on its predicted performance over its entire life cycle – inception
through operation. The stages of the life cycle that have been identified for evaluation are the
preconstruction, building design and construction, and building operation and maintenance
stages.

CONSTRUCTION STAGE:

1. SOIL CONSERVATION
2. WATER CONSERVATION
3. SOLID WASTE MANAGEMENT
4. AIR AND NOISE POLLUTION

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
GRIHA CONSIDERATIOONS

4. SOLID WASTE MANAGEMENT


• .

Use different coloured bins for collecting different


Minimize the disposal of construction waste. categories of waste from the building.
Construction and demolition waste is reused,
recycled or salvaged for later reuse

Allocate separate space for the collected waste Provide at least, the minimum level of sanitation/safety
before transferring it to the recycling/disposal facilities for construction workers. provide clean
stations. drinking water

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
WASTE DISPOSAL ON SITE

The solid waste to be


generated during the
construction phase
• excavated
materials
• used bags
• Bricks
• Concrete
• MS rods
• Tiles
• wood

• Waste shall be deposited at collection center made at the site and will be transported and
disposed to the Burari recycling plant of MCD by approved agency.
• As inert it shall be used to fill material for low -lying areas, landscaping, Road Making etc.
• Finer grade can be molded into blocks and slabs with appropriate binder.

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
GRIHA CONSIDERATIOONS

1. SOIL CONSERVATION
• All topsoil removed during construction is saved and reused.
• Use a formal Site Sediment and Erosion Control Plan to ensure that storm water does
not erode site soil and contaminate local water bodies. This may mean maintaining
site landscape throughout construction or providing ground cover, or it might mean
phasing construction, stabilizing soils, or using other measures. Controlling erosion
with mulch or grass.
• Preserve and protect the landscape during construction/compensatory depository
forestation. Replant, onsite, trees in the ratio 1:3 to those removed during
construction.

2. WATER CONSERVATION
• Reduce landscape water requirement. Landscape using native species and reduce
lawn areas while enhancing the irrigation efficiency, reduction in water requirement
for landscaping purposes.
• Efficient water use during construction. Use materials such as pre-mixed concrete for
preventing loss during mixing. Use recycled treated water and control the waste of
curing water.

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
GRIHA CONSIDERATIOONS

3. PREVENT AIR AND NOISE POLLUTION


• Reduce air pollution during construction. Ensure proper screening,
covering stockpiles, covering brick and loads of dusty materials,
wheel-washing facility, water spraying.
• Develop and implement an Indoor Air Quality Construction Plan.
This should include the below features:
• Plan and implement construction sequencing that requires
absorptive materials (like insulation, carpeting, ceiling tiles,
gypsum, textile materials) to be installed after drying or curing of
materials that may emit chemicals detrimental to IAQ.
• Ensure supply and return air duct systems are clean and verified
before occupancy. This can be done by sealing the air ducts during
construction, or by flushing them out before occupancy. According to NGT guidelines,
• Conduct a complete building flush out using new filters and 100% construction material and debris are
outdoor air for a minimum of one week before occupancy. supposed to be covered with
• All vehicles, equipments and machinery used for construction are tarpaulin while the site itself should
regularly maintained and confirm that emission levels comply with have wind breakers on all sides. The
env. Emission standards. guidelines also state that trucks
• When dust ladden material is to be stored or handled, measures carrying material should be suitably
are taken to suppress the dust produced by such storing or covered and the area for debris
handling and suitable personal protective equipment are supplied storage physically demarcated.
to and used by the building workers working for such storing or
handling.

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SEWAGE TREATMENT TECHNOLOGY

Technology Proposed- MBR (Membrane Bio Reactor)

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
RAIN WATER HARVESTING AND STORM WAT

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
Sewer System
• The alignment and slope of the sewer line will follow the road network, drains
or natural ground surface and will be connected to the trunk sewers.
• The discharge point will be a treatment plant, a pumping station, a water
course or an intercepting sewer. Pumping stations would be provided at places
where the natural slope of the terrain is insufficient to permit gravity flow or
the cost of excavation is uneconomical to do the same

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SITE PHOTOS

PILES AT SITE BARRICADING

VEHICULAR MOVEMENT PEDESTRIAN ENTRY


CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SITE PHOTOS

TOWER CRANES AT SITE EXCAVATION AND DEWATERING

TOWER CRANES AT SITE CONVENTON CENTRE CONSTRUCTION WIP

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
BARRICADING

SEPERATED PATHWAYS FOR PEDESTRIAN SEPERATED PATHWAYS FOR PEDESTRIAN

TOWER CRANES AT SITE STORAGE AREAS

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SITE PHOTOS

DRINKING WATER AREA DG SET

TOWER CRANES AT SITE SITE INSIDE BARRICADING


CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SITE
SITEVISIT
PHOTOS

CONSTRUCTION LOGIC
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
DEPARTMENT OF BUILDING ENGINEERING AND MANAGEMENT,SPA,DELHI 5TH GROUP--PROJECT PLANNING AND SCHEDULING

WBS/ACTIVITY LISTING
IIEC,PRAGATI MAIDAN

APOORV AGARWAL ANUBHA SINGHAL SANDEEP SINGH


THOUFEER MUHAMMED N RAYMON PRAKASH SHINEY ELIZABETH ABRAHAM
1. SITE PREPARATION

(CONVENTION CENTRE & BASEMENT)


2. SUB STRUCTURE

IECC, PRAGATI MAIDAN


3. SUPER STRUCTURE

4. SERVICES

5. FINISHING

6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SITE PREPARATION

1.1 SITE & VEGETATION CLEANING

1.2 SITE BARRICADING

1.3 DEMARCATION OF EXCAVATION


1. SITE PREPARATION BOUNDARY

IECC, PRAGATI MAIDAN (CONVENTION CENTRE


& BASEMENT) 2. SUB STRUCTURE 1.4 SETTING UP TEMPORARY SERVICES

3. SUPER STRUCTURE 1.5 RESOURCE MOBILISATI0ON

4. SERVICES

5. FINISHING

6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SITE PREPARATION

1.1 SITE & VEGETATION CLEANING 1.4.1 SETTING OF SITE OFFICE

1.2 SITE BARRICADING 1.4.2 SEDIMENTATION TANK

1.3 DEMARCATION OF EXCAVATION


1. SITE PREPARATION 1.4.3 MOBILE TOILETS
BOUNDARY
IECC, PRAGATI MAIDAN (CONVENTION CENTRE

2. SUB STRUCTURE 1.4 SETTING UP TEMPORARY SERVICES 1.4.4 ELECTRIC & WATER SUPPLY
& BASEMENT)

3. SUPER STRUCTURE 1.5 RESOURCE MOBILISATI0ON 1.4.5 MEDICAL & SAFETY OFFICE

1.4.6 WORKSHOP & MATERIAL TESTING


4. SERVICES
LAB

5. FINISHING 1.4.7 TEMPORARY ACCESS ROAD

6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SITE PREPARATION

1.1 SITE & VEGETATION CLEANING

1.2 SITE BARRICADING

1.3 DEMARCATION OF EXCAVATION


1. SITE PREPARATION
BOUNDARY
IECC, PRAGATI MAIDAN (CONVENTION CENTRE

1.5.1 SETTING UP TOWER CRANES

2. SUB STRUCTURE 1.4 SETTING UP TEMPORARY SERVICES

1.5.2 SETTING UP BATCHING PLANT


& BASEMENT)

3. SUPER STRUCTURE 1.5 RESOURCE MOBILISATI0ON

1.5.3 MATERIAL STOARAGE AREA

4. SERVICES

1.5.4 VEHICLE FOR RESOURCE


TRANSPORTATION

5. FINISHING

6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SUB STRUCTURE

2.1 EARTHWORK

2.2 WATERPROOFING

2.3 RAFT FOUNDATION (BASEMENT)

1. SITE PREPARATION

IECC, PRAGATI MAIDAN (CONVENTION


2.4 PILE FOUNDATION (CONVENTION
CENTRE)

CENTRE & BASEMENT) 2. SUB STRUCTURE

2.5 RETAINING WALL

3. SUPER STRUCTURE

2.6 BEAM

4. SERVICES

2.7 SLAB

5. FINISHING

2.8 COLUMNS AND SHEAR WALLS

6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SUB STRUCTURE

2.1.1 TOP SOIL


EXCAVATION & STORAGE

2.1.2 SOIL STABILIZATION


THROUGH ANCHORED
SHEET PILING

2.1.3 EXCAVATION

2.1 EARTHWORK
2.1.4 DEWATERING

2.2 WATERPROOFING
2.1.5 SOIL COMPACTION

2.3 RAFT FOUNDATION


(BASEMENT) 2.1.6 ANTI TERMITE
1. SITE PREPARATION TREATMENT
2.4 PILE FOUNDATION
(CONVENTION CENTRE &

(CONVENTION CENTRE)
IECC, PRAGATI MAIDAN

2.1.7 BACK FILLING


2. SUB STRUCTURE

2.5 RETAINING WALL


BASEMENT)

3. SUPER STRUCTURE

2.6 BEAM

4. SERVICES

2.7 SLAB

5. FINISHING
2.8 COLUMNS AND SHEAR
WALLS
6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SUB STRUCTURE

2.1 EARTHWORK

2.2.1 PROVIDING HDPE MEMBRANE


2.2 WATERPROOFING
WATER PROOFING

2.3 RAFT FOUNDATION (BASEMENT)

1. SITE PREPARATION
IECC, PRAGATI MAIDAN (CONVENTION

2.4 PILE FOUNDATION (CONVENTION


CENTRE)

2. SUB STRUCTURE
CENTRE & BASEMENT)

2.5 RETAINING WALL

3. SUPER STRUCTURE

2.6 BEAM

4. SERVICES

2.7 SLAB

5. FINISHING

2.8 COLUMNS AND SHEAR WALLS

6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SUB STRUCTURE

2.1 EARTHWORK

2.3.1 PCC LAYING

2.2 WATERPROOFING

2.3.2 SHUTTERING AND


FORMWORKS

2.3 RAFT FOUNDATION (BASEMENT)

1. SITE PREPARATION 2.3.3 REINFORCEMENTS


IECC, PRAGATI MAIDAN (CONVENTION

2.4 PILE FOUNDATION (CONVENTION


CENTRE)

2. SUB STRUCTURE 2.3.4 CONCRETING


CENTRE & BASEMENT)

2.5 RETAINING WALL

3. SUPER STRUCTURE

2.6 BEAM

4. SERVICES

2.7 SLAB

5. FINISHING

2.8 COLUMNS AND SHEAR WALLS

6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SUB STRUCTURE

2.1 EARTHWORK

2.2 WATERPROOFING

2.4.1 BORING

2.3 RAFT FOUNDATION (BASEMENT)

1. SITE PREPARATION 2.4.2 REINFORCEMENTS


IECC, PRAGATI MAIDAN (CONVENTION

2.4 PILE FOUNDATION (CONVENTION


CENTRE)

2. SUB STRUCTURE 2.4.3 CONCRETING


CENTRE & BASEMENT)

2.5 RETAINING WALL

2.4.4 PILE CAPS


3. SUPER STRUCTURE

2.6 BEAM

4. SERVICES

2.7 SLAB

5. FINISHING

2.8 COLUMNS AND SHEAR WALLS

6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SUB STRUCTURE

2.1 EARTHWORK

2.2 WATERPROOFING

2.3 RAFT FOUNDATION (BASEMENT)

2.5.1 SHUTTERING AND


1. SITE PREPARATION
FORMWORKS
IECC, PRAGATI MAIDAN (CONVENTION

2.4 PILE FOUNDATION (CONVENTION


CENTRE)

2. SUB STRUCTURE 2.5.2 REINFORCEMENTS


CENTRE & BASEMENT)

2.5 RETAINING WALL

3. SUPER STRUCTURE 2.5.3 CONCRETING

2.6 BEAM

4. SERVICES 2.5.4 WATERPROOFING

2.7 SLAB

5. FINISHING

2.8 COLUMNS AND SHEAR WALLS

6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SUB STRUCTURE

2.1 EARTHWORK

2.2 WATERPROOFING

2.3 RAFT FOUNDATION (BASEMENT)

1. SITE PREPARATION
IECC, PRAGATI MAIDAN (CONVENTION

2.4 PILE FOUNDATION (CONVENTION


CENTRE)

2. SUB STRUCTURE
CENTRE & BASEMENT)

2.6.1 SHUTTERING AND


2.5 RETAINING WALL
FORMWORKS

3. SUPER STRUCTURE

2.6 BEAM 2.6.2 REINFORCEMENTS

4. SERVICES

2.7 SLAB 2.6.3 CONCRETING

5. FINISHING

2.8 COLUMNS AND SHEAR WALLS

6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SUB STRUCTURE

2.1 EARTHWORK

2.2 WATERPROOFING

2.3 RAFT FOUNDATION (BASEMENT)

1. SITE PREPARATION
IECC, PRAGATI MAIDAN (CONVENTION

2.4 PILE FOUNDATION (CONVENTION


CENTRE)

2. SUB STRUCTURE
CENTRE & BASEMENT)

2.5 RETAINING WALL

3. SUPER STRUCTURE

2.7.1 SHUTTERING AND


2.6 BEAM
FORMWORKS

4. SERVICES

2.7 SLAB 2.7.2 REINFORCEMENTS

5. FINISHING

2.8 COLUMNS AND SHEAR WALLS 2.7.3 CONCRETING

6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SUB STRUCTURE

2.1 EARTHWORK

2.2 WATERPROOFING

2.3 RAFT FOUNDATION


(BASEMENT)

1. SITE PREPARATION
(CONVENTION CENTRE & BASEMENT)
2.4 PILE FOUNDATION
(CONVENTION CENTRE)

2. SUB STRUCTURE
IECC, PRAGATI MAIDAN

2.5 RETAINING WALL

3. SUPER STRUCTURE

2.6 BEAM

4. SERVICES

2.8.1 SHUTTERING AND


2.7 SLAB
FORMWORKS

5. FINISHING

2.8 COLUMNS AND SHEAR WALLS 2.8.2 REINFORCEMENTS

6. SITE DEVELOPMENT

2.8.3 CONCRETING

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SUPER STRUCTURE

1. SITE PREPARATION

IECC, PRAGATI MAIDAN (CONVENTION 2. SUB STRUCTURE


CENTRE & BASEMENT)
3.1 IN SITU CONSTRUCTION

3. SUPER STRUCTURE

3.2 PRE-FAB CONSTRUCTION

4. SERVICES

5. FINISHING

6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SUPER STRUCTURE

3.1.1.1.1 SCAFFOLDING

3.1.1.1.2 PERI
SHUTTERING
3.1.1.1TREE COLUMN
3.1.1.1.3 PLACING OF
3.1.1 COLUMN
REINFORCEMENT
1. SITE PREPARATION 3.1.1.2VERTICAL COLUMN

3.1.2 BEAM 3.1.1.1.4 CONCRETING


(CONVENTION CENTRE &
IECC, PRAGATI MAIDAN

2. SUB STRUCTURE
3.1 IN SITU
3.1.3 SLAB
BASEMENT)

CONSTRUCTION
3. SUPER STRUCTURE
3.2 PRE-FAB
3.1.4 WALLS
CONSTRUCTION
4. SERVICES

3.1.5 STAIRCASE & RAMPS

5. FINISHING

6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SUPER STRUCTURE

3.1.2.1 SCAFFOLDING

3.1.1 COLUMN

1. SITE PREPARATION 3.1.2.2 PERI SHUTTERING

3.1.2 BEAM
(CONVENTION CENTRE &

3.1.2.3 PLACING OF
IECC, PRAGATI MAIDAN

2. SUB STRUCTURE
REINFORCEMENT

3.1 IN SITU CONSTRUCTION 3.1.3 SLAB


BASEMENT)

3. SUPER STRUCTURE 3.1.2.4 CONCRETING

3.2 PRE-FAB CONSTRUCTION 3.1.4 WALLS

4. SERVICES

3.1.5 STAIRCASE & RAMPS

5. FINISHING

6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SUPER STRUCTURE

3.1.1 COLUMN

1. SITE PREPARATION 3.1.3.1 SCAFFOLDING

3.1.2 BEAM
(CONVENTION CENTRE &
IECC, PRAGATI MAIDAN

2. SUB STRUCTURE 3.1.3.2 PERI SHUTTERING

3.1 IN SITU CONSTRUCTION 3.1.3 SLAB


BASEMENT)

3.1.3.3 PLACING OF
3. SUPER STRUCTURE
REINFORCEMENT

3.2 PRE-FAB CONSTRUCTION 3.1.4 WALLS

4. SERVICES 3.1.3.4 CONCRETING

3.1.5 STAIRCASE & RAMPS

5. FINISHING

6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SUPER STRUCTURE

3.1.1 COLUMN

1. SITE PREPARATION

3.1.2 BEAM
(CONVENTION CENTRE &
IECC, PRAGATI MAIDAN

2. SUB STRUCTURE

3.1 IN SITU CONSTRUCTION 3.1.3 SLAB 3.1.4.1 AAC BLOCKS MASONRY


BASEMENT)

3. SUPER STRUCTURE

3.2 PRE-FAB CONSTRUCTION 3.1.4 WALLS 3.1.4.2 BRICK WALLS MASONRY

4. SERVICES

3.1.5 STAIRCASE & RAMPS 3.1.4.3 RCC WALLS

5. FINISHING

6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SUPER STRUCTURE

3.1.1 COLUMN

1. SITE PREPARATION
IECC, PRAGATI MAIDAN (CONVENTION

3.1.2 BEAM

2. SUB STRUCTURE
CENTRE & BASEMENT)

3.1 IN SITU CONSTRUCTION 3.1.3 SLAB

3. SUPER STRUCTURE

3.2 PRE-FAB CONSTRUCTION 3.1.4 WALLS

4. SERVICES

3.1.5 STAIRCASE & RAMPS

5. FINISHING

6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SUPER STRUCTURE

3.2.1.1 TRANSFERRING OF STEEL


JOISTS

1. SITE PREPARATION
3.2.1.2 SETTING UP OF
CRAWLER CRANE
(CONVENTION CENTRE &
IECC, PRAGATI MAIDAN

2. SUB STRUCTURE

3.2.1.3 INSTALLATION OF STEEL


3.1 IN SITU CONSTRUCTION
JOISTS
BASEMENT)

3.2.1 COMPOSITE DECK


3. SUPER STRUCTURE
FLOORING
3.2.1.4 PLACEMENT OF STEEL
3.2 PRE-FAB CONSTRUCTION
DECK

4. SERVICES 3.2.2 ROOF TRUSS

3.2.1.5 LAYING OF
REINFORCEMENTS

5. FINISHING

3.2.1.6 CONCRETING

6. SITE DEVELOPMENT

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SUPER STRUCTURE

1. SITE PREPARATION
(CONVENTION CENTRE &

3.2.2.1 TRANSFER OF STEEL


IECC, PRAGATI MAIDAN

2. SUB STRUCTURE
MEMBERS

3.1 IN SITU CONSTRUCTION


BASEMENT)

3.2.1 COMPOSITE DECK 3.2.2.2 PLACEMENT AND


3. SUPER STRUCTURE
FLOORING WELDING OF MEMBERS

3.2 PRE-FAB CONSTRUCTION

4. SERVICES 3.2.2 ROOF TRUSS 3.2.2.3 BOLTING AND FIXING

5. FINISHING 3.2.2.4 ROOF SHEETING

6. SITE DEVELOPMENT 3.2.2.5 FINISHING

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SERVICES

1. SITE PREPARAION

IECC, PRAGATI MAIDAN (CONVENTION CENTRE


4.1 HVAC

2. SUB STRUCTURE

4.2 ELECTRICAL
& BASEMENT)

3. SUPER STRUCTURE

4.3 PLUMBING

4. SERVICES

4.4 FIRE FIGHTING

5. FINISHING

4.5 BMS

6. SITE DEVELOPMENT

4.6 LIFT AND ESCALATORS

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SERVICES

4.1.1.1 AHU

4.1.1.2 CHILLER PLANTS

1. SITE PREPARAION 4.1.1 HIGH SIDE


(CONVENTION CENTRE & BASEMENT)

4.1 HVAC
4.1.1.3 COOLING TOWERS
2. SUB STRUCTURE 4.1.2 LOW SIDE
IECC, PRAGATI MAIDAN

4.2 ELECTRICAL
4.1.1.4 PUMPS & EQUIPMENNTS
3. SUPER STRUCTURE FOR PLANT ROOM

4.3 PLUMBING

4. SERVICES

4.4 FIRE FIGHTING

5. FINISHING

4.5 BMS

6. SITE DEVELOPMENT

4.6 LIFT AND ESCALATORS

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SERVICES

4.1.2.1 PIPING

1. SITE PREPARAION 4.1.1 HIGH SIDE 4.1.2.2 DUCTING


(CONVENTION CENTRE & BASEMENT)

4.1 HVAC

2. SUB STRUCTURE 4.1.2 LOW SIDE 4.1.2.3 FCU


IECC, PRAGATI MAIDAN

4.2 ELECTRICAL

3. SUPER STRUCTURE 4.1.2.4 RETURN & SUPPLY GRILLS

4.3 PLUMBING
4.1.2.5 SPLIT UNITS
4. SERVICES

4.4 FIRE FIGHTING

5. FINISHING

4.5 BMS

6. SITE DEVELOPMENT

4.6 LIFT AND ESCALATORS

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SERVICES

4.2.1.1.1 INSTALLATION OF
TRANSFORMERS

4.2.1.1.2 INSTALLATION OF
HT PANELS
4.2.1.1 INSTLLATION OF
SUBSTATIONS 1,2 &3
4.2.1.1.3 INSTALLATION OF
LT PANELS
1. SITE PREPARAION
4.2.1.1.4 TERMINATION
4.1 HVAC ,TESTING AND
(CONVENTION CENTRE &
IECC, PRAGATI MAIDAN

COMMISIONING
2. SUB STRUCTURE 4.2.1 HIGH SIDE

4.2 ELECTRICAL 4.2.1.2.1 INSTALLATION OF


BASEMENT)

CHIMNEYS
3. SUPER STRUCTURE 4.2.2 LOW SIDE

4.3 PLUMBING 4.2.1.2.2 INSTALLATION OF


COOLING TOWER
4.2.1.2 INSTALLATION OF 6
4. SERVICES DG SETS
4.4 FIRE FIGHTING
4.2.1.2.3 ATS PANEL
5. FINISHING CONECTION,TESTING AND
COMMISSIONING
4.5 BMS

6. SITE DEVELOPMENT

4.6 LIFT AND ESCALATORS

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SERVICES

1. SITE PREPARAION 4.2.2.3.1 FLOOR PANEL


4.2.2.1 CONDUITING &
4.1 HVAC
(CONVENTION CENTRE &

CABLE TRAY INSTALLATION


IECC, PRAGATI MAIDAN

2. SUB STRUCTURE 4.2.1 HIGH SIDE 4.2.2.3.2 PEAK-LDB


4.2.2.2 CABLING,EARTHING
4.2 ELECTRICAL
& WIRING
BASEMENT)

3. SUPER STRUCTURE 4.2.2 LOW SIDE 4.2.2.3.3 NON PEAK-LDB


4.2.2.3 PANEL & DB
4.3 PLUMBING
INSTALLATION
4. SERVICES 4.2.2.3.4 UPS- DB
4.2.2.4 TERMINATION
4.4 FIRE FIGHTING ,TESTING AND
COMMISSIONING
5. FINISHING 4.2.2.3.5 RAW POWER –DB

4.5 BMS

6. SITE DEVELOPMENT 4.2.2.3.6 INVERTOR-DB

4.6 LIFT AND ESCALATORS

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SERVICES

4.3.1.1 WATER PUMPS

4.3.1.2 BASEMENT DRAINAGE


PUMPS

1. SITE PREPARAION
(CONVENTION CENTRE & BASEMENT)

4.1 HVAC 4.3.1.3 WATER TANKS

2. SUB STRUCTURE
IECC, PRAGATI MAIDAN

4.2 ELECTRICAL 4.3.1.4 SEWAGE PUMPS

3. SUPER STRUCTURE 4.3.1 HIGH SIDE

4.3.1.5 WATER TREATMENT


4.3 PLUMBING
PUMPS

4. SERVICES 4.3.2 LOW SIDE

4.3.1.6 MBR-SEWAGE
4.4 FIRE FIGHTING
TREATMENT PLANT

5. FINISHING

4.5 BMS 4.3.1.7 STORM WATER DRAINAGE

6. SITE DEVELOPMENT

4.3.1.8 RAIN WATER HARVESTING


4.6 LIFT AND ESCALATORS
TANK

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SERVICES

1. SITE PREPARAION
(CONVENTION CENTRE & BASEMENT)

4.1 HVAC

2. SUB STRUCTURE
IECC, PRAGATI MAIDAN

4.2 ELECTRICAL

3. SUPER STRUCTURE 4.3.1 HIGH SIDE

4.3.2.1 SANITARY FIXTURE AND


4.3 PLUMBING
FITTINGS

4. SERVICES 4.3.2 LOW SIDE

4.4 FIRE FIGHTING 4.3.2.2 INTERNAL PIPE LAYOUTS

5. FINISHING

4.5 BMS

6. SITE DEVELOPMENT

4.6 LIFT AND ESCALATORS

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SERVICES

1. SITE PREPARAION
(CONVENTION CENTRE & BASEMENT)

4.1 HVAC

4.4.1.1 EXTERNAL FIRE


2. SUB STRUCTURE
IECC, PRAGATI MAIDAN

HYDRANTS

4.2 ELECTRICAL

4.4.1.2 CONNECTION TO FIRE


3. SUPER STRUCTURE
TANKS

4.3 PLUMBING

4. SERVICES 4.4.1 HIGH SIDE 4.4.1.3 EXTERNAL PIPE NETWORK

4.4 FIRE FIGHTING

5. FINISHING 4.4.2 LOW SIDE


4.4.1.4 UG AND OH WATER TANKS
4.5 BMS

6. SITE DEVELOPMENT 4.4.1.5 INSTALLATION OF PUMPS

4.6 LIFT AND ESCALATORS

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SERVICES

1. SITE PREPARAION

4.1 HVAC
(CONVENTION CENTRE &
IECC, PRAGATI MAIDAN

2. SUB STRUCTURE

4.2 ELECTRICAL
BASEMENT)

3. SUPER STRUCTURE

4.3 PLUMBING

4. SERVICES 4.4.1 HIGH SIDE


4.4.2.1.1 BEAM
4.4.2.1 FIRE ALARM
4.4 FIRE FIGHTING DETECTORS,SMOKE
SYSTEM
DETECTORS
5. FINISHING 4.4.2 LOW SIDE

4.5 BMS 4.4.2.2 SPRINKLER SYSTEM

6. SITE DEVELOPMENT

4.6 LIFT AND ESCALATORS

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SERVICES

1. SITE PREPARAION

4.1 HVAC
(CONVENTION CENTRE &
IECC, PRAGATI MAIDAN

2. SUB STRUCTURE

4.2 ELECTRICAL
BASEMENT)

3. SUPER STRUCTURE

4.3 PLUMBING

4. SERVICES 4.5.1 LIGHTING INTEGRATION

4.4 FIRE FIGHTING


4.5.2 CCTV SYSTEM
5. FINISHING
INTEGRATION
4.5 BMS
4.5.3 FIRE ALARM SYSTEM
6. SITE DEVELOPMENT
INTEGRATION
4.6 LIFT AND ESCALATORS
4.5.4 ACCESS AND CONTROL
ROOMS

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SERVICES

1. SITE PREPARAION

4.1 HVAC
(CONVENTION CENTRE &
IECC, PRAGATI MAIDAN

2. SUB STRUCTURE

4.2 ELECTRICAL
BASEMENT)

3. SUPER STRUCTURE

4.3 PLUMBING

4. SERVICES

4.4 FIRE FIGHTING

5. FINISHING 4.6.1 LIFT INSTALLATION

4.5 BMS
4.6.2 TESTING ,
6. SITE DEVELOPMENT COMMISIONING
&LISENCING
4.6 LIFT AND ESCALATORS
4.6.3 ESCALATOR
INSTALLATION

4.6.4 TESTING
,COMMISIONING AND
LISENCING

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
FINISHING

5.1.1.1.1 RUBBER OVERLAY

5.1.1.1. IPS FLOORING


5.1.1.1.2 CARPET FLOOR
TILE/ FIRE RETARDENT
CARPET FLOOR

5.1.1.2.3 POLISHED KOTA


1. SITE PREPARATION STONE FLOORING
(CONVENTION CENTRE &

5.1.1.2.4 ITALIAN MARBLE


IECC, PRAGATI MAIDAN

2. SUB STRUCTURE 5.1.1.2. STONE FLOORING FLOORING WITH CARPET


OVERLAY
5.1.1. FLOORING
BASEMENT)

5.1.1.2.5 POLISHED
3. SUPER STRUCTURE
GRANITE FLOORING
5.1.3. WALL FINISH

4. SERVICES 5.1.1.3.6 VITRIFIED TILES

5.1. INTERNAL FINISHES 5.1.4. CEILING 5.1.1.3. TILE FLOORING

5. FINISHING 5.1.1.3.7 ANTI STATIC TILES

5.2. EXTERNAL FINISHES 5.1.5. PARTITIONS 5.1.1.4 SKIRTING

6. SITE DEVELOPMENT

5.1.6. ACCESSORIES

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
FINISHING

1. SITE PREPARATION

5.1.1.1VITRIFIED TILE 5.1.1.2.1 WOODEN


(CONVENTION CENTRE &
IECC, PRAGATI MAIDAN

CLADDING (UPTO 4 FT)


2. SUB STRUCTURE

5.1.1. FLOORING 5.1.1.2 WALL CLADDING


5.1.1.2.2 RIGATO/SAND
BASEMENT)

BLASTED FINISHED
3. SUPER STRUCTURE
NATURAL DHAULPUR
5.1.1.3 FABRIC PANELLING STONE CLADDING
5.1.3. WALL FINISH
(4FT – 8FT)
4. SERVICES

5.1. INTERNAL FINISHES 5.1.4. CEILING 5.1.1.4 PAINTING


5.1.1.5.1 MICRO-
5. FINISHING PERFORATED WOODEN
PANELLING
5.1.1.5 ACOUSTIC
5.2. EXTERNAL FINISHES 5.1.5. PARTITIONS
TREATMENT
5.1.1.5.2 0.7 NRC
6. SITE DEVELOPMENT STRETCHED FABRIC
PANRLLING
5.1.6. ACCESSORIES

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
FINISHING

5.1.1.2.1 GYPSUM BOARD


CEILING

1. SITE PREPARATION
5.1.1.2.2 POP FALSE
5.1.1.1 SCAFFOLDING
CEILING
(CONVENTION CENTRE &
IECC, PRAGATI MAIDAN

2. SUB STRUCTURE
5.1.1.2 DECORATED FALSE 5.1.1.2.3 GRC PANELLING
CEILING WITH COVE LIGHTS
5.1.1. FLOORING
BASEMENT)

3. SUPER STRUCTURE
5.1.1.2.4 VENEERED
WOODEN FLOATED CEILING
5.1.3. WALL FINISH

4. SERVICES
5.1.1.2.5 ALUMINIUM GRID
CEILING
5.1. INTERNAL FINISHES 5.1.4. CEILING

5. FINISHING 5.1.1.3.1 0.7 NRC MICRO


PERFORATED GYP BOARD
5.2. EXTERNAL FINISHES 5.1.5. PARTITIONS CEILING
5.1.1.3 ACOUSTIC
TREATMENT CEILING
6. SITE DEVELOPMENT 5.1.1.3.2 ACOUSTUCAL
DESIGNER WOODEN
5.1.6. ACCESSORIES CEILING
5.1.1.4 MR GRADE GYPSUM
GRADE CEILING

5.1.1.5 P5.LASTERING WITH


OBD/ WHITE WASH

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
FINISHING

1. SITE PREPARATION
(CONVENTION CENTRE &

2. SUB STRUCTURE
IECC, PRAGATI MAIDAN

5.1.1. FLOORING
BASEMENT)

3. SUPER STRUCTURE

5.1.3. WALL FINISH

5.1.4.1 INSTALLATION OF DOUBLE


4. SERVICES
STUD FRAMEWORK

5.1. INTERNAL FINISHES 5.1.4. CEILING

5.1.4.2 GYPSUM BOARD DRY


5. FINISHING
WALL (STC 55)

5.2. EXTERNAL FINISHES 5.1.5. PARTITIONS

5.1.4.3 ALUMINIUM CURTAIN


6. SITE DEVELOPMENT
WALLS

5.1.6. ACCESSORIES

5.1.4.4 PRE-LAMINATED
MODULAR TOILET PARTITIONS

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
FINISHING

1. SITE PREPARATION
(CONVENTION CENTRE &

2. SUB STRUCTURE
IECC, PRAGATI MAIDAN

BASEMENT)

3. SUPER STRUCTURE

5.2.1.1 STEEL SUPPORT FRAME


FIXED WITH RCC STRUCTURE

4. SERVICES 5.2.1 GRC CLADDING

5.2.1.2 FIXING OF GRC PANEL TO


5.1. INTERNAL FINISHES
STEEL SUPPORT FRAME

5. FINISHING 5.2.2 ALUMINIUM CLADDING

5.2. EXTERNAL FINISHES

6. SITE DEVELOPMENT 5.2.3 TERRACE GARDEN

5.2.4 INSTALLATION OF HELIPAD

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
FINISHING

1. SITE PREPARATION
(CONVENTION CENTRE &

2. SUB STRUCTURE
IECC, PRAGATI MAIDAN

BASEMENT)

3. SUPER STRUCTURE

5.2.3.1 INSTALLING GALVANISED


STEEL FRAME ONTO RCC
4. SERVICES 5.2.1 GRC CLADDING STRUCTURE

5.1. INTERNAL FINISHES


5.2.3.2 FIXING ALUMINIUM
5. FINISHING 5.2.3 ALUMINIUM CLADDING CLADDING ONTO STEEL BRACKET

5.2. EXTERNAL FINISHES


5.2.3.3 FIXING ALUMINIUM
CLADDING ONTO GALVANISED
6. SITE DEVELOPMENT 5.2.4 TERRACE GARDEN
STEEL FRAME ATTACHED TO RCC
COLUMN

5.2.5 INSTALLATION OF HELIPAD

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
FINISHING

1. SITE PREPARATION

IECC, PRAGATI MAIDAN (CONVENTION CENTRE

2. SUB STRUCTURE
& BASEMENT)

3. SUPER STRUCTURE

4. SERVICES 5.2.1 GRC CLADDING

5.1. INTERNAL FINISHES

5. FINISHING 5.2.2 ALUMINIUM CLADDING

5.2. EXTERNAL FINISHES

6. SITE DEVELOPMENT 5.2.3 TERRACE GARDEN

5.2.4 INSTALLATION OF HELIPAD

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
FINISHING

1. SITE PREPARATION

IECC, PRAGATI MAIDAN (CONVENTION CENTRE

2. SUB STRUCTURE
& BASEMENT)

3. SUPER STRUCTURE

4. SERVICES 5.2.1 GRC CLADDING

5.1. INTERNAL FINISHES

5. FINISHING 5.2.2 ALUMINIUM CLADDING

5.2. EXTERNAL FINISHES

6. SITE DEVELOPMENT 5.2.3 TERRACE GARDEN

5.2.4 INSTALLATION OF HELIPAD

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SITE DEVELOPMENT

1. SITE PREPARATION 6.1.1. SITE WORK


(CONVENTION CENTRE &
IECC, PRAGATI MAIDAN

2. SUB STRUCTURE 6.1.2. CONSTRUCTION OF STEPPED AREAS


BASEMENT)

3. SUPER STRUCTURE 6.1.3. LAYING OF GRASS/SHURBS

6.1. LANDSCAPING

4. SERVICES 6.1.4. LANDSCAPE WORK FOR PATHWAYS

6.2. ROADS

5. FINISHING 6.1.5.EXTERNAL LIGHTING

6.3. BOUNDARY WALL


6.1.6INSALLATION OF FOUNTAIN AND
6. SITE DEVELOPMENT
WATER BODY
6.4. PAVING

6.5. ENTRANCE GATE

6.6. GRADING & LEVELING

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SITE DEVELOPMENT

1. SITE PREPARATION

(CONVENTION CENTRE &


IECC, PRAGATI MAIDAN
2. SUB STRUCTURE

6.2.1 EARTH WORK


BASEMENT)
3. SUPER STRUCTURE
6.2.2 FILLING (3 LAYER
6.1. LANDSCAPING
ROLLING)
4. SERVICES

6.2. ROADS 6.2.3 RCC

5. FINISHING

6.3. BOUNDARY WALL 6.2.4 PREPARE SUBGRADE

6. SITE DEVELOPMENT
6.2.5 CONCRETE SUB BASE
6.4. WALK WAY
OVER SUBGRADE

6.5. ENTRANCE GATE

6.6. GRADING & LEVELING

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SITE DEVELOPMENT

1. SITE PREPARATION

(CONVENTION CENTRE &


IECC, PRAGATI MAIDAN
2. SUB STRUCTURE
BASEMENT)
3. SUPER STRUCTURE 6.3.1 EARTH WORK

6.1. LANDSCAPING

4. SERVICES 6.3.2 FOUNDATION

6.2. ROADS

5. FINISHING 6.3.3 BRICKWORK

6.3. BOUNDARY WALL

6. SITE DEVELOPMENT 6.3.4 EARTH BACK FILLING

6.4. WALK WAY


6.3.5 INSTALLATION OF
FENCING
6.5. ENTRANCE GATE

6.3.6 FINISHING

6.6. GRADING & LEVELING

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SITE DEVELOPMENT

1. SITE PREPARATION

(CONVENTION CENTRE &


IECC, PRAGATI MAIDAN
2. SUB STRUCTURE
BASEMENT)
3. SUPER STRUCTURE

6.1. LANDSCAPING

4. SERVICES

6.2. ROADS 6.4.1 PCC

5. FINISHING

6.3. BOUNDARY WALL 6.4.2 Brickwork


6. SITE DEVELOPMENT

6.4. WALK WAY


6.4.3 60mm thk
Paver block

6.5. ENTRANCE GATE


6.4.4 60mm thk
Paver block (grass)

6.6. GRADING & LEVELING 6.4.5 Kerb stone

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
SITE DEVELOPMENT

1. SITE PREPARATION

(CONVENTION CENTRE &


IECC, PRAGATI MAIDAN 2. SUB STRUCTURE

BASEMENT)
3. SUPER STRUCTURE

6.1. LANDSCAPING

4. SERVICES

6.2. ROADS

5. FINISHING

6.3. BOUNDARY WALL

6. SITE DEVELOPMENT 6.5.1 GATE FABRICATION

6.4. WALK WAY

6.5.2 FIXING OF GATE


6.5. ENTRANCE GATE
6.5.3 LAYING OF
ELECTRICAL SERVICES
6.6. GRADING & LEVELING
6.5.4 SURFACE
FINISHING

WBS
RE-DEVELOPMENT OF PRAGATI MAIDAN INTO IECC
PROJECT PLANNING AND SCHEDULING

THANK YOU!

GROUP 5: APOORV AGARWAL ANUBHA SINGHAL SANDEEP SINGH


THOUFEER MUHAMMED N RAYMON PRAKASH SHINEY ELIZABETH ABRAHAM