Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
&
BPC
Vision & Mission
66 kV
10%
33 kV
13%
22 kV
1%
≤ 11 kV
2% ≥ 220 kV
43%
IMP is valued customer of CPRI
Awarded for 100% success in SC testing.
The only firm in INDIA who have successfully short circuit tested
160MVA (3 variants) & 100MVA (4 variants) 220kV transformers,
within 2-years, which proves consistency of our robust Design &
Quality. IMP has been awarded with valued customer award from CPRI
for three times.
2009 2016
160 MVA, 230/110/11kV Auto Transformer
160 MVA, 220/132kV Auto Transformer
160 MVA, 220/66kV Power Transformer
2017
100 MVA, 230/110/11kV Auto Transformer
100 MVA, 220/132kV Auto Transformer
100 MVA, 220/66kV Power Transformer
EPC 51 A2Z, AMAR RAJA, ASHA BANU, ADEPT, BAJAJ, BS, BRG, ETA, ERL,
FEDDERS, GODREJ, GREENAGE, GAJA, GENUS, GVPRL, HPL, ISAT,
IVRCL, ISOLUX, JYOTI, JSP, KAILASH, KALPATARU, KEC, NCC, NKG,
NARESH AGRAWAL, OMICRON, PUNJ, PACE POWER, PRATHIBHA,
PRATEEK, REGEN, RENEW, SAFETY, SHREEM, SPIC, S.K.AGRAWAL, SMS,
SKS-BUILD, SUDHIR, SHYAMA, SHAYAM-FERRO, SHYAM-SEL, SHYAM-
INDUS, SUNIL HITECH, TATA, UB, VIHAN, VIKRAN, VISHWANATH.
Name
Voltage
11kV to 132kV 11kV to 220kV 11kV to 220kV 11kV to 220kV 220 kV 220 kV
Class
Smallest
100 kVA 100 kVA 100 kVA 100 kVA 100 MVA 100 MVA
Rating
Highest
31.5 MVA 100 MVA 100 MVA 160 MVA 100 MVA 100 MVA
Rating
pmyadav@imp-powers.com
customerservices@imp-powers.com
Power Transformer:
Erection, Testing & Commissioning
at Site
Receipt, Storage, Erection & Processing of
Transformer at Site
1. Receipt of Main Unit: Inspect main unit for its transit damage /
Paint & Note reading of Impact Recorder
2. Receipt of Accessory : Check transit / unloading damage to
Bushing Crates, Radiators, Drive Mechanism & Oil Drums
3. Core Isolation: Check Core - Frame is intact
4. N2/Dry Air filled Transformer: Check Tank Valve & Cylinder is
in open condition. Also check pressure gauge is showing positive
reading of N2 / Dry Air along with its dew point.
5. Oil Filled Transformer: Check Oil Level as per manufacturers
guideline & Oil BDV.
6. Insurance Coverage: Ensure coverage of Transit Damage /
Shifting Damage, Damages during ETC, if noticed. Report to
manufacturer to cover in Insurance Claim / Do as per the Terms &
Condition of Contract
Storage –Check Points
6. Check distance between Main tank & Fire Wall should be as per
statutory requirement
7. Check A Frames & Radiator position
8. Assembly of Coolers (Radiators / Heat Exchangers), Conservators
& other accessories
9. Erection & alignment of OLTC DM & Bevel Gear Shaft
10. Checking of Lead Entry during bushing erection
Preliminary Testing
Note:
For transformers supplied with in-tank type/ external OLTC, the
diverter / OLTC compartment shall be equalized with the main tank
before applying vacuum
Rate of filling of oil should not be more than 3-4 kL/hr, to permit
proper impregnation of insulation with oil and avoid trapping of air
bubbles.
Fitting of Turret, Bushing & Other Parts
1. Fit PRV, Turret & its pipeline, Buchholz Pipe Line, OLTC Pipe line.
2. Fit bushings – check lead entries in bushings & clearances around.
3. Check mounting direction mark on Buchholz Relay & OSR
direction towards conservator.
4. Start tightening the parts from main tank towards conservator.
5. Fit Radiator, Heat Exchanger etc.
6. Now the transformer is ready for oil topping up.
Bushing Lead Entry
39
Rated Voltage & Vacuum Application
The bolt shall be fastened four times or five times symmetrically and
uniformly, not dispossibly one by one from the position of diagonal.
See the Figure, the sequence is 1~2~3~4~5~6~7~8~1~.
1. After fitment of PRV, start oil topping up through top filter valve
2. Fill oil in OLTC through equalizer pipeline
3. Remove equalizer between OLTC & Main transformer.
4. Open valves towards conservator.
5. Open top side valves of heat exchanger or radiators.
6. During oil filling, monitor air release from all possible points.
7. Fill oil in conservator level up to 2-3 stud heights of prismatic
gauge.
8. In OLTC conservator oil to be filled separately through oil filling
hole provided at the top of conservator up to the level marked on
the gauge.
9. Transformer is ready for carrying out oil filtration.
Oil Filtration
Check the
Fitting of
Air Cell
Air Cell Commissioning
Air Cell
after giving
pressure
Air Cell Commissioning
1. Loosen air release plugs (labeled as ‘C’ & ‘D’ - refer Oil-filling
Instructions Plate provided on the transformer).
2. Pressurize the flexi-separator (Inflate) with dry air or N2 to
1-1.5 psi (max) by closing the valve in the breather pipe line.
3. Push oil from bottom till it starts flowing from all the air
release plugs, thus allowing removal of the air trapped inside
the conservator. Stop oil filling at this stage for a while &
tighten all the air release plugs after oil release/bleeding. At
this stage, the prismatic oil level gauge will show full oil level,
where as the MOG will be indicating zero oil level.
Air Cell Commissioning
4. Continue oil filling at slow rate. During oil pushing the pressure
inside the air separator will rise. Maintain the pressure in side
the separator between 1 to 1.5 psi by releasing N2 / Dry Air
through the valve.
(Note: The pressure of 1-1.5 psi could be maintained by opening the valve in
the breather pipeline by maintaining rate of release of N2 / Dry Air
approximately equal to the rate of filling of oil).
5. In this condition, the air cell will float on oil and MOG will start
indicating the actual level of oil. Stop filling of oil when the
MOG indicates level corresponding to 35° mark, i.e.,
corresponding to temperature of top oil in transformer. Oil
level in the sight glass remains constant during the operation
& in service. While the MOG indicates the actual oil level in
conservator, the oil level indication in the prismatic sight glass
will be different
Air Cell Commissioning
PRECAUTIONS:
Oil Testing: As per IS 1866 Latest Revision all test & DGA
Functional Testing: All protection to be checked for its functional testing and
operation to be cross checked as per scheme