Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Presentation
SubmittedTo
Dr. Prof. Ashok Kumar Gupta
(HOD, Deptt of Civil Engineering)
By
RISHAB ATTRI [182601]
Abbreviation
Concept Description
Budget at Completion BAC Baseline cost of 100% of the
project.
Actual Cost AC Total costs actually incurred so far.
Amount of budget earned so
Earned Value EV far based on physical work
accomplished, without
reference to actual costs.
The budget for the physical work
Planned Value PV scheduled to be completed by
the end of the time period.
Metrics
Abbreviation
Concept Description
Measure of cost overrun.
Cost Variance CV
CV = EV – AC
Measure schedule
Schedule Variance SV
slippage. SV = EV –
PV
Cost efficiency
Cost Performance Index CPI
ratio. CPI =
EV/AC
Scheduled Performance Index Schedule efficiency
SPI
ratio. SPI = EV/PV
Expected total cost based on the current
Estimate at Completion EAC cost and schedule efficiency ratios.
EAC = AC+((BAC-EV)/(CPI*SPI))
Numerical
The project is to build a 4 wall room. The cost per wall is 10,000 Rs. and it will
take 1 day to construct 1 wall. At the end of the 3 day we have finished 2.5 walls
and our actual cost is 28,000 Rs. then our values are :