GENERAL

CONDITIONS
GENERAL CONDITIONS
SECTION I- DEFINITIONS AND
DOCUMENTS
contract documents
• agreement
• general conditions
• special provisions
• specifications and supplementary
specifications
• drawings
key players
• owner
• architect
• engineer
• project representative
• contractor
• sub-contractor

CONTRACT DOCUMENTS

GENERAL CONDITIONS
bonds
proposal bond : guarantee to enter into a contract if awarded
performance bond : guarantee to execute the work in accordance with
the terms of the contract (15% of contract amount,
upon contract signing)
payment bond : guarantee to pay all obligations arising from the
contract (15% of contract amount upon contract
signing)
guarantee bond : guarantee workmanship and quality of materials
and equipment for 1 year (30% of contract amount)

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Work of the Contractor
Furnish : purchase/ fabricate and deliver
Install : build in, mount in position, connect, apply for
intended use
Provide : furnish and install

CONTRACT DOCUMENTS

GENERAL CONDITIONS
bidding
• proposal
• tender documents
• invitation to bid
• bid bulletin
• instruction to bidders

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 2: execution, correlation and intent of documents
• signature on documents- by owner and contractor
• intent of contract documents- complementary and binding
• conformity to the contract documents
• contract documents at site of work
• ownership of contract documents and models- by the Architect

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 3: drawings and specifications
• copies of drawings and specifications
• coordination of drawings and specifications
• clarification of meaning- cost arising from discrepancies in
information
• discrepancies in drawings- necessary adjustments to produce first
class work

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 4: detail drawings and inspections
• supplementary drawings and instructions-
to be considered of equal force
• schedule for submission of detail and shop drawings-
setting drawings, templates, patterns at contractor’s
expense

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 5: shop drawings
•conditions in the preparation of shop drawings
•checking drawings of sub-contractors
•identification
•letter of transmittal
•corrections, changes and variations
•responsibility for accuracy

CONTRACT DOCUMENTS

GENERAL CONDITIONS
SECTION II- LAWS, REGULATIONS, SITE
CONDITIONS, PERMITS, TAXES
Art. 6: laws, regulations and site conditions
• laws and regulations- codes, ordinances services/
utility regulations
• site conditions- visit prior to bidding

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 7: permits, taxes and surveys
• permits and licenses
• taxes
• construction stakes and reference mark
• services of licensed surveyor
• final certification

CONTRACT DOCUMENTS

GENERAL CONDITIONS
SECTION III- EQUIPMENT AND MATERIALS
Art. 8: general (equipment and materials)
Art. 9: equipment
•quality of equipment
•equipment approval data- complete catalog data

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 10: materials, fixtures, appliances, fittings

•manufacturers and dealers- all transactions through the contractor


•samples of materials- properly labelled; for approval; pre-paid transportation cost
•trade name materials and substitutes
•testing samples of materials
•quality of materials
•storage and stockpiling of materials
•defective materials- cost of removal and replacement
•imported materials, fixtures and equipment- time element

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 11: materials, equipment, fixtures, appliances
and fittings furnished by the owner
Art. 12: royalties and patents
Art. 13: manufacturer’s directions

CONTRACT DOCUMENTS

GENERAL CONDITIONS
SECTION IV- PREMISES AND TEMPORARY
STRUCTURES
Art. 14: use of premises
• limitation of use- legal provisions
• safeguard for structure- safety concerns

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 15: temporary structures and facilities
• office and contractor’s building • stairs, ladders, ramps,
runways
• housing for workers
• elevators and hoists
• sanitary facilities and first aid station
• temporary enclosures
• barricades and guard lights
• trial usage
• water, power and telephone facilities
• removal of temporary
• signs
structures
• roadways

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 16: protection of work and owner’s property
• safeguard measures- theft, fire, damage
• old materials
• trees and other plants- protection, transplanting, removal
• drainage- altering waterways

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 17: protection of adjacent property and
existing utilities
• contractor’s sole responsibility
• existing utilities

Art. 18: protection of life, work and property


during an emergency
• authorization to contractor- compensation for
emergency work

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 19: labor
• character of workmen- discharging, removal of
inefficient employee
• superintendence and supervision- licensed, at least once
a week inspection

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 20: work
• methods and appliances- changing of performance levels
• laying out the work- protecting & replacing markers
• inspection of work
• defective work
• work during an emergency
• increased or decreased quantities

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 20: work
• changes in the work
- changes ordered by owner
- change of sub-surface conditions
- adjustment of contract
- value of extra work
- period for which claim for adjustment has to be asserted- 15 days
- changes ordered by the architect- not involving cost and change in concept
- award of extra work to other contractors

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 20: work
• claims for extra cost- caused by instructions from architect or
owner; delays in owner-supplied materials- within 15 days
• cleaning up at completion of work
• use of completed portions of work- not be deemed as acceptance
• certificate of completion of work- 98% completion
• period of making good known defects or faults- not more than
60 calendar days
• making good of known defects or faults
• search for causes of defects or faults- contractor’s expense

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 21: time of completion of work
•notice to proceed
•contract time- 7th day from NTP receipt
•schedule of completion
•extension of time- request 15 days after
•liquidated damages

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 22: payments
• detailed breakdown of contract amount
• requests for payment
• progress photographs
• architect’s action on request for payment- within 15 days
• approval withheld
• conditions relative to payment
• owner’s action on approved certificate of payment

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 22: payments
• payment of contractor’s obligations
• correction of work before final payment
• other requirements before final payment
• acceptance and final payment
• correction of work after final payment
• release of retention- 3 months after final payment

CONTRACT DOCUMENTS

GENERAL CONDITIONS
• Certificate of final bldg
occupancy

Art. 22: payments • Certificate of final inspection of


utilities
• payment of contractor’s obligations • 3 sets of as-built drawings

• correction of work before final payment • 3 copies of directory of panel


boards and list of circuits
• other requirements before final payment • 3 copies of manual of
operations and maintenance
• acceptance and final payment
• 3 copies of keying schedule
• correction of work after final payment
• Guarantee bond – 30% of
• release of retention- 3 months after final contract price covering 1 year
after final acceptance
payment

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 23: separate contracts to other contractors
•owner’s right to let other contracts

Art. 24: contractor-separate contractors relations


•storage of materials and work coordination
•cutting, patching and digging
•defective work by separate contractors
•damage caused by contractor to separate contractors

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 25: sub-contracts
•general
•competency of sub-contractor
•contractor’s responsibility

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 26: contractor - sub-contractors relations
Art. 27: contractor’s right to suspend work or terminate
contract
Art. 28: owner’s right to terminate contract
Art. 29: owner’s right to proceed work after takeover from
contractor

CONTRACT DOCUMENTS

GENERAL CONDITIONS
SECTION IX- RESPONSIBILITIES AND LIABILITIES
OF CONTRACTOR AND OWNERS

Art. 30: contractor’s responsibility for accidents and


damages

• safeguards to be undertaken by contractor


• contractor’s responsibility
• indemnity

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 31: contractor’s insurance and bonds

• contractor’s liability insurance


• contractor’s fire insurance
• contractor’s performance and payment bonds
• contractor’s guarantee bond
• contractor’s guaranty warranty

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 32: owner’s responsibilities and liabilities

• protection of employees and professionals performing services


for the owner
• owner’s optional insurance

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 33: liens, disputes and arbitration

• liens
• assignment
• damages
• disputes
• arbitration

CONTRACT DOCUMENTS

GENERAL CONDITIONS
Art. 34: architect’s status

Art. 35: authority and responsibilities of the engineers

Art. 36: authority and duties of the project


representatives, resident architects, resident engineers or
construction inspectors

CONTRACT DOCUMENTS

GENERAL CONDITIONS
CONTRACTOR’S COST

• Shop drawings
• Permits and Licenses
• Project-related taxes
• Grade lines/ benchmarks
• Surveyor’s certificate
• Cost of revisions due to delay
• Transport cost of samples
• Testing of samples
• Material storage
• Removal/ replacement of defective matl
• Royalties and patents
• Clearing & protection of trees
• Damage to adjacent interests
• Uncovering of works to be inspected
• Search for cause of defects

CONTRACT DOCUMENTS

GENERAL CONDITIONS