ALUMINA REFINERY
DAMANJODI, ODISHA
3
REG.NO. M&R /TQM/ELECT/QC-39 /2003
UNIT ALUMINA REFINERY
DEPARTMENT ELECTRICAL
SECURITY FILTRATION
HYDRATE FILTRATION
AREA &
PRECIPITATION
3rd & 4th PHASE
MEETING DAY EVERY WEDNESDAY
11 AM
4
OUR TEAM
J.PASAYAT
FACILITATOR .Mgr (ELEC.)
5
IDENTIFICATION OF AREA PROBLEMS
(THROUGH BRAINSTORMING)
SL NO PROBLEMS CATEGORY
6
IDENTIFICATION OF AREA PROBLEMS
(THROUGH BRAINSTORMING)
SL NO PROBLEMS CATEGORY
11 There is no facility to check sample grease of HT motors A
12 PPT motors exposed to rain environment B
7
IDENTIFICATION OFAREA
IDENTIFICATION OF AREA PROBLEMS
PROBLEMS
(THROUGH BRAINSTORMING)
(THROUGH BRAINSTORMING)
SL NO PROBLEMS CATEGORY
22 Some time motor’s temperature raising high while running. A
23 Pendant problem in PPT hoist. A
24 Difficulties on greasing Sump pump 815 & 816. B
25 T.B. push type connector problem of Disc filter ‘s LCP. A
26 No feeder getting close in test position of H.T. Panels. C
27 Carbon deposition over the power contacts of Vacuum pumps B
28 Frequent brake failure in disc filters. A
8
IDENTIFICATION OF AREA PROBLEMS
(THROUGH BRAINSTORMING)
SL NO PROBLEMS CATEGORY
33 Frequent failure of VFD (ABB) cooling system leading to drive tripping B
41 Inter stage cooler motors having low current even it is running in full load. A
9
IDENTIFICATION OF AREA PROBLEMS
(THROUGH BRAINSTORMING)
SL NO PROBLEMS CATEGORY
43 Continuous glowing of light in unmanned sub – station. A
44 Indication lamps are getting fuse in ht panel A
45 HT drive feed back problem at the time of starting the motor A
10
IDENTIFICATION OF AREA PROBLEMS
(THROUGH BRAINSTORMING)
SL NO PROBLEMS CATEGORY
53 Frequent failure of control fuses of limit switches. B
11
IDENTIFICATION OF AREA PROBLEMS
(THROUGH BRAINSTORMING)
SL NO PROBLEMS CATEGORY
63 Siemens VFD trips when there is power failure. A
12
DETAILS OF PROBLEM
74
45
29
3 SPRING CHARGING OF INCOMMER OF PMCC NOT TAKING PLACE AS PER EFFICIENCY INCREASED
PROCEDURE.
4 IMPROPER OPERATION OF PPT MODULES AVAILABILITY ENSURED
8 HOIST OF 05 AREA IS NOT GOING TO ITS GROUND LANDING POSITION. EFFICIENCY INCREASED
14
BENEFITS FROM COMPLETED PROJECTS
SL. SOLVED PROBLEMS BENEFITS
NO
14 FAILURE OF INDICATION SYSTEM IN SWITCH BOARD. EFFICIENCY INCREASED
15 DIFFICULT TO REPLACE MOTOR OF GREASE PUMP OF BOKELA DISC FILTER. EFFICIENCY INCREASED
16 CONTINIOUS GLOWING OF LIGHTS IN UNMANNED SUB – STATION. Rs.3,00,982./-
17 FAILURE OF UNLOCK LIMIT SWITCH OF KELLY FILTERS. AVAILABILITY INCREASED
18 IMPROPER SHUT DOWN SYSTEM IN KELLY FILTERS. Rs.44,352/-
(UNNECESSARY RUNNING OF HYDRAULIC OIL PUMP)
19 IDLE RUNNING OF KELLY FILTER WASH WATER PUMP NO 383. Rs.74,244/-.
20 ELEMINATING IDLE RUNNING OF HYDRO-COUPLER MOTOR IN HT PUMP 755 B. Rs.1,46,355/-
21 FREQUENT BREAK DOWN OF DISC FILTER FLOOR CRANE. Rs.28,700/-
22 UNSAFE WORKING CONDITION WHILE CCL CHARGING IN KELLY FILTER. SAFETY ENSURED
23 DIFFICULTIES IN RACK IN/ OUT IN ALSTHOM / BCH MOTOR MODULE. SAFETY ENSURED
24 DIFFICULTIES IN ASSESSING OIL LEVEL IN DAY TANK OF DG SETS. AVAILABILITY INCREASED
25 HARD APPROACH TO SUMP PUMP 815 & 816. SAFETY ENSURED
26 FREQUENT PROBLEM IN L & T MAKE LT MODULES.
Rs. 6,25,200 /-
27 FREQUENT PROBLEM IN 4TH PHASE DISC FILTER LCP AVAILABILITY INCREASED
Rs.
28 PROBLEM IN DIASTER FEED PUMP. 77,25,282/- Rs.10,00,000 /-
07 NOS
C' CATEGORY
29 NOS
16
SELECTION OF PROBLEM (FROM “A”CATEGRY)
SL NO PROBLEM DESCRIPTION
1 FREQUENT TRIPPING OF ASB-494
2 BCH MODULE INSERTING PROBLEM
3 CHOCKING OF COOLING AIR SUCTION PATH IN SEED TK AGTR MOTORS
17
SELECTION OF PROBLEM
SL NO PROBLEM DESCRIPTION
17 FREQUENT BURNING OF CLOSING COIL OF PMCC 386 & 387.
18
SELECTION OF PROBLEM
(MULTIVOTING METHOD)
19
SELECTION OF PROBLEM
(MULTIVOTING METHOD)
NO OF
SL NO SHORT LISTED PROBLEMS VOTES
20
SELECTION OF PROBLEM
(CRITERIA RANKING)
SL
NO. HEADS WEIGHTAGE
1 PRODUCTION 0.6
2 SAFETY 0.2
3 INTERNAL CUSTOMER SATISFACTION 0.2
21
SELECTION OF PROBLEM
(CRITERIA RANKING)
PRODUCTION HEAD(WEIGHTAGE SCALE:0.1-0.6)
NKR MKN RKS MDH MKP DG KB PKC TOTAL
PROBLEM-1 0.5 0.6 0.5 0.6 0.3 0.5 0.6 0.5 4.1
PROBLEM-2 0.4 0.5 0.4 0.5 0.4 0.4 0.5 0.4 3.5
PROBLEM-3 0.6 0.3 0.6 0.3 0.4 0.6 0.3 0.6 3.7
PROBLEM-4 0.6 0.5 0.6 0.5 0.6 0.6 0.5 0.6 4.5
PROBLEM-5 0.3 0.4 0.3 0.4 0.5 0.3 0.4 0.3 2.9
PROBLEM-6 0.2 0.3 0.2 0.3 0.4 0.2 0.3 0.2 2.1
PROBLEM-7 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 2.4
PROBLEM-8 0.4 0.2 0.3 0.4 0.4 0.4 0.3 0.4 2.8
SAFETY HEAD (WEIGHTAGE SCALE: 0.1-0.2)
NKR MKN RKS MDH MKP DG KB PKC TOTAL
PROBLEM-1 0.2 0.1 0.2 0.2 0.1 0.2 0.2 0.1 1.3
PROBLEM-2 0.1 0.2 0.2 0.1 0.2 0.2 0.1 0.2 1.3
PROBLEM-3 0.1 0.1 0.2 0.1 0.1 0.2 0.1 0.1 1
PROBLEM-4 0.2 0.2 0.1 0.2 0.2 0.1 0.2 0.2 1.4
PROBLEM-5 0.1 0.2 0.2 0.1 0.2 0.2 0.1 0.2 1.3
PROBLEM-6 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.8
PROBLEM-7 0.2 0.1 0.1 0.2 0.1 0.1 0.2 0.1 1.1
PROBLEM-8 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.8
22
SELECTION OF PROBLEM (CRITERIA RANKING)
HEADS
23
SELECTED PROBLEM
24
MILE STONE CHART (PLAN)
NAME OF QC AREA INCHARGE FACILITATOR TEAM:
SYNERGY MR.R.N SWAIN. AGM(ELCT.) MR J. PASAYAT. MGR.(ELCT.) Md. HUSSAIN
PROJECT- INTERRUPTION IN REASON FOR SELECTION N.K.RATH
EMERGENCY POWER TO INCREASE AVAILABILITY OF EMERGENCY POWER. D.GOPE.
CRITICAL DRIVES OF 4TH MK NAYAK
PHASE. MK PANDA
PROJECT NO-30 DATE OF STARTING PLANNED DATE OF COMPLETION K BHOI
10.06.15 31.12.15 PK CHETTY
RK SENAPATI
SL
ACTIVITIES / WEEK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
NO
1 IDENTIFICATION OF PROBLEM
2 SELECTION OF PROBLEM
9 PROBABLE RESISTANCE
10 TRIAL IMPLEMENTATION
11 REGULAR IMPLEMENTATION
12 FOLLOW UP/REVIEW
25
MINES
DEFINITION OF THE PROBLEM
HIGH LEVEL FLOW DIAGRAM
26
EVAPORATION
DEFINITION OF THE PROBLEM (ABOUT PRECIPITATION AREA)
CLASSIFYING
16
CYCLONE
T 16
INLET AT 100 0C H T 16
H T 16
H T 16
H T 16
PLATE HEAT EXCHANGER H T 16
H T 16 PRODUCT FILTER
H T 16
H T 16
TANK
DEFINITION OF THE PROBLEM
(POWER FEEDING SYSTEM)
EMERGENCY
POWER
PPT AGITATOR
UNIT
SUBSTATION
06 - EX
LOOP
SUB
STATION
GRID SUPPLY
DEFINITION OF THE PROBLEM
(ELECTRICAL DISTRIBUTION SYSTEM TO CRITICAL DRIVES)
US-06EX
TRF 3311 & 3312 SWBD-
407
PPT /
CDS LS-02 SEED
TANK
AGTR.
US-06EX
TRF-3309 & 3310 SWBD-
406
29
DEFINITION OF THE PROBLEM
(EMERGENCY DG POWER)
BOARD-407
DG POWER -1250 KVA DG SWITCH BOARD-409 +
PPT
TANK
30
DEFINITION OF THE PROBLEM
(WHEN EMERGENCY POWER FAILS)
EMERGENCY 06E
POWER ELECTRICAL
PANEL
PPT SWITCH BOARD-406
&407
31
DEFINITION OF THE PROBLEM
(IMPACT)
( DUE TO POWER INTERRUPTION)
1. Settling of precipitation & seed tanks.
2. Huge tank revival cost.
3. Deterioration of production quality.
4. Stoppage of process for long periods.
5. Huge production loss.
6. Fearness among area people.
7. Bad impression on area as well as on department.
8. Chances of accident / flashover.
9. Safety hampered.
10. Internal customer dis-satisfaction.
32
DEFINITION OF THE PROBLEM
34
GOAL
35
ANALYSIS OF PROBLEM
HOW By studying.
36
ANALYSIS OF PROBLEM
(DATA ON NORMAL POWER FAILURE & INTERRUPTION OF EMERGENCY POWER) JULY”14 TO JUNE”15
1 28-07-14 No
2 31-07-14 No
3 03-08-14 Yes
4 19-08-14 No
5 10-10-14 No
6 11-11-14 Yes
7 10-03-15 No
8 17-04-15 No
9 18-06-15 Yes
37
ANALYSIS OF PROBLEM
(LOSSES)
1.
LOSSES
SL EFFECTS NUMBERS
(In Rupees )
Settling of
1 01 6,00,000.00
precipitation tanks.
3. Process hampered.
4. If two adjacent tanks settle then total phase will hampered for longer period.
38
ANALYSIS OF PROBLEM
(DATA ON LOSSES)
39
IDENTIFYING THE CAUSES
(THROUGH BRAINSTORMING)
1. No fuel.
2. Outgoing Breaker problem.
3. Relay malfunctioning.
4. DG AMF panel breaker problem.
5. Battery problem.
6. DG in over load.
40
C & E ANALYSIS
41
C & E ANALYSIS
SWBD 409
SWBD- 409
I/C
BREAKER PROBLEM OUT GOING
BREAKER PROBLEM
NO STANDBY
I/C,DG
TWO DG SETS
RUNNING REQUIRED
42
C & E ANALYSIS
407- SWBD
RELAY
MALFUNCTION TWO DG RUNNING REQUIRED
OVER LOADING
SPURIOUS RATING OF AGTR. MOTOR
TRIPPING IS HIGH (DESIGN)
I/C BRKR
PROBLEM
CLOSING COIL BURNT EACH PPT DRAWS MORE CURRENT
43
IDENTIFIED ROOTCAUSES
44
VALIDATION OF ROOT CAUSE
1. Fuel solenoid problem.
2. Radiator jamming.
Radiator problem may be there but it is
looked after by mech. Dept. so valid but not actionable.
45
4. Relay malfunctioning.
Sl No Date DG No Remarks
Looked after by (Not valid)
testing group
(Not valid)
46
Root cause -6
Late detection of DG overload.
DG DG
409 DG SWBD
407 SWBD
20 NOS
PPT MOTOR M M
64KW
48
Root cause -7
Insufficient capacity in 407-SWBD(in case of one DG trip).
Load calculation of DG
DG-1001(section-A) DG-1002(section-B)
SL. DRIVES CURRENT SL. DRIVES CURRENT
NO. NO. In Amps NO. NO. In Amps
1 PPT-1111 100 1 PPT-1110 92
2 PPT-1113 103 2 PPT-1112 94
3 PPT-1116 90 3 PPT-1115 106
4 PPT-1117 91 4 PPT-1119 96
5 PPT-1118 90 5 PPT-1120 98
6 PPT-1123 95 6 PPT-1121 90
7 PPT-1124 90 7 PPT-1125 102
8 PPT-1126 90 8 PPT-1127 96
9 PPT-1128 92 9 PPT-1129 80
Total 9 no.s 841 TOTAL=1695A Total 9 no.s 854
49
Root cause -7 Insufficient DG capacity in 407-SWBD
(in case of one DG trip).
OBSERVATION:
DG CAPACITY=1740Amps
SWBD-406
LOAD LTG
409 408
406 LTG
BOARD
407 ENTRANCE
US 06EX
52
Total substation light is from one DG.
Root cause -9
DG DG
SWBD-406
LOAD LTG
53
VALIDATION OF ROOT CAUSE
N
No data Charger, battery are being checked regularly and
O
11. Battery
electrolyte low. found preventive maintenance is being done every month . T
54
DEVELOPMENT OF SOLUTION
(ROOT CAUSE-1)
Late detection of
DG overload. Deputation of shift person to DG
room for monitoring load.
Due to insufficient
There is two DG rooms (4No.s DG sets)
manpower, it is not
Not Accepted
possible.
55
DEVELOPMENT OF SOLUTION
(ROOT CAUSE-2)
1. No stand by
Addition of new Standby It takes more cost
DG incomer NOT ACCEPTED
modules for critical drives (2 in1 isolator 400A +module400A
in 406- in switch board 407.
+cable300sq mm 25mtrs)
SWBD.
56
DEVELOPMENT OF SOLUTION
(ROOT CAUSE-3)
Stoppage of tank
There is a load requirement of Not
around 2000A after stoppage of
agitator which are
offline tanks against capacity of accepted
not in line or CCL.
1600A.
57
DEVELOPMENT OF SOLUTION
(ROOT CAUSE-4)
Lighting to be
segregated. Part of the Light will still be there in case Accepted
lights to be supplied one DG has any problem.
from other DG set.
58
ACCEPTED SOLUTIONS
59
DEVELOPMENT OF SOLUTION
(ACTION PLAN)
SL TARGET DATE
ACTION PLAN RESPONSIBILITY RESULT
NO. (PLANNED)
60
FORESEEING PROBABLE RESISTANCE
61
61
TRIAL IMPLEMENTATION OF SOLUTION
62
TRIAL IMPLEMENTATION OF SOLUTION
No stand by DG incomer SWBD - 406 Use of spare out going breaker as 22.12.2015
in 406-SWBD. incomer .
X X
X X X X
63
TRIAL IMPLEMENTATION OF SOLUTION
SWBD-407
B/C-1 B/C-2 B/C-3
X X X
X X X X
64
DG DG
DG
409 DG SWBD
2 spares CALCINATION
TWO
We need one breaker in each section of the switchboard. But we there was two spare breakers
in section 1 & no spare breaker in section2.
So brain storming was carried out & decided to shift calcination feeder breaker to section-1. This
will make one breaker free in each section of the Switch board.
65
TRIAL IMPLEMENTATION OF SOLUTION
ROOT CAUSE NO- 4 LOCATION SOLUTION IMPLEMENTED
DATE
Total substation light is Lighting to be segregated. Part of
from one DG. AT US-06EX the lights to be supplied from other 29.12.2015
DG set.
409 408
406 LTG
BOARD
US
06EX
407 ENTRANCE
TUBE LIGHT
66
US 06EX TUBE LIGHT
409 408
406 LTG
BOARD
ENTRANCE
407 ENTRANCE
67
COST OF IMPLEMENTATION
SL.NO ITEMS QUANTITY COST
In Rs.
1. Power cable with glanding & 110 x 4 3,52,000
termination runs=440mtr
3.5x300sqmm Al.
2 Control cables 210mtr 16,800
Total 3,96,050
All materials listed above were taken from balance of expansion project.
68
CHECKING PERFORMANCE
TRIAL
WORK DONE LOCATION IMPLEMENTATION NO OF OBSERVATION RESULT
DATE INSTANCES
Monitoring of
loading of all DG set
in shift room. US-06E 17.12.2015 03 Monitored satisfactory
Provision of second
incomer in SWBD SWBD-406
406. 22.12.2015 03 Second Incomer satisfactory
could take the
load.
Provision of
additional DG SWBD-409
source at DG 27.12.2015 03 Load was given satisfactory
Distribution without voltage
board:409 drop.
Provision of partial
lighting from 3RD US-06EX 29.12.2015 03 Illumination was satisfactory
phase DG set. sufficient .
After success of trail implementation the solutions were kept in line permanently & declared as
regular implementation.
69
CHECKING PERFORMANCE
Resumption of Power
after implementation
Solution implemented GOAL
within 15 minutes
(Yes/No)
70
FOLLOW UP/ REVIEW &
RECURRENCE PREVENTION
CHECK LIST
06 months
2. Spare breaker
06 months
3. Cable tightness
06 months
4. Lighting circuit
71
CHECKED BY
FOLLOW UP/ REVIEW &
RECURRENCE PREVENTION
STANDARDIZATION
72
TANGIBLE BENEFITS
OPPORTUNITY BENEFIT
RISK due to non
SWBD NO. availability of COST Tentative cost Remarks
emergency power saving in Rs.
Tank cleaning Per hour
cost & phase production:1500/24
Settling of seed tank stoppage of =62.5 ton.
406 agitator, SL tank one phase for 25,00,000 4 hr production
agitator at least 4 hours loss: 62.5x4=250
ton. Price of
Alumina per kg is
Rs.10.
TOTAL Rs.49,00,000 /-
73
INTANGIBLE BENEFITS
74
MILE STONE CHART (PLAN v/s ACTIVITY)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
ID EN T IF IC A T ION OF PR OB LEM
S E LE C T IO N O F P R O B LE M
D E F IN IN G T H E P R O B LE M
A N A LY S IN G T H E P R O B LE M
ID E N T IF Y IN G T H E C A US E S
F IN D IN G R O O T C A US E S
A N A LY S IS O F R O O T C A US E S
D E V E LO P IN G T H E S O LUT IO N
P R O B A B LE R E S IS T A N C E
T R IA L IM P LE M E N T A T IO N
R E G ULA R IM P LE M E N T A T IO N
F O LLO W UP / R E V IE W
75 PLANNED ACTUAL
QC TOOLS & TECHNIQUES USED
FLOW DIAGRM
CAUSE & EFFECT DIAGRAM
BRAINSTORMING
DATA COLLECTION
MILESTONE CHART
76
WE ARE THANKFUL TO:
77
OUR NEXT PROJECT
78
Thank You
SYNERGY TEAM
80
Root cause -9 Total substation lighting is from one DG.
409 408
406 LTG
BOARD
407 ENTRANCE
81
ANALYSIS OF PROBLEM
(Interruption of power to critical drives)
SL NO. DATE DG NO. NATURE OF FAILURE IMPACT
82
83
06E DG Distribution board 384 (3rd phase) 06Ex DG Distribution board 409. 4th phase)
84
VALIDATION OF ROOT CAUSE
1. Late detection of DG overload.
Charger problem.
Battery electrolyte low.
Connecting lead problem.
STEAM CCL
No fuel.
85
APPROVED FINANCIAL VETTING
86
Ppt agtr ,motor,switch board,dg,trf
PHOTO
87
NORMAL POWER FAIL / INTERRUPTION
88
DEFINITION OF THE PROBLEM
(AN OVERVIEW OF PRECIPITATION TANKS)
89
747
US-6EX
P
ELECTRICAL SWITCH BOARD
O
PPT AGTR PPT AGTR
MODULE
TRF MODULE TRF 1029
DG
3311
POWER
3312 W
PPT AGTR PPT AGTR
MODULE MODULE
1250KV R
DG 1001
&1002
90
DEFINITION OF THE PROBLEM
GRID POWER
(NORMAL POWER
FROM CDS)
PPT SWBD No-407 (CRITICAL DRIVES)