Cost
Effort Planned/Spent ($000’s):
Man Months Planned Spent EAC G On Track N Not Started Timeline Duration
166.0* $3,149* $2,210* $3,509* A At Risk H On Hold Proposed
R Off Track C Completed Progress
Current FTE:
Group Planned Spent
Operations 7.5 5.1 Project Orig. Rev.
IT 6.8 7.1 1.Project charter Aug 10
2.Business requirements Apr 11 Aug 10 C
* Incomplete estimate, refer to underlying projects 3.Web GUI Apr 10 Dec 10 C
4.Standard reports Sep 10 Jan 12 C
5.Workflow module Mar 11 G
6.Standard alerts Apr 10 Mar 11 G
Stakeholders
7.Return confirm workflow Mar 11 G
Sponsor Organization: Operations
8.Document creation Jun 11 G
Initiative Sponsor: Baduchi
Initiative Owner: Davis 9.Custom reports Apr 10 Jun 11 A
Initiative Manager: Pearlman 10.Custom alerts & workflow Aug 11 G
IT Manager: Albert
4Q10 1Q11 2Q11 3Q11 4Q11 1Q12 2Q12
Project Office: TBD