Introduction to Project

Planning

YOKOGAWA INDIA LIMITED


AGENDA:

The Need of Project Planning


The Language of Scheduling
The project scheduling process
Example: Replacement of a Power Transformer

YOKOGAWA INDIA LIMITED


The Need of Project Planning

Project planning is done


•To complete the project in time
•To prevent and control delays
•To use resources efficiently
Effective monitoring and control is possible..

YOKOGAWA INDIA LIMITED 3


The Language of Scheduling

Activity
– task or set of tasks
– use resources
Event
– state resulting from completion of one or more activities
– consume no resources or time
– predecessor activities must be completed
Network
– diagram of nodes and arcs
– used to illustrate technological relationships
Path
– series of connected activities between two events
Critical Path
– set of activities on a path that if delayed will delay completion of project

YOKOGAWA INDIA LIMITED


The Language of Scheduling continued
Milestone and Baselines
– Milestone are used as points of payment,
measurement of progress on the project and for
determining baselines.

– IEEE definition of baseline includes “a formally agreed


specification that then serves as the basis for further
development”
• Functional baseline: This document is the basis for all
design and implementation, and in particularly it is
the basis for system testing and acceptance.

YOKOGAWA INDIA LIMITED


The project scheduling process

Developing a project schedule includes the following


steps:
– Establish the detailed WBS
– Determine the task dependence or precedence
– Identify time lags
– Roll-up time estimates from bottom level WBS
– Assign resources (i.e. people) to tasks & resolve conflicts
– Identify milestone dates
– Implement trade-off if schedule is not acceptable

YOKOGAWA INDIA LIMITED


Project Planning Methods

Main methods used in project planning:


Gantt Diagram
PERT Diagram
– Critical Path

YOKOGAWA INDIA LIMITED 7


Example:
Replacement of a Power Transformer

No Activity Start End


1 Replacement design 1.6.03 5.6.03
2 Trans. Procurement 6.6.03 18.6.03
3 Announce Cut down 8.6.03 12.6.03
4 Electricity Cut Down 13.6.03 13.6.03
5 Remove old trans. 14.6.03 15.6.03
6 Place new trans. 19.6.03 22.6.03
7 Tests and control 23.6.03 23.6.03
8 Electricity connection 24.6.03 24.6.03

YOKOGAWA INDIA LIMITED 8


Transformer Replacement (Gantt Chart)

ay '03 01 Jun '03 08 Jun '03 15 Jun '03 22 Jun '03


IDActivity W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
1 Design

2 Procurement

3 Announcement
4 Cut dow n

5 Removal of old tr.

6 Place new tr.


7 Tests

8 Electricity is on!

YOKOGAWA INDIA LIMITED 9


Pert Chart

Design Procurement New TR. Control

1 5 days 2 13 days 6 4 days 7 1 day


Mon 01.06.98
Fri 05.06.98 Sat 06.06.98
Thu 18.06.98 Fri 19.06.98
Mon 22.06.98Tue 23.06.98
Tue 23.06.98

Announcement Cut Dow n Old TR. Turn on Electricity

3 5 days 4 1 day 5 2 days 8 1 day


Mon 08.06.98
Fri 12.06.98 Sat 13.06.98
Sat 13.06.98Sun 14.06.98
Mon 15.06.98 Wed 24.06.98
Wed 24.06.98

YOKOGAWA INDIA LIMITED 10


Pert Chart

Design Procurement New TR. Control

1 5 days 2 13 days 6 4 days 7 1 day


Mon 01.06.98
Fri 05.06.98 Sat 06.06.98
Thu 18.06.98 Fri 19.06.98
Mon 22.06.98Tue 23.06.98
Tue 23.06.98

Announcement Cut Dow n Old TR. On

3 5 days 4 1 day 5 2 days 8 1 day


Mon 08.06.98
Fri 12.06.98 Sat 13.06.98
Sat 13.06.98 Sun 14.06.98
Mon 15.06.98 Wed 24.06.98
Wed 24.06.98

YOKOGAWA INDIA LIMITED 11


Modified Gantt Chart

02 Jun '03 09 Jun '03 16 Jun '03 23 Jun '03 30


ID Task Name Duration T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
1 Replacement Design 5 days
2 Trans. Procurement 12 days
3 Announce Cut dow n 4 days
4 Electricity Cut Dow n 1 day
5 Remove old trans. 1 day
6 Place new trans. 1 day
7 Tests and control 1 day
8 Electricity connection 1 day

YOKOGAWA INDIA LIMITED 12


Critical Path

Design Procurement New tr. Placement Control

1 5 days 2 13 days 6 4 days 7 1 day


Mon 01.06.98
Fri 05.06.98 Sat 06.06.98
Thu 18.06.98 Fri 19.06.98
Mon 22.06.98Tue 23.06.98
Tue 23.06.98

Cut dow n Cut dow n Removal Electricity

3 5 days 4 1 day 5 2 days 8 1 day


Mon 08.06.98
Fri 12.06.98 Sat 13.06.98
Sat 13.06.98 Sun 14.06.98
Mon 15.06.98 Wed 24.06.98
Wed 24.06.98

YOKOGAWA INDIA LIMITED 13


Resources

31 May '98 07 Jun '98 14 Jun '98 21 Jun '98 28


Details
ID Resource Name S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
1 Eng Ahm et Work ####
####
####
####
####
####
####
####
########
####
####
####
####
####
########
####
####
####
####
####
########
Design Work ####
####
####
####
####
ProcurementWork ####
####
####
########
####
####
####
####
####
########
####
Removal Work ####
####
Work
New tr. Placement ####
####
####
####
Control Work ####
Electricity Work ####
2 Off Mehm et Work ####
####
####
########
####
####
####
####
####
########
####
ProcurementWork ####
####
####
########
####
####
####
####
####
########
####
Announce Cut Work
down ####
########
####
####
3 Tech Cemal Work ####
####
#### ####
####
####
####
########
Cut down Work ####
Removal Work ####
####
Work
New tr. Placement ####
####
####
####
Control Work ####
Electricity Work ####
Work