1) RFO-06,Kopar
2) Br no 122, Ulhas
2) Br no 126, Bhiwandi
4) Br no 135-Kamvadi
5) Br no 19, Damanganga
Sr. no Item Letter No Action By Remarks
1 D&D of Abutments IISLT-1745 Engineer
Foundation &
Substructure A1 & A2
2 D & D of Embankment & IISLT-1796 Engineer
Slope
6) Br no 60-Par
Sr. no Item Letter No Action By Remarks
1 Revised Alignment & C/S PMC-14796 Employer
2 D&D of Abutments IISLT-1767 Engineer
(Substructure) (A1&A2)
Alternative D&D of Sheet IISLT-1486 Engineer
Pile Cofferdam at P3
7) Br no 240, Tapi
Sr. no Item Letter No Action By Remarks
1 D&D of Well Foundations IISLT-1781 Engineer
at A1 & A2
2 D&D of Well Foundation IISLT-1777 Engineer
at P12, P1, P13 & P14
3 Confirmatory IISLT-1803 Engineer
Geotechnical Investigation
at A1, P1, P12, P13, P14
and A2
IIS – L&T Consortium Dedicated Freight Corridor Corporation
CT P-15A Design Requirement 5
4) RFO-07, Sanjali
• Bearings- Approval for M/s Mageba Bearing Manufacturer –IISLT-1755 dated 25-07-2018
Br No 126
Sep-18 Oct-18 Nov-18 Dec-18
Retaining Wall
Bearing Pedestal
Embankment Works
Superstructure Farbication Works
*Design Requirement-
Approval for Bearing drawings required for casting bearing pedestal
Approval for Retaining Wall Drawings and Variation approval
Approval for Embankment material
Approval of Fabrication Drawings and Engaging Inspection Agency
Br No 135
Sep-18 Oct-18 Nov-18 Dec-18
Jetty Works for P1
P1 foundation - Sheetipiling, excavation and Casting of Foundation
Bearing Pedestal for A1, P2 and A2
A1 backfilling Works
Embankment Works
Superstructure Fabrication
*Requirement-
Approval for Bearing drawings required for casting bearing pedestal
Approval for Embankment material required to commence the embankment Works
Approval of Fabrication Drawings and Engaging Inspection Agency
Br No 60
Sep-18 Oct-18 Nov-18 Dec-18
Jetty Works for P1
Foundation Works up to Well cap - A1, P1, P4, A2
Jetty Works for P2 and P3
Cofferdam Works for P2
Cofferdam Works for P3
Well casting and sinking Works for P2
Substructure Works A1, P1
Br No 19
Sep-18 Oct-18 Nov-18 Dec-18
Abutment A1 Works - Soldier Pile, Excavation and casting of
foundation
Br No 240
Well casting and sinking Works for P7, P8, P9, P10, P11
• Bridge No RFO-06
• Uncharted Utility Shifting Works based upon Variation cost approval
• Bridge No 122
• Pile Load Testing Works
• Engineer to issue Variation Order
• Bridge No RFO-07
• Engineer to issue Variation Order
• Engineer’s instruction to change the superstructure Design would involve complete
redesign and call for additional time
• Bridge No 36B
• Employer’s discussions with GAIL going on for encasing of pipelines
• Employer to confirm the span length required for the Bridge
• Bridge No 38
• Span required for the bridge yet to be confirmed by the Employer
• Bridge No 239
• The GAD had been submitted by the Contractor, Employer to get approval of the GAD
from SUDA.