Sei sulla pagina 1di 16

CT P-15A Project Review: August 2018 1

WDFCCIL Phase -2 Package CTP – 15


A
Special steel bridges in JNPT –Vadodara
section

Date: 13th Aug 2018


PMC-2R
OCG CONSORTIUM Venue: Mumbai
IIS – L&T Consortium Dedicated Freight Corridor Corporation
CT P-15A Design Requirement 2

1) RFO-06,Kopar

Sr. no Item Letter No Action By Remarks


1 Revised Alignment & C/S IISLT-1197 Engineer
2 GAD of Rising Mains PMC-13763 Employer

2) Br no 122, Ulhas

Sr. no Item Letter No Action By Remarks


1 Revised Alignment & C/S PMC-9622 Employer

2) Br no 126, Bhiwandi

Sr. no Item Letter No Action By Remarks


1 Revised Alignment & C/S IISLT-1730 Engineer
2 Superstructure Erection IISLT-1748 Engineer
Scheme (Full Span)

IIS – L&T Consortium Dedicated Freight Corridor Corporation


CT P-15A Design Requirement 3

4) Br no 135-Kamvadi

Sr. no Item Letter No Action By Remarks


1 Revised Alignment & C/S IISLT-1062 Engineer

5) Br no 19, Damanganga
Sr. no Item Letter No Action By Remarks
1 D&D of Abutments IISLT-1745 Engineer
Foundation &
Substructure A1 & A2
2 D & D of Embankment & IISLT-1796 Engineer
Slope

IIS – L&T Consortium Dedicated Freight Corridor Corporation


CT P-15A Design Requirement 4

6) Br no 60-Par
Sr. no Item Letter No Action By Remarks
1 Revised Alignment & C/S PMC-14796 Employer
2 D&D of Abutments IISLT-1767 Engineer
(Substructure) (A1&A2)
Alternative D&D of Sheet IISLT-1486 Engineer
Pile Cofferdam at P3
7) Br no 240, Tapi
Sr. no Item Letter No Action By Remarks
1 D&D of Well Foundations IISLT-1781 Engineer
at A1 & A2
2 D&D of Well Foundation IISLT-1777 Engineer
at P12, P1, P13 & P14
3 Confirmatory IISLT-1803 Engineer
Geotechnical Investigation
at A1, P1, P12, P13, P14
and A2
IIS – L&T Consortium Dedicated Freight Corridor Corporation
CT P-15A Design Requirement 5

4) RFO-07, Sanjali

Sr. no Item Letter No Action By Remarks


1 Revised Alignment & C/S IISLT-1795 Engineer
2 Design & Drawing of IISLT-1800 Engineer
Substructure &
Foundation for Piers &
Abutments A1 & A2
3 RSI IISLT-1636 Engineer

IIS – L&T Consortium Dedicated Freight Corridor Corporation


CT P-15A Special Approvals Required 6

• Bearings- Approval for M/s Mageba Bearing Manufacturer –IISLT-1755 dated 25-07-2018

• Source Approvals for Embankment materials


• Payegaon, Ovali, Vehele and Saphe for Maharashtra-IISLT 1550 and 1555
• Pramukh, Nilkanth for Gujarat, IISLT-1798 dated 08-08-2018

IIS – L&T Consortium Dedicated Freight Corridor Corporation


CT P-15A Four Months look ahead plan for Br No 126, BHIWANDI 7

Br No 126
Sep-18 Oct-18 Nov-18 Dec-18
Retaining Wall
Bearing Pedestal
Embankment Works
Superstructure Farbication Works

*Design Requirement-
Approval for Bearing drawings required for casting bearing pedestal
Approval for Retaining Wall Drawings and Variation approval
Approval for Embankment material
Approval of Fabrication Drawings and Engaging Inspection Agency

IIS – L&T Consortium Dedicated Freight Corridor Corporation


CT P-15A Four Months look ahead plan for Br No 135, Kamwadi 8

Br No 135
Sep-18 Oct-18 Nov-18 Dec-18
Jetty Works for P1
P1 foundation - Sheetipiling, excavation and Casting of Foundation
Bearing Pedestal for A1, P2 and A2
A1 backfilling Works
Embankment Works
Superstructure Fabrication

*Requirement-
Approval for Bearing drawings required for casting bearing pedestal
Approval for Embankment material required to commence the embankment Works
Approval of Fabrication Drawings and Engaging Inspection Agency

IIS – L&T Consortium Dedicated Freight Corridor Corporation


CT P-15A Four Months look ahead plan for Br No 60, Par 9

Br No 60
Sep-18 Oct-18 Nov-18 Dec-18
Jetty Works for P1
Foundation Works up to Well cap - A1, P1, P4, A2
Jetty Works for P2 and P3
Cofferdam Works for P2
Cofferdam Works for P3
Well casting and sinking Works for P2
Substructure Works A1, P1

IIS – L&T Consortium Dedicated Freight Corridor Corporation


CT P-15A Four Months look ahead plan for Br No 19, Damanganga 10

Br No 19
Sep-18 Oct-18 Nov-18 Dec-18
Abutment A1 Works - Soldier Pile, Excavation and casting of
foundation

Pier Works up to Pier cap

IIS – L&T Consortium Dedicated Freight Corridor Corporation


CT P-15A Four Months look ahead plan for Br No 240, Tapi 11

Br No 240

Sep-18 Oct-18 Nov-18 Dec-18


Foundation Works up to Well cap - A1, P1, P2, P3, P4, P12, P13,
P14, A2

Well casting and sinking Works for P7, P8, P9, P10, P11

Pier Works - A1, P1, P13, P14, A2

Island Making P7 and P8

Cofferdam Works for P10

IIS – L&T Consortium Dedicated Freight Corridor Corporation


CT P-15A Four Months look ahead plan for Other Bridges 12

• Bridge No RFO-06
• Uncharted Utility Shifting Works based upon Variation cost approval
• Bridge No 122
• Pile Load Testing Works
• Engineer to issue Variation Order
• Bridge No RFO-07
• Engineer to issue Variation Order
• Engineer’s instruction to change the superstructure Design would involve complete
redesign and call for additional time

IIS – L&T Consortium Dedicated Freight Corridor Corporation


CT P-15A Four Months look ahead plan for Other Bridges 13

• Bridge No 36B
• Employer’s discussions with GAIL going on for encasing of pipelines
• Employer to confirm the span length required for the Bridge

• Bridge No 38
• Span required for the bridge yet to be confirmed by the Employer

• Bridge No 239
• The GAD had been submitted by the Contractor, Employer to get approval of the GAD
from SUDA.

IIS – L&T Consortium Dedicated Freight Corridor Corporation


CT P-15A Approvals for GFC drawings Required up to 31st Aug/15th Sep/30th Sep 14

Items Item Letter No. Date Required by Date

1 Design and Drawings of Bearing 1797 07-08-18 31st Aug

2 Fabrication Drawings 1780 31-07-18 31st Aug


Revised Design and Drawings of Well
3 Foundation of Tapi (A2, P14, P13, P12 1550 04-05-18 31st Aug
and A1)

4 Design and Drawings of Damanganga 1745 18-07-18 31st Aug

Design and Drawings of Retaining Wall


5 15th Sep
(to be resubmitted)

IIS – L&T Consortium Dedicated Freight Corridor Corporation


CT P-15A Approvals for Temporary drawings Required up to 31st Aug/15th Sep/30th Sep 15

Items Item Required by

1 CRS Approval for TAD of Damanganga 31st Aug

2 Well cap Shutter Drawings Tapi 15th Sep

3 Well Cap Shutter Drawings Par 15th Sep

4 Pier Shutter Drawings Tapi 15th Sep

5 Pier Shutter Drawings Par 15th Sep

IIS – L&T Consortium Dedicated Freight Corridor Corporation


CT P-15A 16

IIS – L&T Consortium Dedicated Freight Corridor Corporation