Spec Requirements
End Areas
End-area Volumes
Borrow Pit Volumes
Mass Diagrams
Cost Estimates
Earthwork Specs
Payment based on excavation (Cut)
Specs define methods for cut and fill
Typically not paid for fill
Based on “Excavation measured in
place as computed from survey notes”
Not weighing, counting truck rounds
Look for spec allowing contractor to
dispute volumes in a certain area
Excavation Specs
Common excavation
Determined from survey notes
Describes most of work
Rock/Muck
Rock requires blasting
Muck requires deep dig, granular fill
Before/after volume survey
Haul Payments
Volume payments - $/cy Excavation
Separate lines for common, rock , muck
Free Haul - Stations
Overhaul - $/cy-stations
Borrow - $/cy
Covers cost of lease, haul, reclamation
Waste - $/cy
End Areas
Based on
Cross-sections
Typical section
Area – ft2 CL
Cut
Fill
Construction Grade Staking
Based on “typical section”
Stake centerline, slope “breakouts”
Slope Stakes
w
A c(d ) c( w cs )
2
w 40
A c(d ) 7.6(31.4 ) 390.6
2 2
w c
A (hL hr ) (d L d r )
4 2
40 6.8
A (7.0 6.4) (30.5 29.6) 338.34
4 2
5-Level Sections
1
A (cw hL d L hr d r )
2
1
A (5.8 30 6.9 23.1 6.7 27.3) 258.2
2
Transition Sections
1 w 1
A ( h) ( wh)
2 2 4
1 1
Ac (40 2.6) 15.6 A f (30 2.0) 15.0
4 4
End Area Calculations
Planimeter
Coordinate Calculations
Similar to coordinate area
Start/end at same point
A 12 ( f i di 1 ) ( f i di 1 )
Coordinate Areas