Managing Hard Rock's Rockfest

By Group 5, Section B
Hitesh Jain(PGP10085)
M Aishwarya(PGP10089)
Mayank Kashyap(PGP10093)
Parth Malik(PGP10097)
Praveen Kumar(PGP10101)
Case Facts:
 Hard Rock Café is planning to conduct the annual event
“Rockfest” which expects 100,000 fans
 Vice president Chris Tomasso who is the in charge of Project
management has only 9 months period to plan and execute
 He uses Microsoft project – a project management software
to update his progress
 There are 26 activities to be done to conduct the event
successfully
CRITICAL PATH METHOD:
Critical path and its activities for Rockfest. How long does the
project take ?

 The Critical Path obtained from the above critical chart


where slack is zero is,
 A --->B--> D--> E--> F--> G--> O
 The Time taken for this is 34 weeks.
Critical path and its activities for Rockfest. How long does the
project take ?
 Activities that have slack time of 8 weeks or more are,
 C – 11, K – 11, L -8, M – 8, N – 18, Q – 9, R – 9, V – 12,
W – 12, Y – 12, Z -12.
Major Challenges

• Unexpected surprises/challenges
• Budget shortage
• Control over workers to finish the job in stipulated time
• Shortage in footfall
• One single activity could create a bottleneck for every other
activity
Work Breakdown Structure:
THANKYOU