Sei sulla pagina 1di 16

Project Planning and Scheduling

Demo Class

Project Schedule Updating

Rustam Hafizyar
Ph.D. Candidate, Dept. of Civil Engineering,
Cyprus International University, Nicosia, Northern

Date: 30 /7/ 2019


i

Outline

 Introduction
 Purpose of Schedule Updating
 Project Control Defined
 Baseline Schedule
 Information for Updating Schedules
 Frequency of Updating
 Effect of Adding or Deleting Activities on Logic
 Example Solution
 Reference
1
Project Schedule Updating
Introduction
Schedule updating is simply reflecting actual performance
information:
• Including time of occurrence, and
• Amount of work completed on the schedule

According to Patrick (2004) defined an updated schedule as "revised


schedule reflecting project information at a given data date
regarding completed activities, in progress activities, and changes in
the logic, cost, and resources required and allocated at any activity
level”.
2
Project Schedule Updating
Purpose of Schedule Updating

 Evaluate current project status


• Provide comparison of planned to actual

 Predict Completion date

 Create a Historical Record of the Project

 Better Forecast Needs


• Money, resources

 Better project control


3
Project Schedule Updating
Project Control Defined
Project control comprises following continuous process by Kerzner (2019) are:
 Monitoring work progress
 Comparing it with the baseline schedule and budget
 Finding any deviations, determining where and how much, and analyzing them to
discover the causes
 Taking corrective action whenever and wherever necessary to bring the project back
on schedule and within budget.
• To improve work efficiency,
• To help accelerate the schedule
• To help reduce cost
4
Project Schedule Updating
Baseline Schedule
 A baseline schedule is prepared by the contractor, before the start of the
project, and used for performance comparison.(contract documents.)
 The baseline schedule is also called a target schedule and used by:
contractor and owner.
 It may provide a foundation for resolving any subsequent delay, claim
disputes.
 therefore, a project may have two or more baseline schedules:
one before and one after changes.
5
Project Schedule Updating
Baseline Schedule

According to de Andrade et al, (2019) reviewed the baseline schedules


of project must be reasonable, realistic and take into consideration:
• Work and weather conditions
• The size of project
• Local codes and regulations
• The location of and access to the project site
• The labor market;
• Materials and equipment availability, prices, and delivery and other issues.
6
Project Schedule Updating
Information for Updating Schedules
 Any new information that was not known for the previous update
and relates to the schedule (Wren, 2018).
 This information falls into two main categories:
i. Past information
ii. Future information.
7
Project Schedule Updating
Past information
What has happened since the last update?

 Activities that have started, and the actual start date, percent complete,
and remaining durations
 Activities that are completed, and the actual completion date
 The actual budget spending or resource consumption for each activity

 Past information was divided into two categories: Current and past.
• Past represents information occurred prior to the previous update.
• Current information occurred between the last update and this update.
8
Project Schedule Updating
Future information.
 It comprises any changes such as:
• Any activities that have been added, along with their information
• Any activities that have been deleted
• Activities that have changed in duration, logic, budget, resources, constraints
• Any change to the imposed finish date for the entire schedule
• Any schedule change, such as change in the cost or availability of resources, change
in calendar workdays,
9
Project Schedule Updating
Frequency of Updating
Based on Heldman (2018) describes the five step of frequency are:

 Schedules may be updated monthly, biweekly, weekly.

 Weekly and biweekly are probably the most common.

 Waiting too long to update a schedule may eliminate the effectiveness of updating as a
control tool. (being late in corrective action, create de-motivation on staff).

 Having a long reporting period may encourage procrastinators to put off corrective
measures by using the logic "We'll do it later. There is plenty of time!

 Conversely, a reporting period that is too short may be costly in terms of time
consumption and overhead and reporting costs.
10
Project Schedule Updating
Effect of Adding or Deleting Activities on Logic
 An activity in a schedule is usually like a link in a chain; removing a link may disturb
the whole chain if it is not done properly. As shown in Figure 1 the activity disturb the
whole chain (Mubarak, 2015).

 Therefore, it is strongly recommended that the scheduler review the logic before
making any change.

 Adding a new activity usually has less potential for harming the logic than does
deleting an activity (Mubarak, 2015).

Figure-1: Effect of removing an activity from a schedule: removal of AS250 would disturb
the entire chain (Mubarak, 2015).
Example Solution 11

In example, 10 days after the project has started, you receive the following report:
Activities A and D are complete (actual start and finish dates are given). Activity B started
on day 5. Remaining duration = 2 days. Activity C started on day 2. Some problems were
encountered. Remaining duration = 4 days. The duration for activity F was adjusted to 8
days. Activity J has been canceled. The duration for the new activity P is 4 days. IPA= E. ISA
(immediately succeeding activity) = K.

Figure-2: ( b) Example Solution (Mubarak, 2015).


Solution of Schedule Update 12

Update the logic. Note: When we delete activity J, the schedule must verify
whether we should assign its predecessor to its successor. In other words, would
activity F become a predecessor to activity K.

Figure 3: (c) Update schedule (Mubarak, 2015).


13
Project Schedule Updating
Reference
de Andrade, P. A., Martens, A., & Vanhoucke, M. (2019). Using real project schedule data to
compare earned schedule and earned duration management project time forecasting
capabilities. Automation in Construction, 99, 68-78.
Heldman, K. (2018). PMP: project management professional exam study guide. John Wiley
& Sons.
Kerzner, H. (2019). Using the project management maturity model: strategic planning for
project management. Wiley
Mubarak, S. A. (2015). Construction project scheduling and control. John Wiley & Sons.
Patrick, C. (2004). Construction project planning and scheduling. Pearson Education India.
Wren, A. (2018). Project Management AZ: A Compendium of Project Management
Techniques and How to Use Them: A Compendium of Project Management Techniques and
How to Use Them. Rutledge.
14

THANKS FOR
YOUR ATTENTION

Potrebbero piacerti anche