OUTLINE
STUDY CONCEPT
LOCATION DESIGN
BACKGROUND MASS BALANCE
BASIC
PLANNING
Cianjur
3
STUDY District
Area : 361.463 Ha
LOCATION
Geographically, Cianjur District is located in the
middle of West Java Province, between 6°21 '-
Population :
2.256.589 people
7°25' South Latitude and 106°42'- 107 ° 25' East
Longitude. In general, Cianjur District is divided
into 3 regions, namely the northern Cianjur
region, the central Cianjur region, and the
southern Cianjur region and has total 32
subdistrict.
Cugenan Cianjur Karangteng
g ah
Area : 7.615 Ha Area : 2.614,7 Ha Area : 4.852,5 Ha
Population : Population : Population :
103.378 people 163.828 people 138.891 people
BACKGROUND AND
PROBLEM
IDENTIFICATION
GOAL
TARGET
GAP
EXISTING
CONDITIO
N
SANITATION NATIONAL DOCUMENT : RPJMD & 5
>=80% 18.0
100%
CLEAN WATER
By 2031
CIANJUR AREA
6% By ONE OF SOLUTION
CIANJUR
2021
ACCESS
SERVICE
POPULATION WTP
GOAL TARGET
GAP RIVER
EXISTING CONDITION
WATER
CLEAN WATER SERVICE PDAM ANNUAL GENERAL PROBLEM
SERVICE TARGET
>=67. 13.5
WATER RESOURCE
9% year
CIANJUR AREA
8%
CIANJUR
of 2019 year of
GENERAL
6
N
Area
DESCRIPTION
Water Resources
2018
Installed Utilized
O
(LPS) (LPS)
Cirumput Spring 100,00 74,00
Cilembang Spring 100,00 54,00
Gombong I Drilling Well 15,00 9,00
1. Cianjur
Gombong II Drilling Well 15,00 10,00
Bor Munjul Drilling Well 15,00 11,00
Total 245,00 158,00
Karangteng Hegarmanah Drilling Well 7,00 7,00
2. From Cianjur water resource - 45,00
ah
Pasir Banen Spring 8,00 5,00
Total 15,00 57,00
3 Cugenang - - -
Total 260 215
BASIC
7
DESIGN
PERCENT
AGE
LEVEL
SERVICE
WATER
8
Raw water quality is obtained after laboratory test and the result of these qualities
parameter referring to GovernmentQUALITY
Regulation No. 82 of 2001 concerning the
quality of raw water and Health Ministry Regulation No.492 0f 2010. There are 6
parameter that must be aside and processed as shown in tabel 2.
Standard
Drinking
No Parameter Units Tes result Removal efficiency
water References
standard
1 Turbidity NTU 126 5 Minister of 96,03%
2 Color TCU 60 15 Health 75%
Regulation No.
3 Detergent mg/l 0,315 0,05 84,12%
492 of 2010
4 BOD mg/l 2 3,96 49,5%
5 COD mg/l 10 11,4452 Government 12,5%
regulation No
6 Hydrogen Sulfida mg/l 0,002 0,0168 16%
82 of 2001
7 TSS mg/l 177 50 71,7%
PLANNING POPULATION 10
PERIODS
Period plan in this PROJECTION
DOMESTIC PROJECTION
Regresi
water treatment Cugenang
Parameter Aritmatik Geometrik
Linear
Eksponensial Logaritmik
plant will set 20 subdistrict STD 930.78513 4446.0069 882.0657 915.980916 784.69236
PERCENTAGE
LEVEL SERVICE
Regresi
Parameter Aritmatik Geometrik Eksponensial Logaritmik
Cianjur Linear
Based on PDAM
subdistrict STD 1561.29540 5842.38334 1217.410 1242.8411 977.322648
NON-DOMESTIC PROJECTION
Education Worship Health facilities Commercial facilities
Year Industry (unit)
facilities (unit) facilities (unit) (unit) (unit)
2019
Non domestic projection use Public Works Standard Service to assist number
CLEAN WATER NEEDS
12
PROJECTION
AVERAGE DOMESTIC CLEAN WATER
NEEDS Clean Cugenan
Cugenan Cianjur Karangteng
Cianjur Water g
g Karangteng Subdistrict ah
Subdistri Needs Subdistric Total
Subdistri ah water Subdistrict
Year ct Standar t water (LPS)
ct Subdistrict needs water needs
populati d needs
populati population (LPS) (LPS)
on (l/o/d) (LPS)
on
HC PH HC PH HC PH HC PH
0.1 4.1
2020 104.,58 165,030 141,01 130 30 1.27 0.24 3.47 0.2 10.08
4 9
Based on Ditjen168,174
Cipta Karya Regulation, 0.8 area
23. is in the medium
2029 107,142 145,213 130 30the service
13.9 1.33 19,1 1.10 59.40
0 1
city category with the population less than 500,000
1.5
people. 113.9
2039 108,778 170,164 147,752 130 30 26.7 44 2.54 36.9 2.13
CLEAN WATER NEEDS 3 PERCENTAGE SERVICE RATIO4
STANDARD HOUSE CONNECTION :
HOUSE CONNECTION : 130 PUBLIC HYDRANT
l/people/day 80:20
CLEAN WATER NEEDS 13
PROJECTION
Recapitulation
Kind of Clean Water Needs
Clean Water Needs in
Clean WaterNeeds in 2039 (LPS)
2029 (LPS)
CONCEP
Coagulation,
Screening,
Alterntive Flocculation,
Prasedimentation, -
T
Config 1 Sedimentation,
Activated Carbon
RSF
DESIGN
Coagulation,
Screening,
Alternative Flocculation,
Prasedimentation, -
Config 2 Sedimentation,
Activated Carbon 3 alternatives
SSF
configuration for
Coagulation,
Alternative Screening, Activated Carbon WTP and Sludge
Flocculation,
Config 3 Prasedimentation FIlter Handling
Sedimentation,
Sludge Handling Configuration Thicekener Dewatering
Technology
Alterntive Config 1 Gravity thickener Belt Filter Press
Alternative Config 2 Gravity thickener Sludge Drying Bed
Alternative Config 3 Gravity thickener Centrifugal dewatering
ONCEPT DESIGN
These are alternative configuration
18
consideration
Analytical Hierarchy Process is used as valuation methode to
emphasize critera
Eigen
Criteria Config WTP config Sludge handling
Vector Total
Technology valuation valuation
Invest Cost 0,0571
O & M Cost 0,2643 Alternative 1 0,388773 0,409487 0,7608
O & M ease 0,18727
Removal Alternatif 2 0,312862 0,372072 0,7223
0,14526
efficiency
Sustainability 0,2655 Alternatif 3 0,298415 0,341313 0,6397
Land usage 0,0832
ONCEPT DESIGN
These are concept design for all unit
19
treatment
Technology Concept
Screen Will be placed in intake with bar screen type
Prasedimentation Will be use gravitational system and will be located in
first unit in WTP system
Coagulation Coagulation unit will utilize hydraulic jump to mix
coagullant with raw water and wil be injected powder
activated carbon
Flocculation Flocculation type will be hexaciodal with upflow
system
Sedimentation Sedimentation unit will use plate settler
Rapid Sand Filter RSF will use antrachite and sand as filter media, will
use pipe lateral as underdrain system
Post Chlorination Will build contact basin and use Ca(ClO)2
MASS BALANCE 20
CONCEPT DESIGN 21
LAYOUT
References 22