Disadvantages
10. The belts are at their maximum length when the face
is started. Any defective section can be cut out as the
belt is shortened at regular intervals.
I. Ventilation is efficient.
Development
Cutter operator - 1
Cutter operator’s assistant - 1 (support setting)
Shuttle car operators - 2
Gathering Arm Loader Operator - 1
Coal Drill Operator - 1
Utility Man (supplies vehicle) - 1
Shotfirers - 2
Electrician - 1
Mechanic - 1
(1 manshift / day included
in total number of oil and
pick man)
Deputy - 1
Overman - 1
_____
13
Development using Continuous Miners
(i) Equipment
Miner 1
Torkar 3
Belt Conveyor 1
Face exhaust fan 1
(ii) Crew
Miner Operator 1
Miner Cable Handling 1
Torkar Drivers 3
Fan attendants 2
(iii) Follow up team
Extension of belt 6
Stone dusting and dust barrier 8 in only day shift.
After the formation of pillar, their extraction is done
from one end of the panel.