EHS MANSOON PLAN

Monsoon Preparedness Plan

Project:-For All Projects


EHS MANSOON PLAN

Emergency Evacuation Plan

Please Add Your respective site


Emergency Evacuation Plan
EHS MANSOON PLAN

Inspection’s
• Weekly inspection of Tower Crane, RMC plant, Cranes, Lifting
Equipments, Concrete Pumps, Electrical Equipments.

• Regular Inspection of Excavated Pit .


• Regular Inspection of Confined space areas.
• Restriction for entry of vehicle below high tension line by
Barricading below high tension line.

• All Machinery Kept on height from ground level.


• Regular Inspection at labour camp near Permanent structure
like Retaining wall ,Compound wall, filled soil excavated area.
EHS MANSOON PLAN
Electrical Safety
 working with live electrical panels in the switch yard / sub-station
is not advisable during raining.
 Lay all power cables overhead/over the ground. Avoid power
cable joints. In case cable joints are required, provide the
standard insulations and keep the cables rigidly away from water.
 No worker should be allowed to work at un –protected area
(Electrical pole / towers , free beam / cantilever etc.) at height
during raining.
 DBs shall be protected with adequate weather protection shed
OR plastic cover to restrict entry of water.
 All body earthings of all electrical panels, DBs will be checked for
tightness and effectiveness.
 Welding operation is carry only in shed to protect from moisture
with Fire Precautionary Measures..
EHS MANSOON PLAN

Electrical Safety
 Regularly inspection of RCCB to find out they are properly
working or not.
 Regularly Earthing Resistance Value Checking .
 Check for water accumulation around electrical installation like
meter room, main distribution board, DG sheds, etc., if required
elevate the level for safer approach.
 Do not touch any installation in or near meter room if the wall is
wet.
 Reinforce all sub-distribution boards with further supports /
anchors to avoid board falling.
 Inspect installed ELCB & check earth resistance prior to
monsoon.
 Ensure all temporary DB’s are provided with MS enclosures,
grounding & continuity of earthling.
EHS MANSOON PLAN

Electrical Safety
 Provide water proof covers over all distribution & sub-
distribution boards.
 Rain protection - raincoat / umbrella, gum-boot for all
electrical personnel.
 Check all the temporary joints and make them waterproof to
the extent possible and never allow any temporary joint in
water.
 Poles installed for over head cabling - make them rigid / more
stable.
 Do not use any Halogen at site during this period.
 Avoid / arrest water leakage in all offices / buildings as this
may cause electrical faults / short-circuit in the electrical
system.
EHS MANSOON PLAN
Vehicle And Equipment
 Park all construction equipments in a stable ground & at nights.
 Check all the vehicles entering into the site, check thetyre
conditions (the tread grooves should be of minimum 1.5mm in
all the tyres. Look for sidewall cuts in tires, if so, replace them
immediately).
 Ensure proper functioning of the break system and wipers, signal
light, tail lamp and reverse horn are in working condition.
 No matter how well your vehicle is serviced, nothing substitutes
your being alert and careful while driving.
 Wet-weather driving demands gentle use of all the main
controls - steering, clutch, brake and accelerator - and a larger
allowance for errors and emergencies.
EHS MANSOON PLAN

Vehicle And Equipment

• Carry emergency equipment.


• Things like a flashlight, spanner or ropes may not be required
but it may come in handy during any eventuality.
• First and foremost: slow down! It takes longer to stop or adjust
in wet weather.
• The speed limit during the rains should be 5 km/Hr within the
site premises.
• Leave lots of space between the vehicle and man
Vehicle And Equipment
Inform the drivers about the precautions -
 Do not keep transport vehicles in low level area.
 Never over speed the trucks in rain
 Do not over load the trucks
 Secure all loads in the truck
 Do not move close to the excavated pits
 Do not raise the engine while you notice the tire slip
 Do not drive in unknown water logged areas
 Never drive the Truck, crane & hydra in the bank filled areas.
 Never operate cranes and vehicle in the unleveled area
immediately after the rain.
 The booms of all cranes shall be lowered, if the wind speed
is too high(greater than 25km/hr at nights)
EHS MANSOON PLAN
While and After the Heavy rain and the storm
 If power lines and poles are down in yard or in the site, always
treat then as if they were energized and dangerous.
 Never try to remove any electrical pole unless you are
authorized to do so. Stay away. Call the electrician and report
the location so that, repairs can be made as soon as possible.
 Never try to help some one trapped by a power line. You
endanger your own safety. Inform concern authority.
 Disconnect computers and other delicate electronic equipment.
Consider attaching surge protectors to such equipment.
 Stay away from metal fencing (metal fences could become
electrified by a downed wire. Be very careful, especially after a
storm).
 Necessary warning signs need to be displayed, near all the
water filled pits
EHS MANSOON PLAN
While and After the rain and the storm

 Ensure all the water drainages are not choked and free water is
ensured.
• All the lifting operation stopped for windy condition.
• Ensure Safe approaches for cranes, vehicles etc.
• Inspect all scaffolding materials, shuttering material, waste spoil
particular on construction site and shoring daily by the
competent person to avoid any incident on site.
• Ensure the all Excavated pit it is safe to work then allow to
worker to work inside the pit.
EHS MANSOON PLAN
Height Work

 Regularly Scaffolding Inspection.


 All Fall Protection Devices are Check Regularly.
 Stop the work in heavy rain and high wind Pressure.
 Educate /trained the people prior to start work and ensure
the same regularly.
EHS MANSOON PLAN

LABOR CAMP MONSOON PRECAUTIONS -


• Ensure regular Sewage collection and disposal at labour
camp and sites to prevent foul smell and health hazard.
• Camp area shall be fenced and security lighting be installed.
• All housing units must be of good quality and condition.
• Ensure and monitor housekeeping, hygienic condition of
labour camp & crèche by camp Boss regularly.
• Accommodation units must be cleaned on a regular basis and
all waste disposed of into segregated waste skips with doors.
• Garbage and waste food collection yard should be set away
from living area.
• Regular fogging & pest control is required to prevent from
epidemic diseases.
• Clear all water drains in and around labour camp. Provide
covering on open drains.
EHS MANSOON PLAN
• The camp shall have adequate drainage to eliminate monsoon
rains and units shall be elevated to eliminate water ingress.
• Ensure disposal of food waste & garbage on regular basis.
• Spray DDT powder in an around sanitary facilities OR increase
repellant spray from local authority to prevent from any epidemic
disease.
• Secure all loose G. I. Sheets to prevent from flying off in case of
stormy & gusty wind.
• Ensure conductive grounding is provided to G. I. Sheet partition
for effective functioning of ELCB’s.
• All temporary connections must be rooted through ELCB.
• Ensure all wires / cables are not laid on sharp edges OR through a
hole within the G. I. Sheet as to prevent damage to insulation. If
possible route through conduit pipes and support wire / cables by
suitable hook.
• Ensure all wire / cable joints are water and shock proof to prevent
from shock.
EHS MANSOON PLAN

FOOD WASTE MANAGEMENT:


• All personnel to be taken their food in allocated area. (Rest room
/canteen)
• Ensure availability of two food waste bins nearer the rest
room/canteen.
• Strictly inform to personnel to drop the waste food into the
waste food bins.
• Arrange try inform of water tank for wash the plate to avoid
water spillage on ground.
• Plates should be washed only allocated area.
• Food waste bins to be removed on regular basis to avoid
hygienic problems.

Important Health tips: EHS MANSOON PLAN
• Diseases are rampant during the monsoon.
• Guard against monsoon diseases such as influenza or dysentery.
• Make it a point to consult a doctor in case of illness.
• Protect yourself against mosquitoes. Always carry a mosquito
repellent and take care to cover yourself completely at night. Be
alert to warning signs of malaria including fever, headache, severe
chill or muscle pains.
• Contaminated food and water are a monsoon hazard. Eat only
properly cooked food, and wash fruits and vegetables thoroughly.
Be careful about the water you drink; when in doubt, stick to
bottled mineral water. Also, hot beverages such as coffee and tea
are generally safer than fruit juices, sugarcane juice or buttermilk.
• A good hot water bath is a good practice after a day spent outdoors
in the rain.
GENERAL MONSOON PRECAUTIONS – EHS MANSOON PLAN
• All temporary sheds is protect from flying away (due to high
wind velocity) by providing Load bags on shed.
• Do not keep any loose materials (GI sheets, scaffolding planks
etc.) on the top of the structure, porta cabin roof, and shed.
• While working in the rain all workers, staff have overall rain
protection by Rainy Shoes.
• All possible holes in the DG shed, labour rest room, temporary
stores and roofs of any temporary structures is clogged by using
water resistant compound.
• Pump is ready to evacuate rain fall water from the low area .
• Excavations, trenches etc. barricaded with warning tapes as well
as hard barricading to warn against potential fall.
• Maintain Proper Access.
• Backfill all minor and major excavated pits which are not
required for site execution.
EHS MANSOON PLAN
GENERAL MONSOON PRECAUTIONS –
• Keep ready few battery operated lights to meet the emergency.
• Open / clear all drains in and around project site.
• Barricade all pits & backfill unwanted pits.
• Ensure all pits are effectively shored & ensure de-watering is
done regularly.
• Ensure proper temporary approaches to site offices, stores, and
storage yards etc. if required.
• Rain protection during welding / gas cutting.
• Ensure roads and pathways are cleaned and all pit holes are
filled.
• Water logging inside the premises are to be cleaned on priority
basis.
• Scrap metal pieces are to be taken care of particularly in water
logging area.
• Sharp metal edges may cause injury to the persons passing
through this area.
GENERAL MONSOON PRECAUTIONS EHS MANSOON PLAN
• Ensure stability of scaffoldings daily before commencement of work.
• Water proof Tarpaulin should be arranged to protect material at
site.
• Proper and safe storage arrangements for fuel / oil drums.
• All PPE's and tools to be stored in a dry place.
• Adequate materials for monsoon repair work etc.
• Cover the gears, wire rope drums of cranes / material hoist by
plastic / PVC sheets.
• Antidote arrangements for poisonous insect / snake bite.
• Maintain adequate medicines at the first aid center to treat the
ailing persons.
• Undertake repellent spray from local authority to prevent from any
epidemic disease.
• Provide a safety net to avoid soil collapse,
• Frequency of pest control & fogging to be Twice in a Week .
• Inform all drivers / operators not move close to the excavated area.
• Beware of slippery road condition.
EHS MANSOON PLAN

GENERAL MONSOON PRECAUTIONS


• Frequency of sewage collection at labor camp and at sites trips to
be increased.
• Mark reflective tapes at the edge of the all excavated pits and
main access.
• Rest place for workmen during rain
• Provide lightning arrester at the highest level of site and will
ensure the all temporary shades are covered.
• Anchoring of roofs, wherever required.
• Excavation site shall be cordoned off.
• Ensure roads and pathways are cleaned and all pit holes are filled.
• Water logging inside the premises are to be cleaned on priority
basis.
EHS MANSOON PLAN

GENERAL MONSOON PRECAUTIONS

• Ensure the anemometer are workable and inspect / check


frequently which is fitted with crane and Incase in heavy wind
stop the work.
• Drinking water tank to be cleaned on weekly basis .
• Toilet and Urinal are to be cleaned on Daily Basis.
• For Dewatering will arrange as required no of Dewatering
pump / Mud pump at site ,and location which we install are
mark on monsoon logistic Lay out and also mark the dewater
line which is connected to existing storm water drain.
• Pest control methods have to be implemented on site and at
labour camp
EHS MANSOON PLAN