Sei sulla pagina 1di 99

Operation and maintenance of Hydro tunnels

13th December 2018


Kathmandu, Nepal

Waterproofing membrane under high


hydraulic head
Marco Bacchelli

CARPI TECH – info@carpitech.com


INTRODUCTION
Pressure tunnels and shafts are often
excavated in mountain areas with unfavorable
geological conditions. They are usually lined,
to provide:

• Stability and watertightness to the natural


excavation line
• Avoid water infiltration into the ground
• Minimize head losses

CARPI TECH 2
AGING AND DETERIORATION
With the exception of old tunnels excavated in rocks,
new tunnels and shafts are commonly lined with
steel, reinforced or un-reinforced concrete, and
shotcrete.
Construction of steel and concrete linings may be
expensive and time consuming, and it can be difficult
in remote areas with difficult access.
Over time, especially in presence of geological issues,
concrete and steel linings may deteriorate and water
may leak through fissures, cracks, failing joints, and
increased permeability of the concrete.
7/3/2018 CARPI TECH 3
DAMAGE AND LEAKAGE

Weld failure, severe oxidation,


pitting and panel detachment
in steel lining

Severe concrete spalling,


cracking and fissuring
due to excess of
compression and
thermal stresses in Leakage flow spilling out
concrete lining from the valley flank

7/3/2018 CARPI TECH 4


HYDRO-FRACTURING AND
SPALLING

Typical longitudinal crack due Severe spalling on the


to hydro-fracturing and lining walls and invert for excess
deformation of compressive forces.

7/3/2018 CARPI TECH 5


PRESENCE OF EXTERNAL
PRESSURE AFTER DEWATERING
AN EFFECTIVE SOLUTION

In response to the need of rehabilitating pressure tunnels and shafts, use of


geomembrane lining started more than 40 years ago.

7/3/2018 CARPI TECH 7


COVERED SOLUTION
The first installations of synthetic geomembrane in pressure tunnels were
realized in the 70’s/80’s. The waterproofing system was installed between two
layers of concrete. The first structural and the second as ballast and protection
of the plastic membrane. In other cases the membrane was used as a
secondary protection line behind the structural inner concrete ring.

7/3/2018 CARPI TECH 8


COVERED INSTALLATION
• Water pressure applied on the inner
surface
• Intimate contact between concrete support
and surrounding rock
• Inner concrete ring as ballast and
protection of the waterproofing system
• Inner concrete to be dimensioned in order
to withstand external water pressure

Geomembrane
Structural lining
Concrete Ballast/protection
Concrete

7/3/2018 CARPI TECH 9


PROs vs CONs COVERED SOLUTION
• High durability • High risks of damaging
the membrane during
• Easy installation construction of inner
concrete ring
• Effective mechanical
protection • Higher cost
• Adapt in case of • Longer construction
transport of heavy time
sediments and rocks
• Necessity of careful
• No limit of water speed management of
external negative
• Esay maintenance
pressure
procedures
GEOMEMBRANE LINING SYSTEM

The innovative concept


introduced by Carpi
consists in installing the
geomembrane in EXPOSED
POSITION, therefore in
direct contact with the
flowing water, fully
accessible (for inspection
and maintenance).

7/3/2018 CARPI TECH 11


EXPOSED INSTALLATION

• Water pressure applied on the inner


surface
• Intimate contact between concrete support
and surrounding rock
• Cracks and fissure in the concrete support
do not affect watertightness (less
reinforcement and less quality control)
• Concrete support and surrounding rock
Shotcrete Geomembrane
work together to provide stability
Concrete lining

7/3/2018 CARPI TECH 12


BENEFITS OF THE SYSTEM

The scope of the waterproofing liner is not necessarily only watertightness.


An exposed geomembrane can allow:

• Decrease the surface roughness (reduce head losses)


• Reduce the quantity of construction material and excavation
• Avoid the need of treatment works (grout injection)
• Contract the installation time
• Conform to deformation and cracks of the surrounding rock
• Protect the subgrade from deterioration

7/3/2018 CARPI TECH 13


SURFACE ROUGHNESS
Circular tunnel 4.5 m dia. for 1000 m length
Type of material Manning’s Head loss % Increase
coefficient

Geomembrane 0.011÷0.012 1.37 m -

Cast-in-place concrete 0.012÷0.015 2.06 m + 50 %

Deteriorated concrete 0.014÷0.020 3.65 m + 166 %

Shotcrete (good finishing) 0.016÷0.023 4.83 m + 253 %

7/3/2018 CARPI TECH 14


SURFACE
ROUGHNESS

CONCRETE

7/3/2018 CARPI TECH 15


WATERPROOFING LINER

The waterproofing liner provides


the impervious barrier capable to
resist, better than other
traditional liners, the settlements
and deformation of the structure.

A correct combination of
tensile strength and strain is
paramount to ensure
adequate behavior.

7/3/2018 CARPI TECH 16


WATERPROOFING LINER

Geocomposite liners, type SIBELON® CNT, made of a flexible thermoplastic


geomembrane heat-bonded during fabrication to a non-woven geotextile, provide
adequate characteristics:

• Monotone stress-strain curve (no yield point, elastic behavior)


• High flexibility, break elongation > 250% (geomembrane)
• High strength, excellent bridging capacity over cracks
• Outstanding durability > 100 years (accelerated aging tests)
• Excellent puncture resistance (geotextile moduli contribution)
• No routine maintenance

7/3/2018 CARPI TECH 17


WATERPROOFING LINER
CRACKS BRIDGING CAPACITY
Geocomposite liners, type SIBELON® CNT, were tested extensively to prove
the capacity of bridging large cracks of subgrade under high loads
1. 30 mm open space to
simulate open joint or crack

2. Geocomposite placed above


the subgrade

3. Vessel loaded with 30 bars


water pressure

4. Geocomposite bridging the


open space maintaining
watertightness

7/3/2018 CARPI TECH 19


FASTENING SYSTEM
The waterproofing liner must be fastened
to the subgrade in order to:

• Withstand drag forces and uplift


generated by the water flow
• Withstand sub-pressure (especially in
case of dewatering)
• Facilitate installation, according to the
cross-section
• Avoid formation of folds and wrinkles

7/3/2018 CARPI TECH 20


TENSIONING PROFILES

7/3/2018 CARPI TECH 21


FLAT PROFILES

7/3/2018 CARPI TECH 22


DRAINAGE SYSTEM

In exposed installations, the


waterproofing liner must be
efficiently drained to avoid back-
pressure due to high water table
and water trapped behind the
liner, which could cause uplift and
excessive stresses.
Drainage geonets installed behind
the waterproofing liner are widely
used and are proven effective.

7/3/2018 CARPI TECH 23


DRAINAGE GEONET

7/3/2018 CARPI TECH 24


DISCHARGE DEVICES

One-way relief valves and fuse valves


are adopted when no gravity
discharge point is available and as a
backup/safety devices

7/3/2018 CARPI TECH 25


DISCHARGE DEVICES

7/3/2018 CARPI TECH 26


PERIMETER SEAL
The waterproofing liner is sealed at the peripheries by
means of watertight fixations designed to resist water in
pressure.
The seal consists of batten strips + rubber gaskets,
fastened with anchor bolts and compressing the
geocomposite on the subgrade regularized with epoxy
resin.
A double perimeter seal can be recommended (especially
in deteriorated concrete subgrade) to enlengthen the
gradient and reduce risk of by-pass.

7/3/2018 CARPI TECH 27


PERIMETER SEAL

7/3/2018 CARPI TECH 28


RELEVANT EXAMPLES

•The following hand-made video illustrates recent successful applications of a


Carpi geomembrane system in pressure tunnels and shaft for pumped
storage and hydropower plants.

• REHABILITATION OF BELDEN TUNNEL – USA - 2008

• REHABILITATION OF CHOJLLA TUNNEL – BOLIVIA – 2013

• REHABILITATION OF TUNJITA SHAFT AND TUNNEL – COLOMBIA – 2017

• REHABILITATION OF HELMS HP TUNNEL – USA – 2017

7/3/2018 CARPI TECH 29


BELDEN TUNNEL
REHABILITATION OF THE WATERTIGHTNESS
CHOJLLA TUNNEL
REHABILITATION OF THE WATERTIGHTNESS
CHOJLLA TUNNEL
•Country: Bolivia
• Client: Hidroelectrica Boliviana
• Excavated in rock, total length of 3627m
• Lined with reinforced concrete
•Constant diameter of 2m, except for the last 3m
where the diameter decreases to 1.6m to connect to
the steel lined section
• Normal static pressure inside the tunnel : 5.2bar
•Exceptional maximum internal pressure 6.7bar due
to maximum surge
• Maximum water velocity 2.45 m/s
• Surface lined: 1.372,76 sq. meters
•Installation time: 20 days (Nov. 8 to Nov. 28 2011)
CHOJLLA TUNNEL
•Country: Bolivia
• Support layer (geogrid type Tenax LBO 440)
• Drainage layer (geonet type Tenax CE 750)
•PVC geocomposite waterproofing liner type
Sibelon CNT 3750 ( 2,5 mm PVC backing 500 g/m2
geotextile)
•On the last 50 m of the waterproofed section, in
the most cracked area, a forth layer of anti-
puncturing geotextile 1000 g/m2 has been placed
on the concrete ring before the supporting geogrid
• Watertight sealing upstream and downstream
•3 drainage discharge pipes long the invert,
connected with an existing drainage pipe
• 3 relieve valves on the invert
CHALLENGES

• Chojlla tunnel is located on a very remote area in the middle of


the Andes
• Hidroelectrica Boliviana took care to organize all the logistic,
including transport of materials from La Paz to the site and to the
staging area, diversion of water inside the tunnel, ventilation,
lighting and distribution system inside the tunnel, all civil works,
food, lodging and transport of Carpi crew
• Cooperation with Hidroelectrica Boliviana allowed our crew to
concentrate only on the execution of waterproofing system
• The works were completed one week before the deadline
CHOJLLA TUNNEL

Before waterproofing works: existing


cracks, water coming from the ground
CHOJLLA TUNNEL

Entrance of tunnel with ventilation to extract smoke


CHOJLLA TUNNEL

Placement of support geogrid, drainage


geonet and tensioning profile
CHOJLLA TUNNEL

Placement of extra layer of anti-puncture


1000 g/m2 geotextile on most cracked areas
CHOJLLA TUNNEL

Placement and anchorage of geocomposite panels


CHOJLLA TUNNEL

Upstream and downstream perimeter seals


CHOJLLA TUNNEL

Completed works – Survey monitoring prism


TUNJITA SHAFT AND
TUNNEL
REHABILITATION OF THE WATERTIGHTNESS
FOREWORD
• OWNER - AES CHIVOR
• MAIN CONTRACTOR (EPC) - CONINSA & RAMON SA
• DESIGNER – INTEGRAL
• LOCATION – CHIVOR COLOMBIA 100Km North of
Bogotà
ZONE OF INTERVENTION
• 61 m height surge shaft, from elevation 1601 masl
to elevation 1540 masl;
• 114 m height connection shaft, from elevation
1540 masl to elevation 1426 masl;
• Connection tunnel (137 m lenght), from the lower
elbow until the intersection with the main tunnel
61 m height surge shaft, from elevation
1601 masl to elevation 1540 masl

114 m height connection shaft, from


elevation 1540 masl to elevation 1426
masl

Connection tunnel (137 m lenght), from the


lower elbow until the intersection with the
main tunnel
WATER SPEED
• In the calculation of the fastening system of the
geomembrane sheet, Carpi has considered a
maximum water speed in the beacon of 2.4 m / s
and in the driving tunnel of 0.85 m / s, in
accordance with the indications provided by
Integral S.A.
THE INSPECTION
THE INSPECTION
CRACKS
PATTERN
THE PROBLEM
CARPI SOLUTION
CARPI SOLUTION
CARPI SOLUTION
"'.... J..,...
- - - - r . . .-

·-....

.I
.. /
.
.
-.-.--........
·. ...,..
. ···-.......
-- ..,.,.f·· .

·,.
'"'·"'
' " ·

.
f iJACION 2
•. -
· ' ' •• • •
-

·. o \ ·.,,,
I

.\

. \.
' --:!!
'• " ? ·'.. '\.;·\.'_
\ I
\.J...,
----....t : · - ·- ·

SIBEILON ' CNT 4400


1.. I GEOCOMPUESTO
,....

2.80>m
INSTALLATION OF GEONET
INSTALACION EN T UNEL
GEOCOMPOSITE INSTALLATION
INSTALACION POZO VERTICAL
TUNNEL COMPLETED
TUNNEL COMPLETED
SHAFT COMPLETED
HELMS PENSTOCK ACCESS TUNNEL
•Country: United States (California)
•Tunnel diameter : 25 feet
•Hydraulic head: 1,900 feet static - >2,500 feet dynamic
•Speed of water: 16 ft/sec ~ 3 times the pressure of any other
installation worldwide
•Type of face: concrete
•Geocomposite installation - 2017
•Surface of geomembrane installation: 20,279 sq. feet
•Installation time: 1.5 months
Helms PAT Geomembrane Design Criteria
 Spacing around tunnel circumference between profiles dictated
by geomembrane failure
– Very conservative criteria
– Dictated that the closest profile spacing was on the bottom where water could
build up and burst geomembrane
– At crown – profiles spaced closer together to insure geomembrane was
tensioned and could not sag
 Drainage capacity was defined as 60 gpm
– Essentially 1 drain valve could discharge this amount of water- 9 were installed
– ~ 1 foot of free space longitudinally between profiles for drainage
 4 states of tunnel operations analyzed – defined valve functions
– Regular operations – 99.999+% of time – want valves closed
– Dewatered/ tunnel empty – a few weeks / decade – if valves fail then
geomembrane fails but easily repaired
– Dewatering – few days / decade - if valves fail then geomembrane fails but easily
repaired
– Rewatering – few days / decade – Critical – the drains must work to insure the
geomembrane system integrity into regular operations
Installation Area 2017
0 10 .. .. ..
OriglncJI Helms Pens tock Access Tunnel Pion
s
...........
.. ...10 1'1!1 (210 tl) •
- - - - - - - - - --- - - - - - - - - - - - - o- - - - - - -
- q-- - - u ----q- - - - m----
0

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 5-f+--'"-"1

0 5 10 .. .. .. ..
Actual Helms Penstock Access Tv1111el Pion

..70 m (210 II)

("4
...z=·"·.=
.·= .",.;·;:l-.;.;-.:.-,.- - · - · - · - - - - - - - - - - - - --,.r.::r---- - - --..-:.-.i.··. ---=- - - - - - - - ; r;- -
•.
1 -
f!!-- - - - - - !!.. .:.-- - - - - - - - - - h r-
! ,..,. - - - - - - - - - - - - - - - - - - - - - - --------- -
- · ..!r
-
" " -o · ! ---------""'-··--------"------'' ··..·-----'
----------....
· ·c· _
Testing at former US Navy lab for Deep Submergence Vehicles
to 800+ meters
Drain valve and drain plate testing
(withstands pressure and flows at gpm)
Wood mock-ups of the tunnel circumference were made for
the crew to practice and prevent wrinkles developing at
tapered end pieces
EXPLANATION IN-SITU STRESSES
Stress Tot-..1 750' Water Effective
ezometersandweirs - Rectanglesdenote (psi) (poi) (psi)
•proximate plan locatkln of pressure ood flow
easuretm:ntsi color Indicates relativepressure
1d flow trends: CTt 1500 300 1200
(CTHMAX)
lue• Decreasing trend. CTl 750 300 450
(O'HMIO)
reen • Steady trend. cr> (crv) 1200 300 900

nmge · Sporadic.

l! d • Increasing trend.

by H•.klhnHovland (1976); PG&EDrawin g No. 457782 ReV. 7 [24 January 1983]; and Moiler et al. (1981)

rone(moderatejhiohl
0 80 160 320
lass, _
rout zone
-e tunnel
FEET
Tensioning and anchoring lower part of profiles being
installed
Chemical anchors and stainless
steel rods
Geocomposite
installation
,, /
L
I
Water seepage - before ~500 gpm after ~5 gpm

को ट � स एटे शन को लाि ग
ध�वाद
Operation and maintenance of Hyrdo tunnels
13 December 2018
Kathmandu, Nepal

Disclaimer

a) The speakers are presenting their own personal views and are not expressing the
view of the Foundation.

b) Images are used at the discretion of the speaker. ITACET Foundation cannot take
responsibility for any unauthorised use of images.

c) Papers and documents displayed or handed out during the Event are copyrighted.
The participants must observe and comply with all applicable law regulations
concerning the copyright.

Potrebbero piacerti anche